Data-centre rules

Data centre regulation in Poland

Our tracker lists 10 rules for building and running a data centre in Poland, national and EU, and 5 of them are in force.

Each comes with its status, who it applies to and the next date that matters. When a rule here changes, the change is logged below with its date.

10 rules5 in force

Rules that apply in Poland

National rules first, then the EU rules every member state applies. Status as on the tracker.

RuleLevelStatusApplies toNext date
Draft amendment of the Energy Efficiency Act (UC77), public disclosure of data centre energy performanceNationalGovernment draft, not adopted. Open on the legislation portal, inter-ministry agreement stage last changed 2 Oct 2026New and existing sites. Owners and operators of data centres with IT power demand above 500 kW (Directive 2023/1791 Annex VII information)Council of Ministers adoption was planned for Q3 2026; no adoption shown on 15 Oct 2026 and no new date published
Draft amendment of the Energy Law (UC121), obligation to use waste heat (as described in the Council of Ministers work list)NationalGovernment draft, not adopted. Work-list entry updated 17 Aug 2026Data centres with total rated input power above 1 MW, unless they show use of waste heat is not technically or economically feasibleCouncil of Ministers adoption planned Q4 2026
Delegated Regulation (EU) 2024/1364, reporting to the EU data centre database (applies directly, no Polish transposing rule)NationalIn force. Poland has no separate national reporting systemNew and existing sites. Data centres with IT power demand of at least 500 kW15 May each year
Act of 7 July 2023 on preparing and carrying out investments in the National Data Processing Centre (Dz.U. 2023 item 1501)NationalIn force since 17 Aug 2023State investment in the National Data Processing Centre and accompanying investments; investor is the informatisation minister or a unit it designates; not a rule for private data centresNo date published
EED reporting, Article 12 and Delegated Regulation 2024/1364EUIn forceNew and existing sites. Data centres ≥500 kW installed IT power15 May 2027, next annual report
EED waste heat, Article 26(6)EUIn forceNew and existing sites. Data centres >1 MW total rated energy inputOngoing duty
EED energy management systems, Article 11EUIn force as a Directive duty on Member States; deadline not yet reachedEnterprises, including data-centre operators, with average annual energy consumption above 85 TJ (23.6 GWh) over the previous three years, all energy carriers together11 October 2027, certified energy management system in place
EU rating scheme, delegated regulation adopted 21 Sep 2026EUAdopted, in Parliament and Council scrutinyNew and existing sites. Same ≥500 kW reporting populationIn force 20 days after Official Journal publication, if not objected to
EU minimum performance standardsEUConsultation openNot yet defined14 December 2026, consultation closes
Cloud and AI Development Act, COM(2026) 502EUProposal, with Parliament and CouncilCloud and AI infrastructure providers broadlyNo fixed date

Poland in detail

What the national rules say, with the legal texts.

Poland has set up no national reporting system for data centres. Operators with at least 500 kW of IT power demand report directly to the EU database by 15 May each year. A 2023 act on the National Data Processing Centre covers only the state's own facility. Draft UC77, an amendment of the Energy Efficiency Act, would require owners and operators above 500 kW to publish energy performance information; adoption by the Council of Ministers was planned for the third quarter of 2026 and is not yet recorded. Draft UC121, an Energy Law amendment, would oblige data centres above 1 MW to use waste heat unless not technically or economically feasible, according to the government work list.

Dates to watch

The next dates for Poland and the EU, soonest first.

Add these dates to your calendar
  1. 14 Dec 2026The EU Commission's minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database due every year
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

Verified decisions only. Absence is not evidence of low planning risk.

Area-wide rules

  1. 26 Aug 2026Dobre, Masovia Council removed a data-centre zone from the draft general planStanding

Decisions from 1 Jan 2025; statuses checked 11 Oct 2026.

What changed

Every change to these rules on the tracker, newest first.

  1. 18 Oct 2026Added to the tracker: EED energy management systems, Article 11 (In force as a Directive duty on Member States; deadline not yet reached).
  2. 15 Oct 2026Added to the tracker: Draft amendment of the Energy Efficiency Act (UC77), public disclosure of data centre energy performance (Government draft, not adopted. Open on the legislation portal, inter-ministry agreement stage last changed 2 Oct 2026).
  3. 15 Oct 2026Added to the tracker: Draft amendment of the Energy Law (UC121), obligation to use waste heat (as described in the Council of Ministers work list) (Government draft, not adopted. Work-list entry updated 17 Aug 2026).
  4. 15 Oct 2026Added to the tracker: Delegated Regulation (EU) 2024/1364, reporting to the EU data centre database (applies directly, no Polish transposing rule) (In force. Poland has no separate national reporting system).
  5. 15 Oct 2026Added to the tracker: Act of 7 July 2023 on preparing and carrying out investments in the National Data Processing Centre (Dz.U. 2023 item 1501) (In force since 17 Aug 2023).

Get an alert for Poland

We write to this list when a rule here changes status or a date moves, usually within a week of the change appearing in the log above. Nothing else, and your address is never shared.

See our privacy policy.

Questions

Which rules apply to a data centre in Poland?

Our tracker lists 10 rules for building and running a data centre in Poland, national and EU, and 5 of them are in force.

What is the next date for data centre rules in Poland?

The next date is 14 Dec 2026: the EU Commission's minimum performance standards consultation and call for evidence closes.

From the European data-centre regulation tracker, which cites the legal text for every rule. Data-centre market data for Poland.

Sources: EUR-Lex (Official Journal of the EU), European Commission, Government of Poland.