Tools

European Data Centre Pipeline: Projects Announced and Under Construction

Data-centre projects of 5 MW or more announced, in planning, permitted or under construction across the EU, the UK, Norway and Switzerland, each with its stated capacity, stage and source.

Which data-centre campuses are coming to Europe, how large are they, and how far along is each one? Every row gives the capacity in the terms its source uses, the latest public milestone and a link to where it was published. Pair it with the five-market comparison for power prices and carbon, and the siting cost tool for a specific location.

Projects tracked358
Markets30
Permitted or being built160
Latest milestoneOct 2026
  • 358 projects across 30 markets in 23 countries: 115 announced, 83 in planning, 66 permitted, 5 contractor appointed, 81 under construction, 8 structure complete.
  • By region: Western Europe 176; Nordic countries 72; Southern Europe 88; Central and Eastern Europe 22.
  • 82 projects state 200 MW or more; 42 of them are in Western Europe.
  • The largest stated figure is Campus AI, Fouju at 1,400 MW (final substation power).
  • 116 projects publish no capacity figure.
  • Capacity is quoted on the basis each source gives (IT load, campus power, grid connection), so the figures are not added together.

Projects by market

Every market also has its own page with the grid, power prices, climate, latency and rules: data-centre markets in Europe.

Frankfurt

Frankfurt: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
CyrusOne FRA7, Frankfurt WestsideCyrusOneFrankfurt am Main (Westside)81 MWIT capacity, two buildings, nine data hallsStructure complete
Topped out, February 2026Expected: First phase due in 2026 (reported February 2026)
Baxteltrade press, February 2026Checked 10 Oct 2026
Green Mountain KMW FRA-MainzGreen Mountain and Kraftwerke Mainz-Wiesbaden (Green Mountain KMW Data Center GmbH)Mainz, KMW site on the Ingelheimer Aue (Rhine bank)54 MWpower capacity, three buildingsDeveloper page also states "80 MW in 2026" without basis; 2024 press describes 54 MW as IT capacity.Structure complete
Topping-out ceremony held 7 February 2025; site listed as under construction, February 2025Expected: Ready for service Q4 2026
Green Mountaindeveloper, 2026
it-daily.nettrade press, March 2024Checked 10 Oct 2026
Data4 Hanau campusData4Hanau (former Großauheim barracks)180 MWcampus electrical capacityUnder construction
Ground broken, September 2025Expected: Campus fully completed by 2032 (developer, 2023)
Data4developer, February 2023
DCDtrade press, September 2025Checked 10 Oct 2026
firstcolo FRA7 RosbachfirstcoloRosbach vor der Höhe (Wetteraukreis), about 30 km north of Frankfurt24 MWtotal capacitycloudmagazin states 24 MW total, of which 16 MW IT load; DataCenter-Insider describes up to 24 MW as IT capacity.Under construction
Groundbreaking on 15 June 2026, after the building permit was handed over on 29 January 2026, June 2026Expected: Go-live 2027; phased build-out until end of 2028
firstcolodeveloper, March 2025
DataCenter-Insidertrade press, February 2026
cloudmagazintrade press, July 2026Checked 10 Oct 2026
Digital Realty FRA20, Digital Park FechenheimDigital RealtyFrankfurt am Main (Fechenheim)16 MWIT capacityOne building on a campus planned for 11 data centresUnder construction
Construction started, December 2025Expected: First phase in 2027 (reported)
Structure Researchtrade press, December 2025Checked 10 Oct 2026
NorthC FRA01NorthCFrankfurt am Main (Mainzer Landstraße)6 MWcapacityUnder construction
Preparatory construction works started, September 2026Expected: First phase in January 2028
Baxteltrade press, September 2026Checked 10 Oct 2026
NTT Rhein-Selz-Park campusNTT Global Data CentersNierstein (former Anderson Barracks), about 40 km from Frankfurt482 MWpower supplyPermitted
Nierstein town council adopted the development plan unanimously; building application to follow in 2026, December 2025Expected: Construction from 2027, operation in 2029
heise onlinetrade press, December 2025
DataCenter-Insidertrade press, December 2025Checked 11 Oct 2026
CloudHQ Frankfurt-Höchst campus (FRA03, FRA04, FRA05)CloudHQFrankfurt am Main (Höchst), southern edge of Industriepark Höchst276 MWIT capacity, full campus of three building blocksPermitted
Regierungspräsidium Darmstadt approved 60 emergency generators for FRA03; developer states all legal requirements for construction are met, December 2025Expected: Construction of the first section planned to start in 2026
Entwicklungsstadtpress, December 2025Checked 10 Oct 2026
Frank Cube data centreArgaman GroupBirstein (Main-Kinzig-Kreis), development plan area "Im obersten Grünnel"200 MWIT capacity, up to 200 MW ("IT-Leistung von bis zu 200 Megawatt")The source describes the site as on the edge of the Frankfurt availability zone. The council rejected a citizen petition ("Gemeinsam für Birstein") in June 2026, and the initiative has not ruled out legal action.Permitted
Development plan "Im obersten Grünnel" adopted as a bylaw on 11 June 2026 and in force after official publication on 10 July 2026, July 2026Expected: Commissioning between 2029 and 2030 (originally 2028)
DataCenter-Insidertrade press, August 2026
DataCenter-Insidertrade press, June 2026Checked 10 Oct 2026
Goodman FRA02Goodman Group with CPP InvestmentsFrankfurt (exact site not stated in source)Not disclosedSource gives only portfolio totals for four European sites (435 MW primary power, 282 MW IT load), no FRA02 figure.Permitted
Included in Goodman and CPP Investments European data centre partnership; all sites have planning approvals and power connections, January 2026Expected: Construction expected to commence at the end of June 2026 (portfolio)
W.Mediatrade press, January 2026Checked 10 Oct 2026
Kauri CAB data centre HochheimKauri CABHochheim am Main (Main-Taunus-Kreis), about 5.5 ha east of Frankfurter StraßeNot disclosedDeveloper has not published IT or grid connection capacity. An April 2026 report gives only about 40 MW of heat output for the district heating network.Permitted
Development plan procedure concluded with no objections, rezoning the plot to industrial use, August 2026Expected: First grid capacity from Amprion by 2031; second stage from 2035
DataCenter-Insidertrade press, August 2026
DataCenter-Insidertrade press, April 2026Checked 10 Oct 2026
Vantage data centre campus Im SchleidVantage Data CentersBad Vilbel (Wetteraukreis), northern edge of the town between Im Schleid and the B3160 MWmaximum power drawn from the grid ("bis zu 160 Megawatt Strom aus dem Netz")BUND said the plan would likely be challenged in court. The outcome of the 16 December 2025 council vote is not confirmed in the sources opened; hessenschau still described the project as planned in February 2026.In planning
Fifth amendment of the Im Schleid development plan scheduled for a city council vote on 16 December 2025, December 2025
Landbotepress, December 2025
Landbotepress, December 2025
hessenschau (Hessischer Rundfunk)press, February 2026Checked 10 Oct 2026
AWS data centre, former YMOS siteAmazon Web Services (AWS); acquiring company AGSF Real Estate GmbH, operating company A100 Row GmbHObertshausen (Kreis Offenbach), Industriegebiet Ost, former YMOS AG site100 MWfinal grid connection target, phased from 20 MW in 2030Stepped grid connection per source: 20 MW from 2030, 40 MW in 2031, 80 MW in 2032, 100 MW from 2033. Energienetze Offenbach states no supply contract or agreed timeline exists yet.In planning
City council passed the basic decision that formally starts a two-stage development plan procedure, in the session following the building committee meeting of 7 September 2026 (reported 8 October 2026), 2026Expected: Power ramp from 2030, 100 MW from 2033
DataCenter-Insidertrade press, October 2026Checked 10 Oct 2026
AWS data centre Kilianstädten Nord IIAmazon Web Services (AWS)Schöneck (Main-Kinzig-Kreis), Gewerbegebiet Kilianstädten Nord IINot disclosedThe municipality secured 100 MVA of power capacity for the site (stated in MVA, not MW) after an earlier data centre project by another developer was withdrawn in mid 2025. Final approval of the zoning plan is still pending per IZ.In planning
Purchase agreement for just under 7.5 ha signed with AWS on 31 July 2026; remaining payment due subject to final approval of the zoning plan, July 2026
Immobilien Zeitungtrade press, August 2026
DataCenter-Insidertrade press, November 2025Checked 10 Oct 2026
maincubes FRA04maincubesDietzenbach (Kreis Offenbach), Assar-Gabrielsson-Straße 11-1340 MWIT capacity, depending on the designThe January 2024 announcement said the site was acquired with a committed power of 60 MW and gave operation in 2027; the current developer page gives Q3 2029.Announced
Developer page, updated September 2026, lists FRA04 as in planning with a concluded grid connection contract, September 2026Expected: Ready for service Q3 2029
maincubesdeveloper, September 2026
maincubesdeveloper, January 2024Checked 10 Oct 2026
NorthC Neu-Isenburg data centreNorthCNeu-Isenburg (Kreis Offenbach), Dornhofstraße 14, about 8 km south of Frankfurt10.5 MWfull build-out across 14 modulesPhase one 4.5 MW across 1,830 sqm of white space. A December 2024 report on a second NorthC Frankfurt facility gave 1.5 MW at launch and 10.5 MW at full build-out.Announced
NorthC acquired the site from Lugman Capital for a modular data centre, February 2026Expected: First phase could be live as soon as Q1 2027
BeBeez International (republishing DatacenterDynamics)trade press, February 2026Checked 10 Oct 2026
AWS data centre Maintal-WestAmazon Web Services (AWS)Maintal (Main-Kinzig-Kreis), Gewerbegebiet Maintal-West between the A66 and Frankfurter StraßeNot disclosedAWS treats capacity as confidential; campus of two buildings of just over 200 m each on just over 10 ha.Announced
AWS presented plans at a public information event; urban development contract, development plan and public participation still to follow, May 2026Expected: Operation within three to five years
Hanauer Anzeigerpress, May 2026
DataCenter-Insidertrade press, June 2026Checked 10 Oct 2026
Google Dietzenbach data centreGoogleDietzenbach (Kreis Offenbach)Not disclosedPart of a EUR 5.5 billion German investment programme for 2026 to 2029; waste heat to feed the EVO district heating network.Announced
Google announced construction of a new data centre in Dietzenbach as part of its German investment programme, November 2025
Google Cloud Press Cornerdeveloper, November 2025
hessenschau (Hessischer Rundfunk)press, November 2025Checked 10 Oct 2026

London

London: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Ada Infrastructure Docklands campusAda Infrastructure (GLP Capital Partners)Royal Docks, London Borough of Newham210 MWcampus, three 70 MW buildingsUnder construction
Construction of the first of three 70 MW buildings began, March 2026
GLPdeveloper, June 2024
Structure Researchtrade press, March 2026Checked 11 Oct 2026
Pure DC LON01, Brent CrossPure DCBrent Cross, north London90 MWcampus totalFinal building LON01B2 is 70 MWUnder construction
Piling started on LON01B2, the campus's final build phase, September 2026Expected: Q2 2029
Techeratitrade press, September 2026Checked 10 Oct 2026
Telehouse West TwoTelehouse (KDDI)Telehouse London Docklands campus33 MWoverall building capacityUnder construction
Ground broken on the nine-storey building, October 2025Expected: set for completion in 2028
Telehousedeveloper, October 2025Checked 10 Oct 2026
Corscale Court Lane data centre campusCorscaleCourt Lane, Iver, Buckinghamshire140 MWcampus capacity across two buildings, as reported by the contractor and trade pressDedicated 140MVA substation; Corscale's own website lists the Court Lane campus at 103 MW power capacityContractor appointed
McLaren Construction appointed with Phoenix ME under a pre-construction services agreement; predevelopment enabling works scheduled from 1 July 2026, June 2026Expected: Once complete in late 2029
Construction Enquirertrade press, June 2026
McLaren Groupcontractor, 2026
Corscaledeveloper, 2026Checked 10 Oct 2026
Equinix Hertfordshire campusEquinixSouth Mimms, Hertsmere (85-acre site)250 MWcompute capacity (250+ MW)Permitted
Site acquired; plot permitted for data-centre development, October 2025
Equinixdeveloper, October 2025Checked 10 Oct 2026
Google North Weald Airfield data centreGoogleNorth Weald Airfield, Epping Forest District, Essex163 MWestimated power requirement of the siteSource text reads "163MWW", read as MWPermitted
Outline planning application approved by Epping Forest District Council planning committee, December 2025
DatacenterDynamics (republished by BeBeez)trade press, December 2025
Data Centre Reviewtrade press, December 2025Checked 10 Oct 2026
Manor Farm data centreTritax Big Box REIT (Manor Farm Propco Limited)Land at Manor Farm and land north of Wraysbury Reservoir, Poyle Road, Slough107 MWfacility capacity as stated by the developer; measure not definedPermitted
Planning consent secured after the six-week judicial review concluded; pre-let agreement in solicitors' hands, July 2026
Tritax Big Box REIT (RNS via Investegate)developer, July 2026
Slough Borough Councilauthority, June 2026Checked 10 Oct 2026
Colt DCS Hayes Digital Park, London 6 to 8Colt DCSHayes, London Borough of Hillingdon97 MWIT capacity, three new buildingsCampus total 160 MW after expansionPermitted
Approved by Hillingdon Council, November 2025Expected: Construction from mid-2026, first building early 2029
The Registertrade press, November 2025Checked 10 Oct 2026
Abbots Langley hyperscale data centreGreystoke LandLand off Bedmond Road, Abbots Langley, Three Rivers, Hertfordshire96 MWdevelopment capacity as reported84,000 sq m hyperscale campusPermitted
Planning permission granted on appeal by the Secretary of State, overturning Three Rivers District Council's refusal, May 2025
Construction Managementtrade press, May 2025
DatacenterDynamics (republished by BeBeez)trade press, May 2025Checked 10 Oct 2026
Virtus Saunderton campusVirtus Data CentresSaunderton, near High Wycombe, Buckinghamshire78 MWIT load across four data centresData Centre Review (February 2024) gave 75 MW for the four data centres and a National Grid contract for 120 MVAPermitted
Campus plan announced on an approved planning site, with building works due to start Q4 2024, February 2024Expected: ready for service by the second quarter of 2026 (as stated in February 2024)
Virtus Data Centresdeveloper, October 2026
Data Centre Reviewtrade press, February 2024Checked 10 Oct 2026
Premier Park data centrePure Data Centres and SEGRO (joint venture)Park Royal, west London72 MWpower capacityPermitted
Approved by the Old Oak and Park Royal Development Corporation planning committee, May 2026Expected: Construction expected to start in 2026
London Build Expotrade press, May 2026Checked 10 Oct 2026
Nscale Loughton AI data centreNscaleLoughton, Epping Forest District, Essex50 MWAI compute capacityExpandable to 90MW per BTW Media; Data Centre Review reports a revised proposal 50% larger than originally proposed, with no MW figure givenPermitted
Outline approval granted in 2024; after Nscale revised the plans, Loughton Town Council planning officers asked for a new planning application, with Epping Forest District Council holding the decision, March 2026Expected: construction start in Q2 2026 and operation in Q2 2027 (Nscale spokesperson, March 2026)
Data Centre Reviewtrade press, March 2026
BTW Mediatrade press, January 2025Checked 10 Oct 2026
Heathrow Estate data centreBrixton (Heathrow Estate) Ltd; operator not yet namedCranford, London Borough of Hounslow48 MWIT load (64 MW power requirement)Up to three buildings; a future operator brings the detailed scheme through reserved mattersPermitted
Approved by Hounslow Council, August 2026
Baxteltrade press, August 2026Checked 10 Oct 2026
Ark Longcross Park LP02Ark Data CentresLongcross Park, Runnymede, Surrey36 MWnew LP02 data centre buildingApproval also covers vertical extensions to existing buildings; row covers the LP02 expansion onlyPermitted
Planning approval for LP02 and expansion of existing buildings, with a GBP 807 million investment announced, June 2026
IT Brief UKtrade press, June 2026Checked 10 Oct 2026
Foxboro Business Park data centreCastleforge and Galaxy Data Centers (joint venture)Foxboro Business Park, Redhill, Reigate and Banstead, Surrey15 MWdata centre capacityPermitted
Full planning consent granted by Reigate and Banstead Borough Council planning committee, May 2026
Infrastructure Intelligence (ACE)trade press, May 2026
New Steel Constructiontrade press, May 2026Checked 10 Oct 2026
45 Maylands Avenue data centreNorthtree Investment Management45 Maylands Avenue, Hemel Hempstead, Dacorum, Hertfordshire5 MWper data hall (two halls planned)Up to 5,100 sqmPermitted
Outline planning permission granted for redevelopment of a self storage site into a data centre, August 2025
DatacenterDynamics (republished by BeBeez)trade press, August 2025
Data Centre Reviewtrade press, August 2025Checked 10 Oct 2026
Caineal Wickford AI data centreCainealNear the A127 and Old Nevendon Road, Wickford, Basildon, EssexNot disclosedReported investment GBP 1.3bnPermitted
Planning approval by Basildon Council Planning Committee; construction to start once final formalities are completed, September 2025
Infrastructure Intelligence (ACE)trade press, September 2025Checked 10 Oct 2026
CyrusOne Southall campus (former Honey Monster factory)CyrusOneBridge Road, Southall, London Borough of EalingNot disclosedMore than 52,000 sqm of floorspace across four storeysPermitted
Approved by Ealing Council planning committee on 17 July 2026, July 2026Expected: Works could start at the beginning of 2027; campus opening hoped for by 2030
Data Centre Reviewtrade press, July 2026Checked 10 Oct 2026
Equinix Wexham Road campus (former AkzoNobel paint factory)EquinixOff Wexham Road, SloughNot disclosedThree buildings; a detailed application is still requiredPermitted
Outline planning permission for a three building data centre campus approved by Slough Borough Council planning committee, November 2025
DatacenterDynamics (republished by BeBeez)trade press, December 2025Checked 10 Oct 2026
Microsoft Langley datacentreMicrosoftLangley, SloughNot disclosedSite received outline planning permission for a datacentre in 2020Permitted
Site with outline datacentre permission being cleared; community information sessions held July and September 2026, September 2026
Microsoftdeveloper, 2026Checked 10 Oct 2026
SEGRO Slough Trading Estate powered shell data centreSEGROSlough Trading Estate, SloughNot disclosedSource gives 50MVA of power when fully operational (MVA, not MW)Permitted
Pre-let agreed with an existing customer for a 30,000 sq m powered shell; planning in place via the Simplified Planning Zone, March 2026
SEGRO (RNS via Investegate)developer, March 2026Checked 10 Oct 2026
Ebbsfleet AI Data Centre CampusClearstone (applicant CSE52 Limited)Land adjacent to New Barn Road, Dartford, Kent300 MWcampus capacity as reported; basis not stated in the opened sourcePower to come through a National Grid transmission connectionIn planning
Section 35 direction issued so the campus is treated as a Nationally Significant Infrastructure Project requiring a Development Consent Order, July 2026Expected: targeting an operational start date of 2030
GOV.UK (Ministry of Housing, Communities and Local Government)authority, July 2026
W.Mediatrade press, July 2026Checked 10 Oct 2026
SDC M40 CampusSlough Holdings UK LimitedBetween the A40 Oxford Road and the M40, about 2km west of Gerrards Cross, Buckinghamshire (Planning Inspectorate project EN0110030)300 MWIT load across three buildings (c.100MW each)On-site energy centre maximum generating capacity approximately 250 to 350MWIn planning
Planning Inspectorate published a Scoping Opinion; project at pre-application stage of the Development Consent Order process, June 2026Expected: The application is expected to be submitted January 2027
Planning Inspectorate, National Infrastructure Consentingauthority, June 2026Checked 10 Oct 2026
Charlton Riverside data centreGreater London Industrial (GLi), joint venture of Patrizia and Kingston Space PropertyLand off Anchor and Hope Lane, Charlton Riverside, Royal Borough of Greenwich180 MWdevelopment total as reportedGreenwich Wire gives 100,000 sqm for the centreIn planning
Request filed with the Royal Borough of Greenwich asking whether a full Environmental Impact Assessment is needed; full application expected later, August 2026Expected: Work could start in 2028 and be finished by 2033
DatacenterDynamics (republished by BeBeez)trade press, August 2026
Greenwich Wirepress, August 2026Checked 10 Oct 2026
Project Blackwater data centre campusTritax Big Box REITBeaulieu Parkway, Beaulieu Park, Chelmsford, Essex125 MWcampus total as reportedSame source says each of the two buildings would offer 44MW; figures not reconciled in the sourceIn planning
Planning application for a two-building campus submitted; Tritax Management appointed to provide development management and technical services, June 2026
DatacenterDynamics (republished by BeBeez)trade press, June 2026Checked 10 Oct 2026
Thames Valley Park data centreFH Trustees Limited and FH Trustees 2 Limited (Mapeley Beta HL Unit Trust)Thames Valley Park, Earley, Wokingham Borough, Berkshire72 MWIT capacityPeak demand about 110MW; application documents give 49.9MW and 42.5MW for the initial fuel cell supplyIn planning
Outline application (ref 262274) validated by Wokingham Borough Council; consultation to 29 October 2026, September 2026Expected: demolition April to October 2027; main construction February 2028 to August 2031 (per application documents)
Planning Geektrade press, October 2026
Silicon UKtrade press, October 2026Checked 10 Oct 2026
Bromley green belt data centreDare DCBetween Cudham Lane North and Charmwood Lane, London Borough of Bromley50 MWdata centre capacity as reportedTwo-building campus on a ten-hectare siteIn planning
EIA screening opinion request submitted to Bromley Council; no full planning application yet, July 2026Expected: grid connection hoped for 2028
DatacenterDynamics (republished by BeBeez)trade press, July 2026Checked 10 Oct 2026
Amazon tape data centre, Hemel HempsteadAmazonHemel Hempstead, Dacorum, HertfordshireNot disclosedEstimated footprint of 1,935 sqmIn planning
Planning application lodged with Dacorum Borough Council, February 2026Expected: decision likely later in 2026
Data Centre Reviewtrade press, February 2026Checked 10 Oct 2026
Arena Essex data centre campusApplicant not named in the council noticeArena Essex and Fishing Lake, Arterial Road, Purfleet-on-Thames, ThurrockNot disclosedOutline element covers up to four data centre buildings with a total GEA of up to 130,500 sqmIn planning
Hybrid planning application 25/00573/OUT advertised by Thurrock Council, July 2025
Thurrock Councilauthority, July 2025Checked 10 Oct 2026
Denham data centre campusMulberry Commercial Developments IILand either side of Denham Court Drive, Denham, BuckinghamshireNot disclosed60,000 sqm (645,835 sq ft)In planning
Planning application submitted to Buckinghamshire Council on 1 June 2026; Denham Parish Council objected and asked for a call-in to committee, June 2026
BeBeez International (republishing DatacenterDynamics)trade press, June 2026Checked 10 Oct 2026
East Havering Data Centre CampusDigital ReefNorth Ockendon, London Borough of HaveringNot disclosedIBTimes reports a 600MVA connection via the Warley substationIn planning
Formal consultation on the East Havering Datacentre Local Development Order closed; revised plan reported as due in autumn 2026, April 2026
London Borough of Haveringauthority, April 2026
International Business Times UKpress, August 2026Checked 10 Oct 2026
Ark Elstree campus (former Mercure Hotel)Ark Data CentresFormer Mercure Hotel site, Watford (Ark's Elstree campus), Hertsmere Borough, Hertfordshire200 MWsite capacity as reportedUp to six data centre buildings reportedAnnounced
Public consultation launched ahead of a planning application to Hertsmere Borough Council, November 2025Expected: Construction could start in 2026, with the first building launching in 2029
DatacenterDynamics (republished by BeBeez)trade press, November 2025Checked 10 Oct 2026
CyrusOne LON6CyrusOneIver Heath, Buckinghamshire90 MWIT capacityAnnounced
Plans announced for a new campus; groundbreaking targeted for Q3 2026, June 2025Expected: Groundbreaking Q3 2026; first capacity early 2028
CyrusOnedeveloper, June 2025Checked 10 Oct 2026
VIRTUS LONDON19Virtus Data CentresSlough Trading Estate, Slough32.5 MWIT loadAnnounced
Development of LONDON19 announced on the Slough campus, July 2026
Intelligent CIO Europetrade press, July 2026Checked 10 Oct 2026
Kao Data Park Royal campusKao DataFormer Frogmore Industrial Estate, Park Royal, west LondonNot disclosed4.7-acre siteAnnounced
Site acquired; planning proposals to be submitted over the coming months, May 2026Expected: ready for service in 2029
Kao Datadeveloper, May 2026Checked 10 Oct 2026

Amsterdam

Amsterdam: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Pure DC Amsterdam Westpoort AMS01Pure Data Centres Group (Pure DC)Westpoort, Amsterdam (Donauweg 12)78 MWtotal site capacity, three towers each housing 26MW of data halls; site powered by 100MVA via a private substationComputable (Jan 2026) reports Microsoft is the sole tenant and that separate permits were granted for each of the three towers.Under construction
Planning permissions secured and on site private substation constructed and live; data hall development scheduled from January 2026; DutchNews reported in February 2026 that the three building data centre is being built, February 2026Expected: Data hall development from January 2026; no completion date published
Pure Data Centres Groupdeveloper, December 2025
Pure Data Centres Groupdeveloper, 2026
Computabletrade press, January 2026
DutchNewspress, February 2026Checked 10 Oct 2026
Digital Realty AMS11 (phases 3 and 4)Digital RealtyKoolhovenlaan 35-45, Schiphol-Rijk, Haarlemmermeer27 MWIT capacity of the full AMS11 facility across four phases; capacity of the remaining phases 3 and 4 not disclosedPhases 1 and 2 are operational; this row covers the remaining two phases. Completion of phases 3 and 4 in 2026 not yet confirmed in sources opened.Under construction
AMS11 opened with the first two of four phases operational; remaining phases scheduled for completion in 2026, November 2025Expected: Remaining phases scheduled for completion in 2026
W.Mediatrade press, November 2025
Digital Realtydeveloper, 2026Checked 10 Oct 2026
Iron Mountain AMS-1 expansion (new hall, Haarlem)Iron Mountain Data CentersWaarderpolder, Haarlem10 MWcapacity of the new hall built by Heijmans, as reported by Dutch IT Channel; Iron Mountain separately states an additional 10MW will be added to AMS-1Heijmans did not name the client or site; Dutch IT Channel (sources) and NH Nieuws identify Iron Mountain in the Waarderpolder. Iron Mountain gives a maximum AMS-1 buildout of 60MW.Under construction
Permits granted and construction by Heijmans under way on the new hall, contract worth EUR 96 million to Heijmans, February 2025Expected: Delivery expected October 2026
Iron Mountaindeveloper, February 2026
Dutch IT Channeltrade press, February 2025
NH Nieuwspress, February 2025Checked 10 Oct 2026
Equinix Amstel IIIEquinixAmsterdam Zuidoost (Amstel III business park)80 MWgrid connection capacity, four towersOnly the first tower starts now; TenneT substations for full capacity expected around 2036Permitted
Construction permit granted, July 2026
NL Timespress, July 2026Checked 10 Oct 2026
EdgeConneX AMS10EdgeConneXKoolhovenlaan 142, Schiphol-Rijk, HaarlemmermeerNot disclosedOmgevingsdienst Noordzeekanaalgebied allowed foundation and steel works to start early at the developer's own risk (December 2025); start of those works not confirmed in sources opened.Permitted
Omgevingsdienst Noordzeekanaalgebied, on behalf of the Province of Noord-Holland, granted the phase 1 environmental permit and phase 2 building permit for the data centre, July 2026
Provincie Noord-Holland / Omgevingsdienst Noordzeekanaalgebiedauthority, July 2026
Provincie Noord-Holland / Omgevingsdienst Noordzeekanaalgebiedauthority, July 2026
Omgevingsdienst Noordzeekanaalgebiedauthority, December 2025Checked 10 Oct 2026
EdgeConneX AMS11EdgeConneXKoolhovenlaan 1, Schiphol-Rijk, HaarlemmermeerNot disclosedPermitted
Omgevingsdienst Noordzeekanaalgebied, on behalf of the Province of Noord-Holland, granted the permit to build a data centre with office (AMS 11), June 2026
Provincie Noord-Holland / Omgevingsdienst Noordzeekanaalgebiedauthority, June 2026
Omgevingsdienst Noordzeekanaalgebiedauthority, July 2026Checked 10 Oct 2026

Paris

Paris: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Goodman PAR II A and PAR II BGoodman France (Pôle Villa Nova 1 SNC)Villeneuve-Saint-Georges, Val-de-Marne, ZA des Prés de l'Hôpital (former Signify site)200 MWproject power as stated by Saint-Quentin-en-Yvelines for the Villeneuve-Saint-Georges projectThe May 2024 MRAe opinion states a planned IT room power of 105 MW for each of the two data centresUnder construction
Listed as under construction in a 2026 Saint-Quentin-en-Yvelines planning notice; public inquiry received a favourable opinion and deconstruction was completed in 2024, September 2026Expected: MRAe (May 2024): site works planned from Q1 2025, first IT room in Q2 2026, rooms filled over three years
Saint-Quentin-en-Yvelines (document published by DCmag)authority, September 2026
MRAe Île-de-Franceauthority, May 2024
DCmagtrade press, September 2024Checked 10 Oct 2026
Dugny Digital Hub (PAR15, PAR16, PAR17)Digital RealtyDugny, Seine-Saint-Denis, former French Air Force site176 MWcampus capacity across three data centresMore than 65,000 m² of IT spaceUnder construction
Construction started in 2025; PAR15 due in 2027, 2025Expected: PAR15 in 2027; no dates published for PAR16 and PAR17
Digital Realtydeveloper, 2026Checked 10 Oct 2026
CloudHQ Paris campus, build-out beyond the first IT rooms (CDG1 remaining rooms, CDG2 and second substation)CloudHQLisses, Essonne, Léonard de Vinci business park150 MWcampus critical IT load once a second substation, still to be built, is in placeCurrent critical IT load is 74.4 MW from the first 225 kV substation; in June 2025 the first two of 24 IT rooms were reported in production and a second substation was envisaged for CDG2Under construction
CDG1 inaugurated with its first two IT rooms reported in production; campus described as under construction with Eiffage as general contractor, June 2025
DCmagtrade press, June 2025
DCmagtrade press, June 2025Checked 10 Oct 2026
Goodman data centre, Tremblay-Charles-de-GaulleGoodman FranceTremblay-en-France, Seine-Saint-Denis, ZA Tremblay-Charles-de-Gaulle105 MWplanned power of the IT rooms (MRAe); same figure given as project power by Saint-Quentin-en-YvelinesUnder construction
Listed as under construction in a 2026 Saint-Quentin-en-Yvelines planning notice, September 2026
Saint-Quentin-en-Yvelines (document published by DCmag)authority, September 2026
MRAe Île-de-Franceauthority, November 2023Checked 10 Oct 2026
Thésée Datacenter Aubergenville expansionThésée DatacenterAubergenville, Yvelines50 MWcampus, built in modulesUnder construction
Construction of the first step of the 50 MW campus announced, November 2025
Structure Researchtrade press, December 2025
Datacenter Magazinetrade press, November 2025Checked 11 Oct 2026
Colt DCS Paris 2 to 6Colt DCSVillebon-sur-Yvette and Les Ulis, Essonne40 MWIT capacity, Colt Paris 2 (first of five buildings)Colt Paris 5 is 45 MW; the five buildings bring Colt's Paris-region total to 170 MWUnder construction
Colt Paris 2 under construction, May 2025Expected: Paris 2 to 4 in 2028 to 2029, Paris 5 in 2030, Paris 6 in 2031
Solutions Numériquestrade press, May 2025Checked 10 Oct 2026
NDC Vélizy urban data centreAltarea (Nation Data Center, NDC)Vélizy-Villacoublay, Yvelines, avenue Morane-Saulnier, Inovel Parc7 MWIT capacityDecember 2025 announcement gave delivery in 2027 and commissioning from the second half of 2027; the September 2026 report gives delivery of the whole property scheme in the first half of 2028.Under construction
First stone laid for the mixed project including the data centre, September 2026Expected: Delivery of the whole property scheme planned for the first half of 2028
DCmagtrade press, September 2026
DCmagtrade press, December 2025Checked 10 Oct 2026
Campus AI, FoujuCampus AI (MGX, Bpifrance, Mistral AI, NVIDIA)Fouju, Seine-et-Marne, 40 km southeast of Paris1,400 MWfinal substation powerContractor appointed
Prefect of Seine-et-Marne approved the project after a favourable public inquiry; substation and shared works contract already awarded to Eiffage, July 2026Expected: RTE to deliver 240 MW by end 2027 and 700 MW before end 2029 (reported)
Eiffagedeveloper, June 2026
Datacenter Magazinetrade press, August 2026Checked 11 Oct 2026
CyrusOne Wissous data centre phase 2CyrusOneWissous, Essonne, Wissous-Villemoisson business zone60 MWtotal cumulative power across three phases, according to CyrusOnePhase 1 declared at 19.8 MW and in service since 2021; opponents cite 100 MW; a third phase taking the total above 50 MW would need an environmental authorisationPermitted
Versailles administrative court of appeal rejected appeals against the phase 2 ICPE registration on 2 April 2026; associations announced an appeal to the Conseil d'État, April 2026
DCmagtrade press, April 2026Checked 10 Oct 2026
Verne AI data centre campus, ZAC Paris-VillarocheVerne (controlled by Ardian)Réau, Seine-et-Marne, future ZAC Paris-Villaroche500 MWtarget capacity of the Île-de-France campus announced by Ardian and VerneFirst tranche of about 200 MW targeted for 2030. The June 2026 announcement named only Île-de-France; the October 2026 report ties the same 5 billion euro Verne project to Réau. The October report gives no MW figure.In planning
Public consultation (concertation) on the Réau site opened at a first meeting in late September 2026 and runs to 3 November 2026, September 2026Expected: Commissioning targeted around 2031 (October 2026 report); first tranche of about 200 MW by 2030 (June 2026 announcement)
DCmagtrade press, October 2026
DCmagtrade press, June 2026Checked 10 Oct 2026
Goodman digital campus, former Stellantis siteGoodman FranceTrappes, ZA Trappes-Élancourt, Saint-Quentin-en-Yvelines, Yvelines300 MWtotal power sought for the campus (puissance totale recherchée)Two or three main buildings plus substation; about 33,928 m² of server rooms per the noticeIn planning
Consultation on the PLUi change (déclaration de projet) for the campus closed on 1 September 2026; Goodman acquired the land for 42 million euros; public inquiry, permits and grid decisions to follow, September 2026
DCmagtrade press, September 2026
Saint-Quentin-en-Yvelines (document published by DCmag)authority, September 2026Checked 10 Oct 2026
Data4 PAR3 campusData4 (DATA 4 NOZAY SAS)Nozay, Essonne, former Nokia Paris-Saclay site along the route de Villejust250 MWenvisaged grid connection powerIT power per building: DC01 75 MW IT, DC02 37.5 MW IT, DC03 15 MW IT. MRAe notes about 100 MW of the connection would not be used by the project. Demolition of the Nokia buildings took place between August 2024 and May 2025.In planning
MRAe Île-de-France opinion on the environmental authorisation, two building permits and the grid connection public utility procedure, issued during public consultation, October 2025Expected: Progressive commissioning between end 2027 and end 2030
MRAe Île-de-Franceauthority, October 2025Checked 10 Oct 2026
Data Hills data centre, former Citroën plantSNC Data HillsAulnay-sous-Bois, Seine-Saint-Denis, boulevard André Citroën240 MWplanned power of the IT roomsThree IT buildings; backup generators total about 240 MWIn planning
MRAe Île-de-France opinion issued on the building permit and ICPE environmental authorisation, February 2025Expected: Site works planned to start end 2025 or early 2026, in four phases running to 2040
MRAe Île-de-Franceauthority, February 2025Checked 10 Oct 2026
Icade hyperscale data centre, Rungis business parkIcadeRungis, Val-de-Marne, rue des Solets130 MWmaximum power via RTE connection (full site, phase 2)First tranche of about 15 to 20 MW via Enedis in 2028; MRAe cites 84 MW IT of the 130 MWIn planning
MRAe Île-de-France opinion on the environmental authorisation issued during parallel electronic public consultation, May 2025Expected: Shell and first tranche in 2028; full site in 2032
MRAe Île-de-Franceauthority, May 2025
DCmagtrade press, April 2025Checked 10 Oct 2026
Data Village Paris-Essonne, second phase (data centres B and C)NTT (project company LCP FR DC1, acquired from Logistics Capital Partners)Le Coudray-Montceaux and Corbeil-Essonnes, Essonne, former Altis Semiconductor site125 MWtotal final installed power of the three data centre campusData centre A was authorised by the Essonne prefect on 28 October 2022 and was under construction; this row covers data centres B and C. NTT gave 84 MW of critical IT load across the three data centres (DCmag, February 2024)In planning
MRAe Île-de-France opinion on the second phase (permit modifications and ICPE/IOTA environmental authorisation), May 2025Expected: Works on data centres B and C from 2025 to 2030
MRAe Île-de-Franceauthority, May 2025
DCmagtrade press, February 2024Checked 10 Oct 2026
Equinix PA15xEquinix (EQUINIX Hyperscale 2 (PA15) SAS)Meudon, Hauts-de-Seine, next to PA13x80 MWgrid connection power20 IT rooms; two 225 kV underground connectionsIn planning
MRAe Île-de-France opinion on the ICPE environmental authorisation and building permit application, November 2025Expected: First phase end 2029, second phase end 2035
MRAe Île-de-Franceauthority, November 2025Checked 10 Oct 2026
Segro data centre, Petits Carreaux zoneSegro (Segro Parc des Petits Carreaux SAS)Bonneuil-sur-Marne and Sucy-en-Brie, Val-de-Marne, Petits Carreaux business zone70 MWgrid connection powerIn July 2026 Segro and Pure Data Centres announced a joint venture for a 48 MW IT data centre in Paris; DCmag reports the site will be either Le Bourget or the Petits Carreaux parkIn planning
MRAe Île-de-France opinion on the environmental authorisation, issued during parallel public consultation, April 2025
MRAe Île-de-Franceauthority, April 2025
DCmagtrade press, July 2026Checked 10 Oct 2026
Equinix PA16Equinix France SASArgenteuil, Val-d'Oise, Val d'Argent industrial zone, next to PA12x55 MWpower required by the project (grid connection estimated at about 55 MW)The grid connection request on file was for 240 MW; Equinix said it would revise it to the power needed for PA16In planning
MRAe Île-de-France opinion on the environmental authorisation and building permit application, issued during public consultation, April 2025Expected: Commissioning planned end 2029, ramp up to 2035
MRAe Île-de-Franceauthority, April 2025Checked 10 Oct 2026
Opcore DC5 extensionOpcoreSaint-Ouen-l'Aumône, Val-d'Oise, Vert Galant industrial zoneNot disclosedIT capacity not stated. The extension raises backup generator nominal thermal power from about 49.5 MW to 71.9 MW, which is not an IT or grid figure.In planning
MRAe Île-de-France opinion on the environmental authorisation for the extension (four additional IT rooms), January 2026
MRAe Île-de-Franceauthority, January 2026Checked 10 Oct 2026
Opcore data centre at the EDF Montereau Vallée de la Seine siteOpcore (site selected by EDF)La Grande-Paroisse and Vernou-la-Celle-sur-Seine, Seine-et-MarneNot disclosedSite is one of the EDF sites eligible for the RTE fast track schemeAnnounced
EDF selected Opcore to build and operate the future data centre, August 2025
DCmagtrade press, August 2025Checked 10 Oct 2026

Dublin

Dublin: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Digital Realty DUB4Digital RealtyGrange Castle Business Park, Clondalkin, Dublin 22 (South Dublin)9 MWfacility capacityBuilding constructed but not in service after grid connection was denied.Structure complete
Digital Realty said it will partner with an energy company to build its own gas power plant for the completed but unconnected DUB4 building, following the July 2025 private wires policy, July 2025
BeBeez (republishing DCD)trade press, July 2025Checked 10 Oct 2026
Equinix DB7xEquinixBlanchardstown, Dublin 15 (Fingal)Not disclosedThe release gives 1,322 sq m and an anticipated $78 million investment in the facility, plus $14 million for a retail IBX buildout. It requires no additional grid power and uses power already allocated to an existing Equinix site.Under construction
Equinix announced construction had begun on DB7x next to its existing Blanchardstown data centres, March 2026Expected: Retail capacity available to enterprises from early 2028
Equinixdeveloper, March 2026Checked 10 Oct 2026
AWS Cruiserath Road campus, Data Centres E, F and GAmazon Web Services (applicant Universal Developers LLC)Cruiserath Road, Mulhuddart, Dublin 15 (Fingal)73 MWcombined power load of the three data centresPermitted
An Coimisiún Pleanála granted permission for three data centres after third-party appeals against Fingal County Council's September 2023 grant, December 2025
The Irish Timespress, December 2025
BreakingNews.iepress, December 2025Checked 10 Oct 2026
CyrusOne Grange Castle South, Building B (permitted data centre development)CyrusOne (CyrusOne Irish Datacentres Holdings Ltd.)Grange Castle South Business Park, Baldonnel, Dublin 22 (South Dublin)Not disclosedPermission SD18A/0134 (ABP-302813-18) as amended by SD20A/0295. The decision lists Building A items as retentions and modifications to Building B Data Centre as new works; no MW figure is given.Permitted
South Dublin County Council granted an extension of duration of amendment permission SD20A/0295, which covers new works including Building B Data Centre, May 2026
South Dublin County Councilauthority, May 2026Checked 10 Oct 2026
EdgeConneX Ballymakaily data centresEdgeConneX Ireland LimitedBallymakaily, west of Newcastle Road (R120), Lucan, Co. Dublin (South Dublin)Not disclosedTwo adjoined single storey data centres with 24 standby generators; no MW figure published.Permitted
An Coimisiún Pleanála granted permission with conditions on appeal, overturning South Dublin County Council's July 2023 refusal (SD22A/0333), July 2025
An Coimisiún Pleanálaauthority, July 2025
TheJournal.iepress, August 2025Checked 10 Oct 2026
Energia Huntstown data centresEnergia Group (Microsoft named as partner)Huntstown, north Dublin (Fingal), beside Huntstown power stationsNot disclosedThe 900MW in the source refers to the wind and solar supply, not the data centre.Permitted
An Bord Pleanála granted permission, with a substation, after appeals against Fingal County Council's April 2022 approval, March 2025
The Irish Timespress, March 2025Checked 10 Oct 2026
Google Grange Castle, third buildingGoogleGrange Castle Business Park, South DublinNot disclosed72,400 m² buildingConditions include evidence of power purchase agreements before development beginsPermitted
Approved on appeal by An Coimisiún Pleanála, overturning the council's refusal, October 2026
W.Mediatrade press, October 2026Checked 10 Oct 2026

Austria

Austria: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Google data centre KronstorfGoogleKronstorf, Upper AustriaNot disclosedheise describes the site as about 50 hectaresUnder construction
Groundbreaking for Google's first data centre in Austria, April 2026
Der Standardpress, April 2026
heise onlinetrade press, September 2026Checked 10 Oct 2026
Microsoft Cloud Region Austria East, next expansion stageMicrosoftGreater ViennaNot disclosedregion with three availability zones in Greater Vienna opened about one year before the source; the row covers the next expansion stage onlyUnder construction
Microsoft reports the next expansion stage of the Austria East region nearing completion, one year after the region's launch, July 2026
Microsoft Pulse Austriadeveloper, July 2026Checked 10 Oct 2026

Belgium

Belgium: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Datacenter United Oostkamp expansionDatacenter UnitedOostkamp (Bruges area), West FlandersNot disclosedExpansion of an existing site with additional technical rooms and cooling upgrades; no MW published.Under construction
Developer roadmap lists expansion works in progress in Q3 2026, 2026Expected: New capacity commissioned Q4 2026
Datacenter Uniteddeveloper, 2026Checked 10 Oct 2026
Google Farciennes data centre campus (Ecopole)GoogleEcopole business park, Farciennes, Aiseau-Presles and Sambreville, Hainaut, WalloniaNot disclosedNo MW published by Google or in the opened press reports; permit covers three data centre buildings.Under construction
Walloon minister for territorial planning refused Google a permit to pump water from the Sambre to cool the planned data centre; Google can still appeal. First building reported under construction in October 2025, August 2026Expected: First building to open in spring 2026 (as stated in October 2025); second building afterwards at Aiseau-Presles
Googledeveloper, 2026
Télésambrepress, October 2025
DH Les Sports+ (dhnet.be)press, April 2024
DCmagtrade press, February 2024
DCmagtrade press, August 2026Checked 10 Oct 2026
Google Feluy-Écaussinnes data centreGoogleFeluy-Écaussinnes industrial zone, Hainaut, WalloniaNot disclosedReport mentions only a temporary medium-voltage connection of 25 MVA offered by Ores pending Elia high-voltage capacity; this is not the project's stated capacity.Permitted
Google reported to have obtained a permit to build a data centre on a site of about 36 hectares; high-voltage grid connection reported as not immediately available, January 2026Expected: Operational by 2029, as reported
DCmagtrade press, January 2026Checked 10 Oct 2026
Kevlinx BRU01 campus expansion (phases after phase 1)Kevlinx Data CentersGalilei site, Neder-Over-Heembeek, Brussels65 MWlong-term campus potential (whole campus, including the live 16 MW phase 1)Phase 1 of 16 MW IT capacity is live (16 MW powered shell, of which 4 MW fully fitted out per the developer); source gives an expansion path toward 32 MW and a long-term campus potential of 65 MW. Row covers the phases beyond phase 1; no MW figure is published for those phases alone.Announced
BRU01 phase 1 (16 MW IT) declared live, with an expansion path toward 32 MW and 65 MW campus potential; citydev.brussels granted a long-term land lease for the 2.5 hectare campus in November 2025, 2026
Kevlinx Data Centersdeveloper, 2026
Kevlinx Data Centersdeveloper, November 2025Checked 10 Oct 2026
Datacenter United new Ghent data centreDatacenter UnitedGhent, East FlandersNot disclosedAnnounced
Developer roadmap lists project planning and site preparation for a new Ghent data centre in 2026, 2026Expected: Construction 2026 to 2027; commissioning and capacity availability after 2027
Datacenter Uniteddeveloper, 2026Checked 10 Oct 2026
Google Saint-Ghislain campus expansionGoogleSaint-Ghislain, Hainaut, WalloniaNot disclosedPart of a EUR 5 billion two-year Belgian investment; no MW or building count published.Announced
Google announced an additional EUR 5 billion investment in Belgium over two years, including expansions of its Saint-Ghislain data centre campuses and 300 full-time jobs, October 2025Expected: Investment over the next two years (by 2027 per DCmag)
Googledeveloper, October 2025
DCmagtrade press, October 2025Checked 10 Oct 2026

France

France: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Digital Realty MRS5Digital Realty (main works by Groupe GSE)Grand Port Maritime de Marseille, Marseille, Bouches-du-Rhône22 MWtarget capacityUnder construction
Under construction by Groupe GSE; technical synthesis mission completed January 2026, July 2026Expected: Commissioning planned December 2026
DCmagtrade press, July 2026
DCmagtrade press, January 2025Checked 10 Oct 2026
Alpilink Cloud data center, Saint-Martin-d'HèresAlpilink CloudSaint-Martin-d'Hères, Isère, Grenoble areaNot disclosedReplaces Alpilink's Seyssinet-Pariset site.Under construction
Data center under construction, June 2026Expected: Operational summer 2027
DCmagtrade press, June 2026Checked 10 Oct 2026
DC Max AI data center, DardillyDC Max with Phoenix GroupDardilly, Métropole de Lyon, Rhône18 MWAI capacityPermitted
Building permit signed January 2025; construction reported to start end of September 2026 (start not yet confirmed), June 2026Expected: Commissioning between Q4 2027 and Q1 2028
DCmagtrade press, June 2026
DCmagtrade press, May 2026Checked 10 Oct 2026
Digital Realty MRS6Digital RealtyZAC des Chabauds, Bouc-Bel-Air, Bouches-du-Rhône (former Décathlon logistics warehouse)50 MWinitial capacitySupply via a new RTE 225 kV underground line.In planning
Favourable municipal council opinion after public inquiry on the ICPE authorisation and building permit, November 2025Expected: Building permit expected 2026; production in about two years, subject to prefectoral decisions and grid connection
DCmagtrade press, November 2025Checked 10 Oct 2026
Goodman Brebières-Corbehem data center campusGoodman (operator not confirmed)Brebières and Corbehem, Pas-de-Calais, Arras area, former Stora Enso plant siteNot disclosedNo capacity published. RTE is to install a 225 kV substation at Noyelles-sous-Bellonne, a few kilometres from the site.In planning
Goodman reported to have filed an application for a four-building campus on the 23 hectare former Stora Enso site, August 2026Expected: Campus to take shape from 2030
DCmagtrade press, August 2026Checked 10 Oct 2026
Microsoft Alsace data center campusMicrosoftPetit-Landau and Hombourg, Haut-Rhin, AlsaceNot disclosedSource gives only estimated annual consumption of about 1,500 GWh, not a capacity figure.In planning
Public inquiry closed with a favourable commissioner opinion; Haut-Rhin prefect decision expected October 2026, August 2026Expected: Construction start 2027; progressive commissioning 2029
DCmagtrade press, September 2026
DCmagtrade press, March 2026Checked 10 Oct 2026
SEGRO logistics platform with data center, Saint-AndréSEGROSaint-André, 16th arrondissement, MarseilleNot disclosedIn planning
Public inquiry commissioner issued three favourable opinions, April 2025
DCmagtrade press, April 2025Checked 10 Oct 2026
Telehouse campus, ZAC des SybillesTelehouseZAC des Sybilles, Les Pennes-Mirabeau, Bouches-du-RhôneNot disclosedNo MW given for the eight-building campus; the same article cites a separate Telehouse plan of 50 MW near Marseille for 2027 without linking it to this site.In planning
Prefect decision on the project still pending amid local opposition; building permit application filed 24 May was under review as of September 2025, March 2026
DCmagtrade press, September 2025
DCmagtrade press, March 2026Checked 10 Oct 2026
Bosquel AI data center campusJoint venture of SoftBank Group and Sesterce (majority owned by SoftBank Group)Bosquel, Somme (Communauté de communes Somme Sud-Ouest), Hauts-de-France1,000 MWcampus capacity as announced (source states 1 GW); basis not specifiedSource states 1 GW. Fluidstack's earlier 1 GW plan for Bosquel was reported abandoned in March 2026 (DCmag citing Bloomberg).Announced
Joint venture selected to develop and operate the campus after a call for expressions of interest by the Communauté de communes Somme Sud-Ouest, announced at Choose France, May 2026Expected: Part of a 3.1 GW first phase across Dunkirk (Loon-Plage), Bosquel and Bouchain planned by 2031
SoftBank Group Corp.developer, May 2026
DCmagtrade press, June 2026
DCmagtrade press, September 2026
DCmagtrade press, March 2026Checked 10 Oct 2026
Brookfield Cambrai AI data centerBrookfieldCambrai, Nord1,000 MWmaximum capacity (source states 1 gigawatt)May 2025 report gives a range of 300 MW to 1 GW; no permit or construction start found.Announced
Cited at Choose France 2026 as a focus of Brookfield's increased AI infrastructure investment in France (EUR 30 billion), June 2026
DCmagtrade press, February 2025
DCmagtrade press, May 2025
DCmagtrade press, June 2026Checked 10 Oct 2026
Data4 Escaudain campusData4 (consortium with Brookfield and BT Immo)Escaudain, Nord, Parc des Soufflantes (former Usinor site), Communauté d'agglomération de la Porte du Hainaut700 MWcampus power at full build; RTE capacity of 700 MW cited for the siteAnnounced
Data4 confirmed launch of the campus after feasibility studies, under the government and RTE fast track procedure, June 2026Expected: Works planned from 2026 per the Choose France 2026 list; described as France's largest data center in 2030
DCmagtrade press, June 2026
DCmagtrade press, December 2025
DCmagtrade press, June 2026Checked 10 Oct 2026
Altarea and Vantage Bordeaux campusAltarea and Vantage Data CentersNear Bordeaux, Gironde (commune not published), on land owned by Altarea400 MWgrid connection secured with the transmission operatorNo IT capacity published.Announced
Partnership signed to develop an AI and cloud data center campus on Altarea land with a secured 400 MW connection, February 2026
DCmagtrade press, February 2026Checked 10 Oct 2026
Bouchain data center on former EDF thermal plant siteSoftBank Group (selected by EDF, the landowner, as preferred bidder)Bouchain, Nord, former Bouchain thermal power plant site400 MWdata center capacity as stated in the EDF preferred bidder announcementAnnounced
EDF named SoftBank Group preferred bidder number 1 for the site; due diligence and a construction lease promise to follow, with the definitive lease once authorisations are obtained, May 2026Expected: Part of a 3.1 GW first phase across Dunkirk (Loon-Plage), Bosquel and Bouchain planned by 2031
DCmagtrade press, June 2026
SoftBank Group Corp.developer, May 2026Checked 10 Oct 2026
Eclairion Loire-sur-Rhône data centerEclairion (selected by EDF)Loire-sur-Rhône, Rhône, former thermal power plant site south of Lyon350 MWelectrical capacity (up to)Announced
EDF selected Eclairion for a 14-hectare plot of the former plant site, subject to administrative authorisations and building permit, May 2026Expected: Potential start of operations from 2028
DCmagtrade press, June 2026Checked 10 Oct 2026
Béthune AI data center (former Bridgestone site)Azur Datacenter (host and funder) for NebiusBéthune, Pas-de-Calais, former Bridgestone industrial site240 MWfull capacity; first phase 120 MWAnnounced
Nebius listed at Choose France with more than EUR 8 billion to convert the former Bridgestone site into a compute centre, June 2026Expected: 120 MW in production from end 2026; full 240 MW at end 2027
DCmagtrade press, February 2026
DCmagtrade press, June 2026Checked 10 Oct 2026
ÆTHER AI gigafactory (FR-SXB1 and FR-SXB2)ÆTHER Infrastructure consortium led by 2CRSiTwo industrial sites in the Strasbourg area, Bas-Rhin42 MWinitial cumulative electrical powerAbout 40 MW more targeted within twelve months; long-term ambition above 400 MW. Linked to the EU AI Gigafactories call. 2CRSi states it will not carry the capital, real estate or energy of the project.Announced
Project detailed with FR-SXB1 service in 2027 conditional on site acquisition before end October 2026, August 2026Expected: FR-SXB1 2027 if acquisition closes by end October 2026; FR-SXB2 a few months later if acquired by end December 2026
DCmagtrade press, August 2026Checked 10 Oct 2026
Azur Datacenter Lyon 01Azur DatacenterMeyzieu industrial zone, Métropole de Lyon, Rhône15 MWstated size of the high density data center; source does not specify IT load or grid connectionIndustrial premises of 4,660 m² on a 12,500 m² plot acquired by Azur Datacenter (January 2026 report).Announced
Full EUR 30 million financing finalised; industrial premises acquired in January 2026 with works due to start, March 2026Expected: Operational "in the coming months" per January 2026 report; no date given
DCmagtrade press, March 2026
DCmagtrade press, January 2026Checked 10 Oct 2026
DataOne AI data center, former Hewlett-Packard siteDataOneRue Raymond-Chanas, Eybens, Isère, Grenoble Alpes Métropole15 MWfirst phase electrical power as reported in earlier publications, extensible to several hundred MWSite acquired from DXC Technology, which inherited the former Hewlett-Packard installations.Announced
Town of Eybens and Grenoble Alpes Métropole scheduled a public meeting on the project for 8 January 2026, December 2025
DCmagtrade press, December 2025Checked 10 Oct 2026
Azur Datacenter Champagnier project (former HRS headquarters)Azur DatacenterChampagnier, Isère, Grenoble Alpes MétropoleNot disclosedInvestment of EUR 360 million stated; no MW published for this site.Announced
Sale promise for the 14,100 m² former HRS site signed 7 August 2026; building permit and ICPE steps still required, August 2026Expected: Site installation could begin end 2026; commissioning planned end 2026 per source
DCmagtrade press, August 2026Checked 10 Oct 2026
Eclairion La Maxe data centerEclairionLa Maxe, Moselle, EDF siteNot disclosedEUR 2 billion announced jointly for La Maxe and Richemont.Announced
Announced at Choose France as one of two new Moselle data centers on EDF call for interest sites, November 2025Expected: Within Eclairion's four-year EUR 2.5 billion plan
DCmagtrade press, November 2025
DCmagtrade press, March 2025Checked 10 Oct 2026
Eclairion Richemont data centerEclairionRichemont, Moselle, EDF siteNot disclosedEUR 2 billion announced jointly for La Maxe and Richemont.Announced
Announced at Choose France as one of two new Moselle data centers on EDF call for interest sites, November 2025Expected: Within Eclairion's four-year EUR 2.5 billion plan
DCmagtrade press, November 2025
DCmagtrade press, March 2025Checked 10 Oct 2026
Moji 2 data center, Bron-ParillyMojiZAC Bron-Parilly, Bron, Métropole de LyonNot disclosed1,000 m² data center on a 3,000 m² plot.Announced
Métropole de Lyon council approved an exclusivity agreement with the operator group including Moji after a call for projects, February 2026Expected: Two-year construction, commissioning in 2028
DCmagtrade press, February 2026Checked 10 Oct 2026
SoftBank Dunkirk AI data center siteSoftBank Group (with SB Energy; Schneider Electric industrial partner)Loon-Plage, Dunkirk, NordNot disclosedNo per-site figure published; Dunkirk (Loon-Plage), Bosquel and Bouchain together form a 3.1 GW first phase.Announced
Named as one of three first-phase SoftBank AI data center sites in France at Choose France, with an industrial cluster with Schneider Electric planned at the Dunkirk site, May 2026Expected: First phase enters service in stages until 2031
SoftBank Group Corp.developer, May 2026
DCmagtrade press, May 2026Checked 10 Oct 2026

Germany

Germany: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
VIRTUS Wustermark CampusVIRTUS Data Centres (ST Telemedia Global Data Centres)Wustermark, Havelland, Brandenburg (about 12 km from the Berlin city limits)204 MWcampus capacity as stated on the developer's pageThe same developer page carries a press release headline giving 300MW and EUR 3BN; DCD (June 2026) gives an initial capacity of 300MW and a 500MW substation with dual 380kV connection to the 50Hertz network.Under construction
Two 185MVA super grid transformers installed for the campus substation, reported one month after groundbreaking, June 2026
VIRTUS Data Centresdeveloper, 2026
BeBeez International (DCD)trade press, June 2026Checked 10 Oct 2026
Schwarz Digits Datacenter Lübbenau (STACKIT)Schwarz Digits (Schwarz Group); operated by STACKITLübbenau/Spreewald, Oberspreewald-Lausitz, Brandenburg (former power plant site)200 MWinitial connection capacity (Anschlussleistung), stated as about 200 MWSource says "rund 200 Megawatt" initially, expandable in two construction phases; EUR 11 billion total investment.Under construction
Symbolic groundbreaking held with the Federal Digital Minister, November 2025Expected: First construction phase of three modules to be completed by end of 2027
Silicon Saxonypress, November 2025
ChannelPartnertrade press, November 2025Checked 10 Oct 2026
maincubes BER02 campus (mainHub Berlin)maincubesNauen, Havelland, Brandenburg200 MWgrid connection agreement with E.DISRelease states the campus will offer up to 200 MW, able to grow to over 400 MW; developer site lists BER02 at 144 to 186 MW depending on design.Under construction
Zoning plan legally binding (2 July 2025) and 200 MW grid connection agreement signed; developer now lists BER02 under construction, August 2025Expected: Ready for service Q1/2028 per developer description (summary box shows Q3/2028)
maincubesdeveloper, August 2025
maincubesdeveloper, 2026
Entwicklungsstadt Berlinpress, August 2025Checked 10 Oct 2026
VIRTUS Marienpark Campus (BERLIN1 to BERLIN4)VIRTUS Data Centres (ST Telemedia Global Data Centres)Berlin, Marienpark business park (Tempelhof-Schöneberg)62.6 MWIT load across four buildings, per developer pageTrade press at groundbreaking (June 2025) stated four 14.4MW buildings totalling 57.6MW of IT load at full build-out.Under construction
Groundbreaking on the four-building campus in the Marienpark business park, June 2025
VIRTUS Data Centresdeveloper, 2026
BeBeez International (DCD)trade press, June 2025Checked 10 Oct 2026
Microsoft data centre Bergheim (Rhenish mining area cluster)MicrosoftBergheim, Rhein-Erft-Kreis, North Rhine-WestphaliaNot disclosedZukunftsagentur Rheinisches Revier cites an investment of EUR 3.2 billion for the planned data centres in Bergheim, Bedburg and Elsdorf; no MW published per site.Under construction
Groundbreaking for the first data centre of the regional cluster after the building permit was granted, March 2026
Microsoft Source EMEAdeveloper, March 2026
Zukunftsagentur Rheinisches Revierauthority, March 2026Checked 10 Oct 2026
NTT Global Data Centers Berlin data centre (HOCHTIEF contract)NTT Global Data CentersBerlin (site not named in the contractor release)36 MWfacility capacity stated in the main contractor's releaseRelease describes a three storey 36 MW data centre and a four storey office building; the site is not named.Contractor appointed
HOCHTIEF awarded the construction contract, worth several hundred million euros, delivered with Turner (Dornan), July 2026Expected: Construction start planned summer 2026; first data halls 2028; full completion 2029
HOCHTIEFcontractor, July 2026
Grupo ACScontractor, July 2026Checked 10 Oct 2026
Microsoft data centre Bedburg (Rhenish mining area cluster)MicrosoftBedburg, Rhein-Erft-Kreis, North Rhine-WestphaliaNot disclosedPart of the EUR 3.2 billion Rhenish mining area programme; no MW published for this site.Permitted
Building permit officially granted; the mayor said construction will begin shortly, March 2026
Microsoft Source EMEAdeveloper, March 2026Checked 10 Oct 2026
Gdd data centre Schladen-WerlaGdd Green Datacenter DevelopmentSchladen-Werla, Landkreis Wolfenbüttel, Lower Saxony200 MWgrid connection capacity (Anschlussleistung), stated as about 200 MWIn planning
Grid operator confirmed reservation of the planned power capacity, following the municipality's unanimous resolution in April 2026 to start the development plan, September 2026Expected: First expansion stages from 2030, at the latest 2031
DataCenter-Insidertrade press, September 2026Checked 10 Oct 2026
Microsoft data centre Elsdorf (Rhenish mining area cluster)MicrosoftElsdorf, Rhein-Erft-Kreis, North Rhine-WestphaliaNot disclosedIn planning
Named by Microsoft as a cluster site; reported in July 2026 as still awaiting approval while Bergheim and Bedburg hold permits, July 2026
Microsoft Source EMEAdeveloper, March 2026
connect professional (dpa)trade press, July 2026Checked 10 Oct 2026
Project Jupiter hyperscale data centreWBS Power and Prime Capital (joint venture)Former military airfield in Brandenburg; Entwicklungsstadt places Project Jupiter in Finsterwalde, Elbe-Elster500 MWplanned capacity ("up to 500 MW")Co-located with a 500 MW / 2,000 MWh battery and up to 150 MWp solar sharing one 50Hertz 380 kV connection. The release gives a construction start of late 2026 or early 2027 for the battery and solar project, not for the data centre.Announced
Joint venture formed to develop a hyperscale data centre on the Project Jupiter site; sale to Prime Capital subject to ready-to-build status, December 2025
WBS Power / Prime Capital (press release)developer, December 2025
Entwicklungsstadt Berlinpress, September 2026Checked 10 Oct 2026
Telis Energie data centre campus MehrumTelis Energie DeutschlandNorth of Mehrum (Gemeinde Hohenhameln, Landkreis Peine), Lower Saxony500 MWcampus capacity as reported ("500MW data center campus")Six buildings on about 380,000 sqm; investment of at least EUR 1 billion.Announced
Plans presented; project in initial planning stages with municipal approval not yet received, April 2026Expected: Construction to begin in 2028 and last up to two years
BeBeez International (DCD)trade press, April 2026Checked 10 Oct 2026
Blue Future technology area data centreFAB (land developer, Leipzig)Eisenach, Thuringia (about 86 hectares between Stockhausen and Hötzelsroda)300 MWgrid capacity the project would take from the expanded local substation, per city FAQCity project page states the data centre could need up to 300 MVA.Announced
Public info market held; formal land-use planning procedure not yet started, awaiting council resolution, February 2026
Stadt Eisenachauthority, 2026
Stadt Eisenachauthority, February 2026Checked 10 Oct 2026
Advisum AI data centre at former Isar nuclear plant siteAdvisumNiederaichbach, Landkreis Landshut, Bavaria (former Isar II nuclear power plant site)100 MWdata centre capacity as reported; separate 900 MW battery storage planned on the same siteAnnounced
Plans published for a 100 MW data centre and 900 MW battery storage on about five hectares, September 2026
DataCenter-Insider (dpa)trade press, September 2026Checked 10 Oct 2026
Polarise AI data centre AmbergPolariseAmberg, Bavaria30 MWfirst phaseCompany told Reuters the site could eventually expand to 120 MW.Announced
Plan announced for a 30 MW AI data centre in Amberg, March 2026Expected: Online in mid-2027
Reuters via Yahoo Financepress, March 2026Checked 10 Oct 2026
Microsoft data centre GrevenbroichMicrosoftGrevenbroich, Rhein-Kreis Neuss, North Rhine-WestphaliaNot disclosedInvestment not disclosed; industry estimates cited by dpa range up to about EUR 1 billion.Announced
Purchase agreement for the site signed, with final validity subject to the pending building permit, July 2026Expected: Could connect to the grid in the early 2030s if on schedule
connect professional (dpa)trade press, July 2026Checked 10 Oct 2026
QTS hyperscale data centre LippetalQTS (Blackstone)Lippetal, Kreis Soest, North Rhine-Westphalia (near Hamm)Not disclosedInvestment of about EUR 4 billion reported from financial circles; no MW stated in the opened sources.Announced
Conditional purchase agreement signed for an industrial plot of over 27 hectares; planning procedure to start, January 2026Expected: Completion expected in the early 2030s
CIO (dpa)trade press, January 2026
NRW.Global Businessauthority, March 2026Checked 10 Oct 2026

Ireland

Ireland: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
EPark Little Island (DC1 to DC3)JCD Group (extension applicant Progressive Commercial Construction Ltd)Former Mitsui Denman site, Little Island, Co. Cork12 MWDC1 electrical grid capacityDeveloper also lists DC2 at 10MW grid capacity and DC3 with a 60MW grid connection pending; it cites 33MWth gas capacity for each of DC1 and DC2. JCD page is undated apart from a 2025 copyright footer (read 2026-10-10).Structure complete
Cork County Council extended the permission for two data centre buildings by two years, to 2027; the first data centre is reported fully constructed with fit-out outstanding, March 2025Expected: DC1 grid capacity to be made live in 2026 (developer)
JCD Groupdeveloper, 2025
Irish Examinerpress, March 2025Checked 10 Oct 2026
Echelon DUB20 Arklow campusEchelon Data CentresAvoca River Business Park (former Irish Fertiliser Industries site), Arklow, Co. Wicklow200 MWIT capacity at full build; 90MW in phase oneThe source gives 200MW of IT capacity eventually, with 90MW made available in phase one.Under construction
Construction under way; Echelon said the campus will become Ireland's first Green Energy Park, with a joint 220kV substation with SSE Renewables, March 2026Expected: Due to be finished by 2028
RTÉpress, March 2026
BeBeez (republishing DCD)trade press, September 2025Checked 10 Oct 2026
Art Data Centres Ennis campusArt Data Centres LtdTulla Road, Ennis, Co. Clare200 MWcampus capacityPermission granted by An Bord Pleanála in April 2024; the source also cites an 83MVA off-grid power source.Permitted
High Court dismissed the remaining judicial review grounds against the permission, allowing enabling works to begin, March 2026Expected: Phase One (substation, Data Halls 2 and 3, site works) scheduled for completion and commissioning by the end of 2028
Clare FMpress, March 2026
BeBeez (republishing DCD)trade press, March 2026Checked 10 Oct 2026
Red Admiral data centre and decentralised energy resource, RochfortbridgeRed Admiral DC Ltd (subsidiary of Lumcloon Energy Ltd)Gneevebane, Oldtown, Farthingstown, Castlelost, Kiltotan and Collinstown, Rochfortbridge, Co. Westmeath250 MWdata centre capacity as reported at pre-application stage (May 2025)The 2026 grant reports give no MW figure; the separate 275MW gas plant and 65MW battery are not counted here.In planning
Westmeath County Council granted a 10 year permission for a six unit data centre in June 2026; third-party appeals lodged with An Coimisiún Pleanála, case PL25M.501550, June 2026Expected: Appeals due to be determined by 27 October 2026
RTÉpress, June 2026
An Coimisiún Pleanálaauthority, June 2026
Westmeath Examinerpress, July 2026
Westmeath Examinerpress, May 2025Checked 10 Oct 2026
Herbata data centre campus, NaasHerbata LimitedHalverstown, Jigginstown and Newhall townlands, Naas, Co. Kildare180 MWcampus capacity at full buildout (six data halls of 30MW each)In planning
Kildare County Council granted permission with 77 conditions (notified 20 August 2025); first-party and third-party appeals lodged with An Coimisiún Pleanála on 16 September 2025, case PL09.323677, still pending, September 2025Expected: Irish Times (September 2026) reported an appeal ruling expected by January
RTÉpress, August 2025
BeBeez (republishing DCD)trade press, August 2025
An Coimisiún Pleanálaauthority, September 2025
The Irish Timespress, September 2026Checked 10 Oct 2026
Echelon Kilmeaden technology parkEchelon Data Centres (applicants Crag Rathnew DC Limited and Kent Homes Limited)Former Kilmeaden cheese factory site, Kilmeaden, Co. WaterfordNot disclosedApplication includes three ICT facility buildings of about 24,000 sq m each and an energy centre with 16 gas turbines; no MW figure published in the sources opened.In planning
Planning application lodged with Waterford City and County Council in September 2025; council decision pending, September 2025Expected: Council decision due 19 October 2026
RTÉpress, October 2026
TheJournal.iepress, October 2025Checked 10 Oct 2026

Netherlands

the Netherlands: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Google Groningen Westpoort data centreGoogleWestpoort business park, Groningen (west of Hoogkerk)Not disclosedNo later status update found after the April 2024 construction start; whether the site is in service as of October 2026 was not confirmed in sources opened.Under construction
Google announced the start of construction of a new data centre with a total investment of EUR 600 million, April 2024
Googledeveloper, April 2024Checked 10 Oct 2026
Equinix Lelystad Flevokust Haven campusEquinixLelystad, Flevokust Haven industrial estate (Buitenhavenweg)150 MWpower use of the campus as reported by press (DutchNews; DCD via BeBeez citing Omroep Flevoland); not stated in an Equinix releaseDutchNews notes council information compared the use to 3,000 to 5,000 households, a comparison disputed by experts it quotes; no other MW figure given.Permitted
Lelystad municipality issued custom rules (maatwerkvoorschriften) allowing a higher noise load for phase 1 of the Equinix data centre at Buitenhavenweg Flevokust; planning permission for the project was granted in 2021, July 2026Expected: Completion in phases through to 2028 or 2029 (as reported December 2025)
Gemeente Lelystadauthority, July 2026
DutchNewspress, February 2026
BeBeez International (summarising DCD)trade press, December 2025Checked 10 Oct 2026
QTS Eemshaven EEMS02QTS (Quality Technology Services)Kwelderweg 21, Eemshaven, Het Hogeland (Groningen)Not disclosedDutch IT Channel reports a EUR 1.4 billion expansion (building named EEMSDC2, on the Kwelderweg) that doubles QTS capacity at Eemshaven, with no MW figure; the permit notice names the building EEMS02, and the sources opened do not state that the two names refer to the same building.Permitted
Province of Groningen granted an environmental permit for a change to the boundary of the EEMS02 data centre at Kwelderweg 21, July 2026Expected: Expansion completed by 2029, with an investment of EUR 1.4 billion (Dutch IT Channel)
Provincie Groningenauthority, July 2026
Dutch IT Channeltrade press, July 2025Checked 10 Oct 2026
Microsoft Middenmeer Campus West expansionMicrosoftAgriport A7, Middenmeer, Hollands Kroon (west side of the A7, land adjoining data centres AMS13 and AMS14 at Westlanderweg 50)Not disclosedThe 300 MW in the Commissie mer advice is the emergency generator thermal input threshold that makes an EIA mandatory. The advice also estimates about 535 MWe from installed generator capacity under its own assumption; neither is a published data centre capacity. Plan covers six new data centres with 120 to 150 emergency generators and two substations.In planning
Commissie mer issued its scoping advice on the environmental impact report for six new data centres, requested by the Omgevingsdienst Noordzeekanaalgebied for the Province of Noord-Holland, March 2026Expected: Permits expected to take at least a year from September 2025, then a few years before operation (NH Nieuws)
Commissie voor de milieueffectrapportageauthority, March 2026
Commissie voor de milieueffectrapportageauthority, March 2026
Microsoftdeveloper, February 2026
NH Nieuwspress, September 2025Checked 10 Oct 2026

Switzerland

Switzerland: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Technologiezentrum Laufenburg (TZL), FlexBase Sovereign AI FactoryFlexBase GroupLaufenburg, canton Aargau500 MWmaximum power draw of the AI data centre at full build-out, per developerSwissgrid approved phase 1 of the grid connection at 800 MW in January 2026; the site also includes a redox flow battery storeUnder construction
Excavation completed and above ground construction started, September 2026Expected: full commissioning planned for summer 2028 (April 2025 release)
FlexBasedeveloper, September 2026
FlexBasedeveloper, April 2025
FlexBasedeveloper, January 2026
FlexBasedeveloper, 2026Checked 10 Oct 2026
Green Datacenter Zürich West 4, Campus ZRH1Green DatacenterLupfig, canton Aargau12 MWpower for customer systems (IT load)Under construction
Construction start announced for the fourth data centre on the Metro Campus Zürich West; campus page still lists it as under construction, August 2024Expected: commissioning 2026 (August 2024 release); new data centre space and about 2,000 m2 of offices available early 2027 (campus page)
Greendeveloper, August 2024
Greendeveloper, 2026Checked 10 Oct 2026
Equinix ZH4 sixth expansion phaseEquinixCity of ZurichNot disclosed680 m2 of additional whitespace and about 200 new cabinets; CHF 40 million investmentUnder construction
Sixth expansion phase of ZH4 initiated, November 2024Expected: completion in 2027
Netzwochetrade press, November 2024Checked 10 Oct 2026
Green Datacenter Campus ZRH2 Dielsdorf expansionGreen DatacenterDielsdorf, canton ZurichNot disclosedcampus figure of 46,000 m2 of data centre space stated; no MW publishedUnder construction
New data centre capacity under construction in Dielsdorf: May 2025 release reported two new facilities being built; campus page lists the third data centre on the campus as under construction, May 2025
Greendeveloper, May 2025
Greendeveloper, 2026Checked 10 Oct 2026
NorthC Münchenstein (Basel) 3, uptownBaselNorthC DatacentersArlesheim, canton Basel-Landschaft (Schorenweg 21, uptownBasel campus)7.5 MWtotal power (Gesamtleistung), per developer site pageNetzwoche reports about 5.5 MW usable power from a 6 MVA supplyContractor appointed
Construction contract signed; 18 month build to start on receipt of the building permit, September 2025Expected: commissioning planned for mid 2027 (Netzwoche); available from 2027 (NorthC)
NorthC Datacentersdeveloper, 2026
Netzwochetrade press, September 2025Checked 10 Oct 2026
Vantage Zurich II (ZRH2)Vantage Data CentersGlattfelden, canton Zurich24 MWcritical IT loadAnnounced
Vantage announced construction of a second Zurich campus, to be built from summer 2024, April 2024
Vantage Data Centersdeveloper, 2026
Netzwochetrade press, April 2024Checked 10 Oct 2026

United Kingdom

the United Kingdom: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
QTS Cambois data centre campusQTSCambois, near Blyth, Northumberland (former Blyth Power Station)720 MWcampus potential across up to 10 facilities (basis not specified by the source)Place North East gives size as up to 10 buildings with up to 6m sq ft GIA; no MW in the planning articles.Under construction
Reserved matters lodged with Northumberland Council for phase two, two further data centre buildings DC03 and DC04 (application by Renaissance Land, with QTS as developer and operator); site preparation began October 2025, September 2026Expected: Phase A completion expected around 2029; final completion estimated for 2035 (Place North East, May 2025)
Place North Easttrade press, September 2026
Data Centre Reviewtrade press, October 2025
Place North Easttrade press, May 2025Checked 10 Oct 2026
DataVita DV3, ChapelhallDataVitaChapelhall, North Lanarkshire (next to DV1)Not disclosedDataVita says every megawatt is contracted to CoreWeave under a 15-year lease; no figure given.Under construction
About £300 million debt facility secured to expand DV1 and fund construction of DV3, which DataVita says it is constructing next to DV1, August 2026Expected: DataVita said in August 2026 that the first facility completes this year; the facility is not named
DataVitadeveloper, August 2026
DataVitadeveloper, September 2026Checked 10 Oct 2026
Vantage data centre campus, former Ford engine plantVantage Data CentersWaterton, Bridgend600 MWplanned development capacity (around)Senedd Research gives "around 600 MW" for Bridgend, linked to the officers' report for P/25/247/HYB.Permitted
Bridgend County Borough Council planning committee unanimously approved hybrid application: full permission for the first data centre and outline for a campus of 10, October 2025Expected: Construction set to begin early 2026 with a two-year build for the first data centre; construction phase at least 15 years
Herald.Walespress, October 2025
Senedd Researchauthority, July 2026Checked 10 Oct 2026
Vantage CWL21, St AthanVantage Data Centers (VDC CWL21 Limited)North of Ffordd Bro Tathan business park, St Athan, Vale of Glamorgan120 MWpossible development total, as stated by planning firm CarneySweeneyThe same article describes three buildings of 32MW each; it does not explain the difference from the 120MW total.Permitted
Reported as recently granted permission by Vale of Glamorgan Council for demolition and a data centre development with a substation, August 2025
BeBeez International / DatacenterDynamicstrade press, August 2025Checked 10 Oct 2026
Era4 Newport modular data centreEra4 (formerly Carbon3.ai)Liberty Steel plant, NewportNot disclosedPermitted
Newport City Council granted change-of-use permission for a modular data centre in an existing building, March 2026
BeBeez International / DatacenterDynamicstrade press, April 2026Checked 10 Oct 2026
Humber Tech ParkHumber Tech Park (Greystoke)North Lincolnshire, near the Humber EstuaryNot disclosedPermitted
Outline planning permission granted by North Lincolnshire Council for an AI data centre project, August 2024
Humber Tech Park (developer website)developer, 2024Checked 10 Oct 2026
Microsoft Skelton Grange data centre campusMicrosoft (MSFT MCIO Ltd), with landowner Harworth GroupSkelton Grange, Leeds, West YorkshireNot disclosedPermitted
Leeds City Council planning committee unanimously resolved to approve full permission for three data centre buildings (424,000 sq ft) with outline permission for a 160,000 sq ft warehouse, April 2026
Place Yorkshiretrade press, April 2026
AJ Bellpress, April 2026Checked 10 Oct 2026
Prosperity Parc technology parkStena Line (Anglesey Land Holdings)Former Anglesey Aluminium (Penrhos) site, Holyhead, Isle of AngleseyNot disclosedPlace North West gives a 349MW target capacity for the site's battery energy storage system, not for the data centre.Permitted
Isle of Anglesey County Council approved outline planning permission (OP/2025/2) for more than 220,000 sq m of data centre, industrial and office development, September 2025
Business News Walespress, September 2025
Place North Westtrade press, March 2025Checked 10 Oct 2026
Teesworks data centre campus, RedcarTeesworks Ltd (South Tees Group); operator not namedTeesworks, Redcar, Redcar and Cleveland (land bounded by the NWL Bran Sands treatment plant and the former ICI landfill)Not disclosedCMS describes "a data centre with more than a gigawatt of computing power" without a specific figure; the reserved matters scheme is 462,419 sq m.Permitted
Reserved matters (appearance, landscaping, layout, access and scale) granted by Redcar and Cleveland Council under R/2025/0382/ESM, August 2025
Redcar and Cleveland Borough Councilauthority, August 2025
CMSpress, December 2025Checked 10 Oct 2026
Chapelcross data centre campusCX Tech LimitedLand north of the former Chapelcross nuclear power station, near Annan, Dumfries and Galloway1,000 MWcampus total (about 1GW; eight buildings of about 120MW each)Sources state "about 1GW total" for the campus; each building about 120MW.In planning
Planning application for eight data centre buildings reported as submitted to Dumfries and Galloway Council; developer states an Environmental Impact Assessment has been undertaken, October 2026Expected: Construction in phases over about eight years; potentially fully operational by 2035 if work begins in 2027
DIGITtrade press, October 2026
EIBItrade press, October 2026Checked 10 Oct 2026
Cato Data CentreILI GroupLand north of Camilla Road, Gleniston, Auchtertool, Fife600 MWproposed capacity as reported by Tech Times; developer and council pages give no MWSPICe gives annual energy use rather than capacity: early phase around 400 GWh per year, ultimate potential 4000 GWh.In planning
Planning permission in principle application 26/01243/PPP for a data centre campus validated by Fife Council; no decision yet, May 2026
Fife Councilauthority, May 2026
ILI Groupdeveloper, 2026
Tech Timespress, September 2026Checked 10 Oct 2026
Ravenscraig Energy Campus data centreApaturaRavenscraig masterplan area (former steelworks), Motherwell, North Lanarkshire550 MWgrid connections (data centre campus)Developer page states a planning application was submitted while its timeline lists submission for Q3 2026.In planning
Developer states it has submitted a formal planning application; NESO grid agreement secured June 2025 and public consultations held October 2025, 2026Expected: 550MW of grid connections expected to come online by 2030
Apaturadeveloper, 2026
STV Newspress, June 2025Checked 10 Oct 2026
Rufus data centreILI GroupHurlford, near Kilmarnock, East Ayrshire540 MWmaximum power draw (as badged)In planning
Developer states the site has secured grid connection and land rights and has entered the planning process, 2026
SPICe Spotlight (Scottish Parliament Information Centre)authority, June 2026
ILI Groupdeveloper, 2026
ILI Groupdeveloper, September 2026Checked 10 Oct 2026
Blyth Data Centre, Factory RoadTBC PartnersFactory Road, Cambois, Northumberland300 MWcampus total suggested on developer website (as reported)Figure attributed to TBC Partners' website, not the planning filing.In planning
EIA screening/scoping opinion requested from Northumberland County Council for a campus of one or two data centre buildings and an on-site substation; full application not yet filed, August 2026Expected: About 24 months of construction; operation intended from 2030 to 2035
BeBeez International (republishing DatacenterDynamics)trade press, August 2026
Hexham Courantpress, 2026Checked 10 Oct 2026
Larbert Data Centre CampusApaturaBeside Glenbervie Business Park, Bellsdyke Road, Larbert, Falkirk300 MWdata centre campusIn planning
Falkirk Council pre-determination hearing held; application still to be decided, September 2026
Apaturadeveloper, 2026
Resultsense (summarising The National)press, September 2026
SPICe Spotlight (Scottish Parliament Information Centre)authority, June 2026Checked 10 Oct 2026
Wilton International Data CentreSembcorp Energy UK with Digital Reef (joint development agreement)Wilton International, Teesside, Redcar and Cleveland280 MWup to, installed capacity; Construction Review labels it Phase 1Data Centre Review says the development "could deliver up to 280 MW of capacity"; Construction Review gives "up to 280MW of installed capacity" and "Up to 280MW (Phase 1)".In planning
Planning application submitted for the initial phase, May 2026Expected: Construction expected to begin later in 2026, subject to planning and other approvals
Data Centre Reviewtrade press, May 2026
Construction Review Onlinetrade press, May 2026Checked 10 Oct 2026
Wester Hermiston Data Centre CampusApaturaWester Hermiston, Edinburgh200 MWdata centre campusIn planning
Scottish Government Planning and Environmental Appeals Division decided on a third-party request that an EIA is required (screening case 25/05576/SCR, City of Edinburgh Council), August 2026
Scottish Government Planning and Environmental Appeals Division (DPEA)authority, August 2026
Apaturadeveloper, 2026Checked 10 Oct 2026
Cardiff East Park and Ride data centreCurtis Hall LtdCardiff East Park and Ride, between Pentwyn and Llanrumney, Cardiff150 MWproposed development capacitySenedd Research lists a 150 MW Cardiff proposal, hyperlinked to this project's noise impact assessment; the developer's site and Nation.Cymru give no MW figure.In planning
Welsh Government issued a holding direction preventing Cardiff Council from granting permission while it considers whether to call in the application, August 2026
Nation.Cymrupress, September 2026
Senedd Researchauthority, July 2026Checked 10 Oct 2026
Sherwood Business Park data centre (Plot 13b)Port@l Limited (Portal Group)Plot 13b, Sherwood Business Park, Annesley Woodhouse, Ashfield, Nottinghamshire20 MWIT capacity (four 5MW data halls)In planning
Outline application (V/2026/0033) for a data centre lodged with Ashfield District Council, March 2026
Public Notice Portal (Mansfield Chad)authority, March 2026
BeBeez International / DatacenterDynamicstrade press, April 2026Checked 10 Oct 2026
Aurelius data centreILI GroupNorth LanarkshireNot disclosedIn planning
Developer states the site has secured grid connection and land rights and has entered the planning process, 2026
ILI Groupdeveloper, 2026
ILI Groupdeveloper, September 2026Checked 10 Oct 2026
DataVita DV4, ChapelhallDataVitaLancaster Avenue, Chapelhall, North LanarkshireNot disclosedResultsense (summarising The National, 29 Sep 2026) refers to a planned 120MW Chapelhall site; DataVita's release gives no MW.In planning
Planning permission in principle submission to North Lanarkshire Council for DV4, September 2026Expected: £849.6 million of construction investment over two years
DataVitadeveloper, September 2026
Resultsense (summarising The National)press, September 2026Checked 10 Oct 2026
Elsham Tech ParkElsham Tech Park Limited (Greystoke)Next to Elsham Wolds Industrial Estate, North LincolnshireNot disclosedBarbour ABI (April 2026) says Elsham Tech Park Limited is seeking approval for "a £10bn 1GW data centre"; the developer website gives no capacity.In planning
Outline planning application submitted to North Lincolnshire Council, 2025Expected: Indicative: reserved matters 2026, construction 2027, first phase opens 2029
Elsham Tech Park (developer website)developer, 2025
Barbour ABItrade press, April 2026Checked 10 Oct 2026
Latos Newton Heath data centreLatos Data CentresBower Street, Newton Heath, ManchesterNot disclosedScheme size given as 28,000 sq ft across two buildings.In planning
Planning application PLA-2026-001350 submitted to Manchester City Council, August 2026Expected: Construction of the 28,000 sq ft scheme by 2030
Place North Westtrade press, August 2026Checked 10 Oct 2026
Mwyndy Cross data centreMaska Group LimitedMwyndy Cross, east of the A4119, Rhondda Cynon TafNot disclosedScheme described as an 18,220 sq m data centre with a 2,260 sq m office block.In planning
Planning application submitted for an 18,220 sq m data centre and office block, June 2026
Nation.Cymrupress, June 2026Checked 10 Oct 2026
West Sleekburn data centre campusWansbeck Regeneration LtdWest Sleekburn, Northumberland (former GlaxoSmithKline site, River Wansbeck)Not disclosedThe article states ancillary gas power generation of up to 49.9MW as a bridging solution; this is not the data centre capacity.In planning
Planning application submitted to Northumberland Council for three data centres totalling 3.9m sq ft GIA and two substations, June 2026
Place North Easttrade press, June 2026Checked 10 Oct 2026
Microsoft Eggborough data centreMicrosoftFormer Eggborough Power Station site, Eggborough, North YorkshireNot disclosedAnnounced
Microsoft stated it intends to apply to North Yorkshire Council for planning permission for two data centre buildings at the former power station site, March 2024Expected: Site cleared by late 2026 and construction starting in early 2027 (as stated in March 2024)
ITProtrade press, March 2024Checked 10 Oct 2026
Spodegreen data centre campusInnovaSouth of Lymm Road, Tatton Estate land, Cheshire EastNot disclosedAnnounced
Public consultation on a 148-acre data campus; application due to be submitted to Cheshire East Council, September 2026Expected: Planning application by early 2027
Place North Westtrade press, September 2026Checked 10 Oct 2026

Denmark

Denmark: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Dansk Data Center 1 (DDC1)Thylander Group with PensionDanmark and Copenhagen Infrastructure Partners (CI Microgrid Electrification Fund)Port of Esbjerg (NATO port), Esbjerg11.5 MWgrid connection through grid operator N1DataCenter-Insider (June 2025) reported a campus starting at 10 to 20 MW with long term expansion to 100 MW or 200 MW; these figures are not used as the row capacity. The W.Media headline says Copenhagen but the body places the site in Esbjerg.Under construction
Groundbreaking ceremony held on 13 August 2026, August 2026
W.Mediatrade press, August 2026
DataCenter-Insidertrade press, June 2025Checked 11 Oct 2026
atNorth DEN02 (sector coupled data centre and greenhouses at Krageris)atNorthKrageris, north of Ølgod, Varde Kommune500 MWcampus total power capacity (up to); first phase 60 MWatNorth's Danish Q&A page gives up to 500 MW total and a 60 MW first phase. Varde Kommune's project page gives no MW figure and describes up to 225,000 m2 of data centre on about 174 hectares.Permitted
Varde City Council approved the planning basis (local plan 24.10.L03 and municipal plan supplement) for the site on 6 October 2026; a four week complaint period follows, October 2026Expected: atNorth expects to start construction of the first phase in Q4 2026
Varde Kommuneauthority, October 2026
atNorthdeveloper, October 2026
Ingeniørenpress, October 2026Checked 11 Oct 2026
Datacenter ved Stovstrup (Projekt MARK)DCS (DCS Development)Stovstrup, Ringkøbing-Skjern KommuneNot disclosedIn planning
Call for ideas and proposals with environmental screening opened on 24 August 2026, followed by a public meeting on 31 August 2026, August 2026
Ringkøbing-Skjern Kommuneauthority, August 2026
Ingeniørenpress, June 2026Checked 11 Oct 2026
Microsoft Western Denmark regionMicrosoftEsbjerg and VardeNot disclosedDescribed as Microsoft's largest single investment in DenmarkIn planning
Varde council decided to start local plan work for Microsoft's sites north of Tinghøj and between Lunde and Nørre Nebel, June 2026
Datacenter Forumtrade press, December 2025
Varde Kommuneauthority, September 2026Checked 11 Oct 2026
Stender data centre on LollandStenderLolland Kommune (Lundegårdsvej area; Rødby and Nakskov named in reporting)Not disclosed114 hectares of fields and a 328,000 m2 building area reported; end tenant not disclosed.In planning
Lolland Kommune held a public meeting on the planned data centre, with a municipal planner presenting the project, September 2026
Ingeniørenpress, September 2026
Ingeniørenpress, September 2026Checked 11 Oct 2026
Varde Park datacenter at Varde SydVarde ParkVarde Syd, between Varde town and Søndre Plantage, Varde KommuneNot disclosedSite area 111.5 hectares. Local plan 23.03.L08 (2021) already zones about 37 ha for data centres; the row describes the expansion now under application.In planning
Varde Kommune is processing the developer's application to expand the data centre area and held an information meeting on 1 October 2026 to form a dialogue group, October 2026
Varde Kommuneauthority, October 2026Checked 11 Oct 2026
Prime Data Centers ESB01Prime Data Centers with Brunswick Real EstateEsbjerg550 MWcampusFirst phase 160 MW of IT capacityAnnounced
Project announced, March 2026Expected: Construction could start in 2027, subject to an environmental impact assessment
W.Mediatrade press, March 2026Checked 10 Oct 2026
Garbe Data Centers Business Park FalsterGarbe Data CentersBusiness Park Falster, Nordfalster, Guldborgsund Kommune350 MWcapacity as reported, basis not statedIngeniøren does not say whether 350 MW is IT load or total power; investment of up to DKK 20 billion attributed to Guldborgsund Kommune.Announced
Guldborgsund Kommune agreed to sell 35 hectares of commercial land in Business Park Falster to the developer, November 2025
Ingeniørenpress, November 2025Checked 11 Oct 2026

Finland

Finland: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
XTX Markets Kajaani campus, second and third data centresXTX MarketsKajaaniNot disclosedNo figure for the second and third buildings; the first data centre was described in January 2025 as three halls totalling 22.5 MW of IT power, with four further data centres planned on the siteStructure complete
Shell and core of the third data centre completed; YIT contracted for its fit-out and MEP works, starting late 2026, September 2026Expected: Second building expected to be completed in 2027
YITcontractor, September 2026
YITcontractor, March 2026
Datacenter Forumtrade press, January 2025Checked 11 Oct 2026
atNorth FIN04, MyllykoskiatNorthMyllykoski, Kouvola430 MWcampus power capacityPermit applied for three new buildingsUnder construction
YIT signed a design-and-build contract of about EUR 300 million; construction began immediately, July 2026Expected: Completion expected by the end of 2027
Datacenter Forumtrade press, February 2026
YITcontractor, July 2026Checked 11 Oct 2026
Nebius Lappeenranta AI campus, PajarilaNebius, developed with PolarnodePajarila district, Lappeenranta310 MWfull campus capacityUnder construction
Pre-construction works for Nebius scheduled to begin in Pajarila on 13 May 2026, delivered by Polarnode with Louhintahiekka Oy; Caverion to build the substation, May 2026Expected: First phase expected to go live in 2027
Polarnodedeveloper, May 2026
Polarnodedeveloper, March 2026
W.Mediatrade press, March 2026Checked 11 Oct 2026
Data Tank Nordic Utajärvi data centreData Tank Nordic Oy (DataTank AG, AmpTank group)Utajärvi200 MWavailable powerBuilding permits and a binding grid connection agreement announced June 2026Under construction
Nyab Finland contracted for first phase preparatory works on the campus, with work starting immediately, October 2026
Rakennuslehtitrade press, October 2026
Datacenter Forumtrade press, June 2026Checked 11 Oct 2026
Compute Nordic Mikkeli AI campusCompute Nordic Finland, with Cerebras SystemsMikkeli, South Savo165 MWcontracted IT capacity, phasedInitial phase 50 MW, then 80 MW, then 165 MW; January 2026 permit report cited 212 MW of IT compute capacity for the first phaseUnder construction
Cerebras partnership announced with construction of the initial 50 MW phase under way, September 2026
W.Mediatrade press, September 2026
Datacenter Forumtrade press, September 2026
Datacenter Forumtrade press, January 2026Checked 11 Oct 2026
Verne Mäntsälä data centre campusVerneKapuli area, Mäntsälä70 MWinitial capacityAbout 10 hectare site; power supplied by NivosUnder construction
Foundation stone ceremony marked the start of construction of the first 70 MW, June 2026
Vernedeveloper, June 2026
Datacenter Forumtrade press, June 2026Checked 11 Oct 2026
atNorth FIN02 expansionatNorthEspoo45 MWgross capacity of the whole facility after expansionUnder construction
Core and shell construction started (Skanska), April 2026Expected: Q3 2027
Skanskacontractor, May 2026Checked 10 Oct 2026
Hyperco Kouvola data centre, Koria (first building)Hyperco (project company Hyperco Fin HoldCo 1 Oy), jointly invested with DayOne; tenant TikTokHiivuri, Koria, KouvolaNot disclosedNo capacity figure published for this building; YIT gives a floor area of approximately 28,000 square metresUnder construction
Under construction since late 2025 with YIT as main contractor; completion in May 2027 restated in June 2026, June 2026Expected: Completion scheduled for May 2027
YITcontractor, October 2025
Datacenter Forumtrade press, June 2026
Datacenter Forumtrade press, August 2025Checked 11 Oct 2026
ASP DC Pori data centre (CompassForge Real Estate I)ASP DCKupariteollisuuspuisto, Pori150 MWinitial green power capacity of the site, as published in January 2025Site described as scalable to 300 MW in January 2025; ASP DC described 300 to 400 MW modular capacity in December 2025Permitted
ASP DC entered a definitive agreement to acquire the zoned 37 hectare project from CompassForge Ventures, December 2025Expected: Construction set to start in 2026; first phase commercial operations in early 2027
Datacenter Forumtrade press, December 2025
Datacenter Forumtrade press, January 2025Checked 11 Oct 2026
Pori data centre project (sold by Polarnode)Undisclosed European data center operator (project developed by Polarnode)Pori150 MWmaximum available grid capacity per developer site specification26 hectare sitePermitted
Polarnode agreed to sell the project, with zoning and building permits in place and grid capacity secured, to an undisclosed European operator, June 2026Expected: Time to power: max 2 years (developer specification)
Polarnodedeveloper, June 2026
Polarnodedeveloper, 2026Checked 11 Oct 2026
Magnora and NEEG Hämeenlinna data centreMagnora (70%) and Northern Europe Energy Group (30%)Hämeenlinna120 MWfacility capacity150,000 m² zoned for data center operationsPermitted
Magnora joined the project as majority owner through a joint venture with NEEG, January 2026Expected: Ready-to-Build stage by the end of 2026
Datacenter Forumtrade press, January 2026Checked 11 Oct 2026
Pure DC Seinäjoki AI campus (SJK01)Pure Data Centres Group, with local partner SDC VenturesSeinäjoki110 MWphase 1 IT capacityFull campus designed to scale beyond 550 MW, with access to more than 700 MVA of renewable power; built in 40 MW modulesPermitted
Phase 1 launched: fully leased, planning permissions and power secured, substation for the first data hall constructed and live, July 2026
Datacenter Forumtrade press, July 2026
W.Mediatrade press, July 2026Checked 11 Oct 2026
Hyperco Koria second data centreHypercoHiivuri, Koria, Kouvola (11.1 hectare plot west of the first building)100 MWIT capacityTotal electrical capacity approximately 130 MW; a separate environmental permit for operations is still requiredPermitted
Building permit granted by the permit department of the Kouvola Technical Board, with approval to start work before the permit became legally binding, June 2026
Datacenter Forumtrade press, June 2026Checked 11 Oct 2026
Aurora Core Technology Mikkeli data centre, PellosAurora Core Technology Oy (3 E Network Technology Group)Pellos industrial area, southern Mikkeli6 MWinitial phaseNearby grid infrastructure supports connection capacity of up to 50 MWPermitted
Land lease for a 10 hectare site with a valid zoning plan allowing data centre development entered into force, December 2025Expected: Initial 6 MW phase expected in operation in the second half of 2026
Datacenter Forumtrade press, January 2026Checked 11 Oct 2026
Microsoft capital region data centres, phase 2MicrosoftEspoo, Kirkkonummi and VihtiNot disclosedPhase 1 under construction since late 2024, expected to finish around the turn of 2026 and 2027Permitted
Construction decision for phase 2 confirmed; building permits in place for all three campuses, April 2026Expected: Phase 2 construction targeted to start during 2026
Microsoftdeveloper, April 2026Checked 11 Oct 2026
DayOne Klaukkala campusDayOneKlaukkala, Nurmijärvi, about 30 km north of Helsinki560 MWtotal grid power, tentative phased potentialNeeds zoning, municipal permits and a Ministry of Defence permitIn planning
Early-stage plan announced; zoning under way, January 2026
W.Mediatrade press, January 2026Checked 10 Oct 2026
Polarnode Sarvenmaa data centre, KeminmaaPolarnode (Polarnode Keminmaa Oy)Sarvenmaa, Keminmaa500 MWpower grid capacity, stated as more than 500 MWSite area 109 ha; zoning ongoingIn planning
EIA programme submitted to the Finnish Supervisory Agency and put on public review until 14 September 2026, August 2026Expected: Time to power 2028 (developer specification)
Polarnodedeveloper, August 2026
Polarnodedeveloper, 2026Checked 11 Oct 2026
Polarnode Kuopio data centre, MustakorpiPolarnodeMustakorpi area, Kuopio50 MWfirst phase design capacityTotal capacity potentially 250 MW in later stages; about 32 hectaresIn planning
City of Kuopio confirmed a reservation agreement allocating the Mustakorpi area to Polarnode; zoning included in the 2026 zoning programme, December 2025Expected: Construction ready during 2027
Polarnodedeveloper, December 2025
Polarnodedeveloper, 2026Checked 11 Oct 2026
Google Finland expansionGoogleHamina, Kajaani, Muhos and VaalaNot disclosedAt least €13 billion for 2027 and 2028, plus a 94 MW battery near KajaaniIn planning
Regulator (LVV) ordered site preparation at Muhos and Kajaani suspended until the environmental impact assessments are complete; projects not cancelled, October 2026Expected: EIA reports for Muhos and Kajaani expected in 2026; Google's written response due 14 October 2026
Google Clouddeveloper, September 2026
Data Center Knowledgetrade press, October 2026Checked 10 Oct 2026
Helios Tervola data centre, KoivuHelios Nordic Energy Finland Oy (project company Helios 1 Cranberry Oy)Koivu, TervolaNot disclosedPreliminary project area about 860 hectares; plans to connect to a planned Fingrid Louepalo substationIn planning
Planning initiative submitted to the municipality; process to include an environmental impact assessment, August 2026
W.Mediatrade press, August 2026Checked 11 Oct 2026
Prime Data Centers Järvenpää data centrePrime Data Centers, with Brunswick Real EstateVähänummi industrial area (Emalikatu), JärvenpääNot disclosedInitial investment about €1.2 billion; plot of about 12 hectaresIn planning
Project entered the environmental impact assessment procedure coordinated by the Finnish Licensing and Supervision Agency, January 2026Expected: Construction expected to begin in 2027, subject to EIA and permits
Datacenter Forumtrade press, January 2026Checked 11 Oct 2026
YIT Kontiolahti data centre, VellamoYIT, with the Municipality of KontiolahtiVellamo business area, KontiolahtiNot disclosedAbout 25 hectares proposed for reservation; depends on energy infrastructure, including a possible future 400 kV connectionIn planning
Planning reservation agreement signed; municipality zoning the business area, February 2026Expected: Zoning expected to be completed during 2026; construction could start between 2027 and 2028
W.Mediatrade press, February 2026Checked 11 Oct 2026
FCDC Rovaniemi data centre, HietavaaraFCDC Corp OyHietavaara, about 15 km outside Rovaniemi500 MWdata centre capacity as reportedGoal to obtain building rights for 180,000 m²Announced
Plan reported for Hietavaara; company seeking building rights, May 2025Expected: Completion in 2029
Datacenter Forumtrade press, May 2025Checked 11 Oct 2026
Sesterce Kaipola AI campusSesterceFormer Kaipola paper mill, Jämsä200 MWfirst phase capacitySecond phase would take the campus to 600 MWAnnounced
€10 billion campus plan announced, with an anchor customer, October 2026Expected: First phase planned to begin in 2026
W.Mediatrade press, October 2026Checked 10 Oct 2026
DayOne Lahti campus, KiveriöDayOne; main tenant TikTokKiveriö district, Lahti128 MWtotal potential IT loadFirst building 50 MW IT load; power connection agreement signed with Lahti EnergyAnnounced
TikTok confirmed a €1 billion investment in the Lahti data centre; Lahti mayor said a main tenant agreement has been signed, April 2026Expected: Ready for service in 2027
Datacenter Forumtrade press, April 2026
Datacenter Forumtrade press, August 2025
W.Mediatrade press, April 2026Checked 11 Oct 2026
APL Group Varkaus data centre campusAPL Group (Asia Pacific Land)Varkaus100 MWdesign capacityFirst phase 60 MW, with a planned 40 MW expansion; 28 hectare site; Scale42 is advisorAnnounced
Development of hyperscale campus announced, June 2025
Datacenter Forumtrade press, June 2025Checked 11 Oct 2026
Solano Pyhäjärvi data campusSolano, with Callio and the Town of PyhäjärviUusi Olkkola, Pyhäjärvi100 MWinitial capacityScalable to several hundred megawatts (up to 800); 80 ha municipal leaseAnnounced
Campus launched on an 80 ha municipal lease; a permitting package covering zoning, grid interconnection and environment aims to deliver a ready to build asset, January 2026
Datacenter Forumtrade press, January 2026Checked 11 Oct 2026
Winda Energy Janakkala data centreWinda Energy, with Gi21 CapitalRastikangas industrial zone, Janakkala100 MWdata centre capacity22 hectare site; about €500 millionAnnounced
Project announced for the Rastikangas industrial zone, April 2026Expected: Construction scheduled to start in 2027; fully operational in 2028
W.Mediatrade press, April 2026Checked 11 Oct 2026
Winda Energy Keminmaa data centreWinda Energy, with Gi21 CapitalRajakangas industrial area, Keminmaa100 MWdata centre capacity, approximate (about 100 MW) as stated by the developerAbout 15 hectares reserved; investment of over half a billion eurosAnnounced
Project development started with about 15 hectares reserved in the Rajakangas industrial area, May 2026Expected: Construction to begin in 2027; first phase completion in 2028
Winda Energydeveloper, May 2026
Datacenter Forumtrade press, June 2026Checked 11 Oct 2026
atNorth FIN05, SaloatNorthSalo75 MWfirst phase powerFull development could reach 230 MWAnnounced
Project announced, October 2026
W.Mediatrade press, October 2026Checked 10 Oct 2026
Valorem Eurajoki data centre, KissankallioValoremKissankallio area, Eurajoki60 MWfirst phase data centreLinked to an 80 MW solar plant and 30 MW battery storage; could expand to several hundred megawattsAnnounced
Project announced; planning reservation agreement for about 55 hectares under negotiation with Eurajoki, March 2026Expected: Building permit sought for next year
Datacenter Forumtrade press, March 2026Checked 11 Oct 2026
Glesys Campus OuluGlesys, with Trevian Asset ManagementOulu8 MWinitial IT load of the first deployment phase (approximately)Long-term expansion potential of up to 300 MWAnnounced
Agreement with Trevian to establish Campus Oulu announced, June 2026Expected: First phase ready for service in autumn 2026
Datacenter Forumtrade press, June 2026Checked 11 Oct 2026
Microsoft GigaVaasa data centre siteMicrosoftGigaVaasa industrial area, Vaasa and MustasaariNot disclosedAbout 190 hectares, two thirds in Vaasa and one third in MustasaariAnnounced
Preliminary agreement signed to buy about 190 hectares for a possible data centre project, June 2026
Microsoftdeveloper, June 2026Checked 11 Oct 2026
Nscale Harjavalta data centre, SievariNscale, with FortumSievari industrial area, HarjavaltaNot disclosedCapacity to be determined during design and permittingAnnounced
Fortum signed a site securing and development agreement with Nscale; preliminary land sale process started with the Town of Harjavalta, April 2026
W.Mediatrade press, April 2026
Datacenter Forumtrade press, April 2026Checked 11 Oct 2026
OnZero Helsinki data centreOnZero Finland OyHelsinkiNot disclosedHelen states the facility could supply more than 500,000 MWh of heat a year to the district heating networkAnnounced
Helen agreed to use waste heat from the planned data centre in Helsinki's district heating network, August 2026Expected: Waste heat recovery scheduled to begin in 2027
Helendeveloper, August 2026
Datacenter Forumtrade press, September 2026Checked 11 Oct 2026
Scale42 Kitee AI data centre, PuhosScale42Puhos industrial area, KiteeNot disclosed10 hectare plotAnnounced
City of Kitee to sign a preliminary property purchase agreement with Scale42, October 2025Expected: Construction start goal 2026; ready and in use by 2027 to 2028
Datacenter Forumtrade press, October 2025Checked 11 Oct 2026

Norway

Norway: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Google SkienGoogleGromstul, Skien240 MWgrid allocation, first phaseUnder construction
Construction started (reported), 2024Expected: Go-live in 2026 (reported)
Datacenter Forumtrade press, 2024Checked 10 Oct 2026
Tydal Data Center AI conversionBitdeer (Tydal Data Center AS)Tydal, Trøndelag121 MWIT capacity, supported by 133 MW grossAn April 2026 report gives 180 MW of gross installed capacity for the site; digi.no reports the site has received 180 MW of power, of which 47 MW is reserved for Bitdeer.ai.Under construction
Conversion of the existing Tydal facility to an AI data centre under way, with Data Center Installations AS contracted for the conversion; 16 year colocation lease signed with Volta Tydal AS, a Volta subsidiary, for capacity serving an AI lab, August 2026Expected: phase one in operation by end of 2026, phase two completed in Q1 2027
W.Mediatrade press, August 2026
digi.notrade press, August 2026
W.Mediatrade press, April 2026
digi.notrade press, May 2026Checked 10 Oct 2026
Green Mountain SVG-UndheimGreen MountainUndheim, Time municipality, Rogaland80 MWtotal IT capacity of two interconnected buildings; site total stated as 100 MWDeveloper site page gives 80 MW IT capacity and 100 MW maximum site capacity; the August 2026 article gives 100 MW total power capacity.Under construction
Under construction with DC Nordics as main contractor; Green Mountain published an economic impact analysis of the site, August 2026Expected: full completion scheduled for 2028
Green Mountaindeveloper, 2026
Green Mountaindeveloper, August 2026
digi.notrade press, April 2026Checked 10 Oct 2026
EdgeConneX FyresdalEdgeConneXMolandsmoen, Fyresdal, TelemarkNot disclosedUnder construction
First building under construction on a 160 mål site acquired through two land companies, September 2026Expected: first building operational in Q3 2027
digi.notrade press, September 2026
E24press, August 2026Checked 10 Oct 2026
Green Horizon Norway 1Green HorizonStavanger area, Rogaland (municipality not named)36 MWpower capacityDeveloper states 96 MW of power secured across three planned data centres.Permitted
Planning approval received for Norway 1 after earlier zoning approval, June 2026Expected: construction to start later in 2026; ready for service targeted for the second half of 2027
Green Horizondeveloper, June 2026
W.Mediatrade press, June 2026Checked 10 Oct 2026
Grenland Data Center, BolvikNscale with Grenland Data Center (Løvenskiold-Fossum)Bolvik, Skien, Telemark576 MWpower requested from StatnettRequested grid capacity, not confirmed allocation.Announced
Option agreement signed in summer 2026 between Grenland Data Center and Skien Tomteselskap for a 500 mål plot near Grenland transformer station, conditional on zoning and power access; reported September 2026, September 2026Expected: zoning expected to take about two years
E24press, September 2026Checked 10 Oct 2026
DC Sarpsborg, HasleØstfold EnergiNext to Hasle transformer station, outside Sarpsborg, Østfold300 MWpower supply the planned data centre would requireSource states the centre will require a power supply equivalent to 300 MW.Announced
Østfold Energi developing a 2,152 decare area for a data centre, with landowner agreements on 1,700 decares; Statkraft expected to bring a data centre customer during the autumn, March 2026Expected: area to be fully zoned in 2027
digi.notrade press, March 2026Checked 10 Oct 2026
BW Velora data centre, Frier VestBW Velora with Frier VestFrier Vest industrial area, Grenland, Telemark250 MWplanned capacityAnnounced
Agreement signed between Frier Vest and BW Velora to build a data centre, May 2026Expected: construction start at the earliest during 2026; operational between 2028 and 2029
digi.notrade press, May 2026Checked 10 Oct 2026
Nscale HelgelandNscaleNedre Røssåga substation area, Hemnes, Nordland250 MWapproximate first phase capacity as stated by Nscale's Scandinavia chief; separate grid requests in Statnett's capacity queue of 250 MW and 750 MWDeveloper gives the first phase as about 250 MW. Two separate grid requests (250 MW and 750 MW) are listed in Statnett's queue; figures not summed.Announced
Nscale listed in Statnett's capacity queue with two power requests at Nedre Røssåga substation in Hemnes, June 2026
digi.notrade press, June 2026Checked 10 Oct 2026
Nscale Narvik campus (announced as Stargate Norway)NscaleKvandal, Narvik230 MWplanned capacityAmbition to add a further 290 MW. OpenAI's offtake talks ended without agreement; Microsoft is expected to take the capacity (reported April 2026)Announced
Nscale expanded its agreement with Microsoft for capacity in Narvik after OpenAI's offtake talks ended, April 2026
Akerdeveloper, July 2025
W.Mediatrade press, April 2026Checked 11 Oct 2026
atNorth NOR01, HaugalandatNorthHaugaland Business Park, Tysvær120 MWinitial phasesDesigned to scale to 350 MWAnnounced
Project announced, June 2026Expected: Power availability projected for 2028
atNorthdeveloper, June 2026Checked 10 Oct 2026
Asp Data Center SuldalAsp Data CenterTysingvatnet, Suldal, Rogaland100 MWavailable capacity stated on the developer's Suldal site page, which lists power capacity as 0 MWAnnounced
Suldal municipal council decided unanimously to sell a 56 decare plot at Tysingvatnet to Asp Eiendom AS for a data centre; detailed planning and approval processes still to begin, December 2025Expected: ready for service Q1 2029
Asp Data Centerdeveloper, January 2026
Asp Data Centerdeveloper, 2026Checked 10 Oct 2026
Polar DRA02 DrangedalPolar Data CentersDrangedal, Telemark40 MWIT capacity (approximately)Announced
DRA02 expansion announced adjacent to DRA01 at the Drangedal campus, July 2026
Polardeveloper, July 2026Checked 10 Oct 2026
Polar HerøyaPolar Data CentersHerøya Industrial Park, Porsgrunn, Telemark40 MWinitial capacity (in the region of 40 MW)Developer locations page lists an entry 'HER – Norway' with 41 MW IT load in development, 100 MW total energy capacity and status pre-design phase.Announced
New AI-ready data centre development announced at Herøya Industrial Park on a 39,000 m2 site described as ready for construction, May 2026
Polardeveloper, May 2026
Polardeveloper, 2026Checked 10 Oct 2026
Green Mountain OSL-Hamar buildings 4 and 5Green MountainHamar, Innlandet30 MWIT capacity per building; two further buildings plannedDeveloper gives 5 x 30 MW maximum IT capacity and 150 MW future campus capacity; three buildings (90 MW) are in operation. Figure not summed.Announced
Developer restated plan for a 150 MW campus at full build-out with five buildings, two more buildings planned beyond the three in operation, August 2025
Green Mountaindeveloper, August 2025
Green Mountaindeveloper, 2026Checked 10 Oct 2026
Bulk Infrastructure Arendal siteBulk InfrastructureArendal, AgderNot disclosedAnnounced
Arendal municipality selling a data centre plot to Bulk Infrastructure for NOK 600 million, June 2026
digi.notrade press, June 2026Checked 10 Oct 2026

Sweden

Sweden: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
EcoDataCenter 2, KvarnsvedenEcoDataCenterBorlänge (former Kvarnsveden paper mill)250 MWpower at launchPotential to scale to 600 MW. Mistral AI announced an AI data centre at the site (EUR 1.2 billion, opening 2027)Under construction
Ground broken, September 2025Expected: First data centre in early 2027
EcoDataCenterdeveloper, September 2025
EcoDataCenterdeveloper, February 2026Checked 11 Oct 2026
Conapto Stockholm 4 South, final phaseConaptoStockholm (Stockholm South Campus)8 MWadditional power from Ellevio for the expansion ("8 MW extension")Conapto states that with the addition "the site will scale from 20 MW to 28 MW"; the new power was to be ready from 1 January 2026. The site is partly operational, and CoreWeave reported initial capacity online there in June 2026.Under construction
New power infrastructure with 50 tonne power pods installed as the site enters its final phase of development, February 2026
Conaptodeveloper, February 2026
Conaptodeveloper, October 2025
Conaptodeveloper, June 2026Checked 10 Oct 2026
EcoDataCenter 1 Hall E, new timber data hall, VästermalmEcoDataCenterVästermalm, FalunNot disclosedThe existing EcoDataCenter 1 site page lists 80 MW total available power; no figure is given for the new hall.Under construction
Byggpartner contracted to build Hall E, a new timber data hall worth about SEK 300 million, with construction starting immediately, May 2025Expected: December 2026
Byggvärldentrade press, May 2025
EcoDataCenterdeveloper, 2026
Byggvärldentrade press, June 2026Checked 10 Oct 2026
Google data centre, HorndalGoogleHorndal, Avesta Municipality, DalarnaNot disclosedTrade press reports plans for up to five server halls.Under construction
Groundbreaking for Google's first Swedish data centre, following a building permit reported in March 2026, June 2026
Googledeveloper, June 2026
Byggvärldentrade press, March 2026
Byggvärldentrade press, June 2026Checked 10 Oct 2026
ScandiDC IScandinavian Data Centers (with Fastighets AB Balder)Eskilstuna (former Second World War rock cavern)6 MWIT load, phase one ("upp till 6 MW")Contractor appointed
Enaco named construction partner for the first data centre in a 6,400 sq m rock cavern, December 2025Expected: Ready for occupancy in Q4 2026
Byggvärldentrade press, December 2025Checked 10 Oct 2026
atNorth SWE04, Hamre Industrial ParkatNorthHamre Industrial Park, Långsele, Sollefteå Municipality300 MWsite power capacityThe developer FAQ on the same page gives a path to power of 200MW on 4 hectares, which differs from the 300 MW and 50 hectare figures stated elsewhere on the page.Permitted
Sollefteå Municipality reports that construction start is approaching on the zoned Hamre Industrial Park site and hosts an atNorth briefing on plans and timetable on 16 October 2026, October 2026Expected: Operational in the first half of 2028 (per W.Media)
atNorthdeveloper, 2026
W.Mediatrade press, February 2026
Sollefteå kommunauthority, October 2026
Byggvärldentrade press, June 2026Checked 10 Oct 2026
Google data centre, Torsboda Industrial ParkGoogle (DSC International AB)Torsboda Industrial Park, Timrå Municipality (jointly owned by Timrå and Sundsvall)1,000 MWpotential power available at the Torsboda site, as stated by Timrå Municipality (not a Google capacity figure)Site of about 214 hectares, of which about 140 hectares have a detailed plan. Google still needs environmental, land and building permits.In planning
Timrå and Sundsvall councils approved on 17 August 2026 the transfer of Torsboda Industrial Park AB to DSC International AB, a Google group company; a private individual appealed the Timrå decision to the Administrative Court in Härnösand, which affects when the transfer can be completed, September 2026Expected: Transaction was planned to close in October 2026, subject to ISP review, legal force of the council decisions and a power agreement with E.ON; the appeal affects the timing
Timrå kommunauthority, September 2026
Timrå kommunauthority, June 2026
Byggvärldentrade press, June 2026Checked 10 Oct 2026
EcoDataCenter third campus, RöbackenEcoDataCenterRöbacken industrial area, Smedjebacken Municipality, Dalarna150 MWcampus power the developer says has the green light from the start ("an immediate 150MW")Developer says there is a credible opportunity to expand further; no further figure given.In planning
Land purchase agreement for 52 hectares signed with Smedjebacken Municipality; building and environmental permits anticipated to be finalised in early 2027, August 2026Expected: Construction to begin once building and environmental permits are finalised, anticipated in early 2027
EcoDataCenterdeveloper, August 2026
W.Mediatrade press, August 2026
Byggvärldentrade press, June 2026Checked 10 Oct 2026
EcoDataCenter NorrsundetEcoDataCenterNorrsundet, Gävle MunicipalityNot disclosedIn planning
Consultation under chapter 6 of the Environmental Code ahead of a permit application for a data centre services facility; comments requested by 11 October 2026, October 2026
EcoDataCenterdeveloper, October 2026Checked 10 Oct 2026
EdgeConneX Skellefteå campus (former Lyten site)EdgeConneXFormer Northvolt industrial area, Skellefteå1,000 MWpotential campus capacity ("up to one gigawatt")Developer gives the figure as potential capacity, conditional on administrative and regulatory processes.Announced
Plan to acquire the Lyten data centre site announced; trade press later reported the land purchase from Lyten, September 2026
EdgeConneXdeveloper, February 2026
Byggvärldentrade press, September 2026Checked 10 Oct 2026
Brookfield AI centre, SträngnäsBrookfieldSträngnäs750 MWplanned capacity (raised from 300 MW)Announced
Investment of up to SEK 95 billion announced, June 2025Expected: 10 to 15 year construction process; construction start listed for 1 September 2028 (Byggfakta, June 2026)
Brookfield (GlobeNewswire)developer, June 2025
Byggvärldentrade press, June 2026Checked 11 Oct 2026
atNorth SWE02atNorthKista, Stockholm30 MWcapacityAnnounced
Project announced, January 2026Expected: Q4 2027
atNorthdeveloper, January 2026Checked 10 Oct 2026

Greece

Greece: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Digital Realty ATH4 (Athens 4)Digital RealtyKoropi, Attica6.8 MWadded capacity to the company's energy footprint, basis not specifiedStructure complete
Inauguration of ATH4 planned for November 2026, October 2026Expected: Inauguration in November 2026
OT.grtrade press, October 2026
Naftemporikipress, August 2025Checked 10 Oct 2026
DATA4 Athens campus, first data centreDATA4Paiania, East Attica (Agiou Louka 33)6 MWinitial IT capacity of the first data centreIT capacity to rise to 15 MW; DATA4 states 90 MW of available electricity reserves for the campusStructure complete
First data centre expected to enter operation within weeks; second phase due within 2027, October 2026Expected: Go live within the following weeks (as of 3 Oct 2026); phase 2 within 2027
OT.grtrade press, October 2026
DATA4developer, 2026Checked 10 Oct 2026
Microsoft Greece cloud region data centresMicrosoft (one facility) with partners (two facilities)Spata and Paiania, East Attica25 MWtotal capacity of the Microsoft data centre investment in East Attica, as reported by ot.grSource does not say whether the 25 MW covers all three facilities; Microsoft has published no MW figureUnder construction
Microsoft states its three data centre campus, one built by Microsoft and two by partners, is expected to be ready in Q4 2027; facilities in Spata and Paiania reported under construction, October 2026Expected: Campus ready in Q4 2027; customer use from early 2028 (ot.gr, Oct 2026)
OT.grtrade press, October 2026
Naftemporikipress, January 2025
OT.grtrade press, January 2026Checked 10 Oct 2026
Data In Scale Spata data centreData In Scale (DAMAC/Edgnex 55%, PPC 45%)Spata, East Attica (opposite Smart Park)12.5 MWinitial capacity of the first phasePotential expansion to 25 MW per the same sourcesUnder construction
Works started on the Spata site, August 2025Expected: Completion in 2026 (ot.gr, Aug 2025)
OT.grtrade press, August 2025
Naftemporikipress, April 2025
OT.grtrade press, September 2026Checked 10 Oct 2026
Lancom data centre HeraklionLancomHeraklion, CreteNot disclosedUnder construction
Reported building a new data centre in Heraklion in March 2025; reported in September 2026 as developing a second data centre in Crete, location not named, September 2026
OT.grtrade press, March 2025
OT.grtrade press, September 2026
Lancomdeveloper, 2026Checked 10 Oct 2026
PPC data centre at former Agios Dimitrios lignite plant (AWS lease)PPC (DEI); Amazon Web Services as tenantAgios Dimitrios, Kozani, Western Macedonia300 MWsupply power (ισχύ τροφοδοσίας) of the first phaseParties plan to explore expansion up to 1 GW subject to further agreements; first phase to be built in four 75 MW modules per ot.grIn planning
Binding memorandum of cooperation signed with AWS for a 15 year lease; permit pre-approval secured, environmental study under way and grid connection application submitted, September 2026Expected: First 300 MW phase operational by end of 2028 (ot.gr); first commercial applications expected from 2027
OT.grtrade press, September 2026
OT.grtrade press, September 2026Checked 10 Oct 2026
Karatzis data centre at KryoneriKaratzi Data Centers S.A. (Karatzis Group)Kryoneri, Municipality of Dionysos, Attica39.072 MWinstalled capacity (26.090 MW IT equipment plus 12.982 MW electromechanical)Earlier plan for the same site under Tectum S.A. was 19.53 MWIn planning
New Environmental Impact Study put out for public consultation, October 2026Expected: 18 month construction programme; no calendar dates given
Naftemporikipress, October 2026Checked 10 Oct 2026
Gemini data centres (ADMIE and Serverfarm joint venture)Gemini (joint venture of ADMIE/IPTO and Serverfarm)Wider Athens area and other ADMIE properties130 MWtotal capacity of the planned data centres (up to)Stated as up to 130 MW across several sitesAnnounced
Joint venture agreement signed to build and operate data centres on ADMIE properties, December 2024
Naftemporikipress, December 2024
OT.grtrade press, March 2025Checked 10 Oct 2026
Kiefer data centre MegalopoliKieferMegalopoli, Arcadia10 MWcapacity, basis not specifiedAnnounced
Reported as expected to begin operation in early 2027, focused on AI applications, October 2026Expected: Operation expected in early 2027
OT.grtrade press, October 2026Checked 10 Oct 2026
Quadrivium Digital Hellas interconnection data centre ChaniaQuadrivium Digital Hellas (Prodea REIC to take 30%)Chania, Crete7 MWdata centre capacity (δυναμικότητα), basis not specifiedFuture expansion possible per the sourceAnnounced
Prodea REIC reported to plan a 30% stake in Quadrivium Digital Hellas and a bond loan of up to EUR 15 million; project in early stages, May 2026
Naftemporikipress, May 2026Checked 10 Oct 2026
Digital Realty ATH5 (Athens 5)Digital RealtyAthens area, site not stated by sourceNot disclosedAnnounced
Digital Realty preparing ATH5, with construction possibly starting within 2027, October 2026Expected: Construction start possibly within 2027
OT.grtrade press, October 2026
OT.grtrade press, September 2026Checked 10 Oct 2026

Italy

Italy: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Digital Realty Rome campus (ROM1), TrigoriaDigital RealtyVia delle Testuggini, former Acea management centre, Trigoria, Municipio IX, Rome, Lazio35.2 MWcampus IT capacity across six buildings on 22 haFirst building ROM1: 3.2 MW IT in four modules (CorCom, December 2025 and October 2026).Under construction
Construction site of the first building ROM1 opened to visitors; Techbau appointed EPC contractor in December 2025, October 2026Expected: First phase to be completed by 2027
CorCom (Corriere Comunicazioni)trade press, October 2026
CorCom (Corriere Comunicazioni)trade press, December 2025
LineaEDPtrade press, September 2025
CorCom (Corriere Comunicazioni)trade press, August 2024Checked 10 Oct 2026
Planetel new Padua data centrePlanetelPadua, VenetoNot disclosedInvestment about EUR 7 million.Under construction
Works started on the new data centre in Padua, December 2025Expected: Works to be completed by November 2026
Soldionlinepress, December 2025Checked 10 Oct 2026
Rai Way Hyperscale Data Center PomeziaRai WayPomezia, Metropolitan City of Rome, Lazio (site of about 140,000 m2)35.2 MWIT capacity, four modules of 8.8 MW eachSource says capacity can be expanded further; separate 5.5 MW photovoltaic plant in authorisation.Permitted
Project presented at MIMIT; building permit recently received, March 2026Expected: Development timing still to be defined
CorCom (Corriere Comunicazioni)trade press, March 2026Checked 10 Oct 2026
Aruba Hyper Cloud Data Center campus Rome, remaining buildingsAruba S.p.A.Tecnopolo Tiburtino, Rome, Lazio30 MWcampus IT power at full build out (five independent buildings of 6 MW IT each)First building (IT4) inaugurated October 2024; this row covers the buildings not yet in service. No MW is published for the remaining phase alone. Clearance date and procedure type not stated by the source.Permitted
Reported among 14 data centre projects cleared by the Ministry of Environment and Energy Security (MASE), as the only site outside Lombardy, for new low emission modules expanding the Rome campus, November 2025
L'Indipendentepress, November 2025
Aruba (datacenter.it)developer, October 2026
Key4bizpress, January 2026Checked 10 Oct 2026
Cavour Hyperscale CampusTechbauTrino, former Galileo Ferraris power plant, Province of Vercelli, Piedmont300 MWtotal power (potenza complessiva), stated as a range of 300 to 400 MW; lower bound enteredSource states a range of 300 to 400 MW; the lower bound is entered. Investment about EUR 4 billion.In planning
Council of Ministers declared the programme of preminent national strategic interest, allowing an extraordinary commissioner to coordinate the single authorisation, July 2026Expected: Conference of services by end of 2026, single authorisation by 2027, first phase in operation in 2028
Italpresspress, July 2026
Radio Goldpress, July 2026
L'Agenda Newspress, July 2026
La Voce di Novarapress, July 2026Checked 10 Oct 2026
Colleferro hyperscale AI data centreCobra Green Hyperscale (controlled by Tendercapital)Colleferro, Metropolitan City of Rome, Lazio (76 ha site between the A1 motorway, Via Casilina and the high speed rail line)150 MWelectrical power assigned by grid operator TernaSources also cite about 34 MW of on site photovoltaic generation, which is separate and not included.In planning
Colleferro city council approved the project with no votes against; VIA, AIA and the final MASE authorisation are still to be obtained, August 2026Expected: Mayor says first construction sites are possible in 2027; authorisation procedures take three to six months
Key4biz (Adnkronos)press, August 2026
Italpresspress, August 2026
CorCom (Corriere Comunicazioni)trade press, August 2026Checked 10 Oct 2026
Digital Vault SulcisEnergy Vault Sulcis (Energy Vault Holdings)Nuraxi Figus, Gonnesa, former Monte Sinni coal mine, South Sardinia30 MWmaximum data centre capacity ('capacità fino a 30 MW'); source does not state whether IT load or grid powerFirst phase of about 20 MW. L'Indipendente reports 100 MW for AI at full capacity; not used. Investment about EUR 1.49 billion.In planning
Council of Ministers declared the project of preminent national strategic interest; extraordinary commissioner to coordinate the single authorisation, August 2026Expected: First phase then modular expansion over about ten years
Italpresspress, August 2026
Sardinia Postpress, August 2026
L'Indipendentepress, August 2026Checked 10 Oct 2026
Torrazza Piemonte former Fornaci site data centreNot named in source (investors)Torrazza Piemonte, former Fornaci area on Traversa Mazzini, Metropolitan City of Turin, PiedmontNot disclosedIn planning
Municipal council unanimously approved a non variant modification to the town plan for the data centre on the abandoned former kiln site, August 2026
Prima Chivassopress, August 2026Checked 10 Oct 2026
Moncalieri former ILTE site data centreNot named in sourcesMoncalieri, former ILTE printing works, Metropolitan City of Turin, Piedmont576 MWtotal planned electrical powerAnnounced
Project for four buildings on about 270,000 m2 at the former ILTE area made public; Piedmont region preparing a data centre law, September 2026
L'Agenda Newspress, September 2026
Quotidiano Piemontesepress, October 2026Checked 10 Oct 2026
Adriatic DC BrindisiAdriatic DCBrindisi industrial area, Puglia500 MWplant capacity as announcedPart of a programme stated above 2 GW in Puglia; no grid or permit status published.Announced
500 MW Brindisi plant announced within the Puglia Data Center Valley programme, June 2025
CorCom (Corriere Comunicazioni)trade press, June 2025
Key4bizpress, July 2026Checked 10 Oct 2026
Adriatic DC BariAdriatic DCBari, former Manifattura Tabacchi, Puglia200 MWdata centre capacity as announcedPart of a programme stated above 2 GW in Puglia. Key4biz (July 2026) still lists the Bari conversion among project hypotheses.Announced
Plan announced to convert the former Manifattura Tabacchi into a 200 MW data centre, June 2025Expected: First construction sites expected by end of 2026
CorCom (Corriere Comunicazioni)trade press, June 2025
Key4bizpress, July 2026Checked 10 Oct 2026
TIM new Rome area data centreTIM (TIM Enterprise)Near Rome, Lazio (site not specified)25 MWfacility capacity: adds 25 MW to TIM group capacity (125 MW total); W.Media describes a 25MW facility in RomeAnnounced
Announced EUR 130 million data centre near Rome; restated as a 25MW Rome facility in the TIM Enterprise EUR 1 billion data centre plan (October 2025), November 2024Expected: Operational by end of 2026
Key4bizpress, November 2024
W.Mediatrade press, October 2025Checked 10 Oct 2026
UniCenter Tier IV green data centreUniCenter S.p.A. (Unidata 25%, Fondo Infrastrutture per la Crescita ESG managed by Azimut Libera Impresa SGR 75%)Rome, Lazio (site not specified)20 MWcapacity of approximately 20 MW (developer release)Over 2,000 racks on 13,000 sqm; initial investment EUR 57 million.Announced
UniCenter S.p.A. established to build and operate a wholesale Tier IV data centre in Rome, March 2026
Unidata S.p.A.developer, March 2026
W.Mediatrade press, April 2026Checked 10 Oct 2026
Umbria Data Garden, PietrafittaUmbria Data Garden (study and design funded by Foro delle Arti)Pietrafitta, Valnestore, between Piegaro and Panicale, Province of Perugia, Umbria (former Pietrafitta power plant site, owned by the municipalities of Piegaro and Panicale)6 MWhypothesised data centre size, stated as a rangeSource gives a range of 6 to 9 MW; lower bound entered. Final builder and operator undecided; investment estimated at about EUR 100 million.Announced
Concept presented on 16 September 2026; study and design phase, no business plan yet, September 2026Expected: Best case ready between late 2029 and 2030
EconomyUppress, September 2026Checked 10 Oct 2026
Figline Valdarno former Bekaert site data centreH2-Era Green Valley with ComtelFigline e Incisa Valdarno, former Bekaert site, Metropolitan City of Florence, TuscanyNot disclosedAnnounced
Memorandum of understanding signed between Comtel and H2-Era Green Valley; final ministerial authorisations for the site awaited, August 2026Expected: Investors hope approvals arrive by end of 2026; photovoltaic park to be built first
Valdarnopostpress, August 2026
Rinnovabili.ittrade press, August 2026Checked 10 Oct 2026
Insiel new regional data centre, PalmanovaInsiel S.p.A. (in house company of Regione Friuli Venezia Giulia)Protezione Civile campus, Palmanova, Province of Udine, Friuli Venezia GiuliaNot disclosedAnnounced
Design contract signed with a professional group led by ATI Project; technical and economic feasibility project being drafted ahead of an integrated works tender, March 2025
Il Friulipress, March 2025Checked 10 Oct 2026
Mediterra PMO01 Carini expansionMediterra DataCentersCarini, Metropolitan City of Palermo, SicilyNot disclosedExisting site (former Open Hub Med) is live; row covers the announced capacity expansion only. The EUR 20 million plan also includes asset acquisition and upgrades to existing infrastructure.Announced
Announced an investment of over EUR 20 million by end of 2026 at PMO01 covering acquisition of local assets, upgrade of existing infrastructure and expansion of current data centre capacity, September 2026Expected: Investment by end of 2026
BlogSiciliapress, September 2026
LineaEDPtrade press, September 2026Checked 10 Oct 2026

Madrid

Madrid: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Madrid Getafe (Phase I)Merlin Properties (operated by Edged)Getafe, Comunidad de MadridNot disclosedPhase I totals 64 MW IT across the Madrid, Barcelona and Basque Country data centres; no Getafe figure given. Nebius leased 18 MW at the Getafe campus (Sept 2026); phase not specified.Structure complete
Phase I fully equipped and let; Getafe will start operating once electrical connections expected in Q4 2026 are completed, July 2026Expected: Electrical connections expected Q4 2026
Merlin Propertiesdeveloper, July 2026
Brains Real Estatetrade press, September 2026Checked 10 Oct 2026
Apto Madrid campus FuenlabradaApto (with Arnaiz; grid access by IGNIS)Fuenlabrada, Comunidad de Madrid240 MWfinal campus power (5 data centres); basis not specifiedSource also cites a 40 MW on site substation already enabled and a second phase of 122 MW. July 2026 IGNIS agreement covers 82 MW of grid access and connection capacity.Under construction
Site cleared and immediate construction phase started; IGNIS agreement signed in July 2026 to secure 82 MW grid access and connection with a 94 MW PV plant, July 2026
Data Center Markettrade press, March 2026
Data Center Markettrade press, July 2026Checked 10 Oct 2026
ADC3 (Alcalá Data Center 3)NabiaxAlcalá de Henares, Comunidad de Madrid100 MWIT capacity, up to, deployed in phasesSource says up to 100 MW IT, deployed progressively until 2029. The same article says Nabiax will reach 135 MW of installed IT power in Spain.Under construction
Construction of ADC3 started with a first stone ceremony; works awarded to Ferrovial; the project completes the expansion of the Alcalá de Henares campus, September 2026Expected: Fully operational in phases through 2029
Data Center Markettrade press, September 2026Checked 10 Oct 2026
Madrid campus MAD-2 to MAD-8 (remaining phases)Iron Mountain Data CentersSan Fernando de Henares, Comunidad de Madrid79 MWapproved IT capacity, full campusMAD-1 is operating with 3 MW per the developer page (2 MW first phase per Mar 2025 press). Remaining buildings per developer page: MAD-2 and MAD-3 at 10 MW each, MAD-4 and MAD-5 at 10 MW each, MAD-6 to MAD-8 at 12 MW each. Developer op ed (Jul 2025) refers to the remaining 76 MW. Delivery dates differ between sources: 2026 and 2027 in the Jul 2025 op ed, 2027 to 2030 on the developer page.Under construction
Developer reports accelerated construction of the remaining 76 MW of the Madrid campus, July 2025Expected: MAD-2 and MAD-3 in 2027; MAD-4 and MAD-5 in 2029; MAD-6 to MAD-8 in 2029 to 2030 (developer page)
Iron Mountaindeveloper, 2026
Data Center Market (op ed by Iron Mountain Data Centers)trade press, July 2025
Data Center Markettrade press, March 2025Checked 10 Oct 2026
MAD02 campus (building DC02)Data4San Agustín del Guadalix, Comunidad de Madrid50 MWcampus power as listed by developer; basis not specifiedDeveloper page lists 50 MW for MAD02 on 6.7 hectares; DC02 building capacity not given.Under construction
Campus reported under construction; BREEAM Excellent design stage certification obtained for building DC02, September 2025
Data Center Markettrade press, September 2025
Data4developer, 2026Checked 10 Oct 2026
Madrid Getafe IIMerlin Properties (operated by Edged)Getafe, Comunidad de Madrid48 MWas stated by developer for the second Getafe data centre; basis not specified (Phase II total of 254 MW is given as MW IT)Under construction
Developer reports works progressing at Madrid Getafe II after demolition and a construction licence request earlier in 2026, July 2026
Merlin Propertiesdeveloper, February 2026
Merlin Propertiesdeveloper, July 2026
Brains Real Estatetrade press, September 2026Checked 10 Oct 2026
MAD01 Meco (Phase 1)Pure DCMeco, Comunidad de Madrid30 MWPhase 1 capacityTotal site capacity 70 MW; Phase 2 of 40 MW subject to permitting. Sale of the 18,000 m2 plot reported July 2024; the seller had secured a 25 MW electrical power contract in 2022.Under construction
Phase 1 fully permitted and under construction; developer lists a planning approval news item dated 26 November 2025, November 2025
Pure DCdeveloper, 2026
Data Center Markettrade press, July 2024Checked 10 Oct 2026
Madrid Tres CantosMerlin PropertiesTres Cantos, Comunidad de Madrid30 MWas stated by developer; basis not specified (Phase II total of 254 MW is given as MW IT)Under construction
Developer reports works progressing at Madrid Tres Cantos after an urbanisation permit request in early 2026, July 2026
Merlin Propertiesdeveloper, February 2026
Merlin Propertiesdeveloper, July 2026Checked 10 Oct 2026
Quetta Tres CantosQuetta Data Centers (Azora and Core Tech Capital)Tres Cantos, Comunidad de Madrid20 MWplanned power, as reported from the companySource says planned power has doubled to 20 MW; earlier figure not stated.Under construction
Construction works started, December 2025
Data Center Markettrade press, December 2025Checked 10 Oct 2026
Ferrovial data centre campus, MAD 01 first phaseFerrovialAvenida Monte de Valdelatas 10 16, Valdelacasa, Alcobendas60 MWfirst phase (MAD 01) powerTotal campus stated as more than 100 MW; investment 1,000 million euros.Permitted
Earthworks licence obtained and first phase declared a Proyecto de Especial Interés by the Comunidad de Madrid investment accelerator, July 2026
Brains Real Estatetrade press, July 2026
idealista/newspress, July 2026Checked 10 Oct 2026
ACS data centre site Alcalá de HenaresACSAlcalá de Henares, Comunidad de MadridNot disclosedPart of a 12,000 million euro programme across Alcalá de Henares, Madrid municipality and Zaragoza.Permitted
Land reported to have all permits and grid access for data centre development, January 2025Expected: Investment over the next 5 to 7 years (programme)
idealista/news (Europa Press)press, January 2025Checked 10 Oct 2026
Ignis Data Beta IIIgnisVillalbilla, Comunidad de Madrid181 MWdata centre capacity as stated; basis not specifiedLinked to seven solar parks and a planned 220 kV substation (SET Beta II).In planning
Project completed the public information stage before Madrid authorities, February 2026
Brains Real Estatetrade press, February 2026Checked 10 Oct 2026
Madrid SurEchelon Data Centres and Iberdrola joint venture (Echelon Iberdrola Digital Infra)South of Madrid (municipality not stated)144 MWinitial operational capacitySecured grid connection of 230 MW on a 160,000 m² site.Announced
Iberdrola confirmed the joint venture with Echelon, with Madrid Sur as its first project; the JV starts activity once regulatory approvals are obtained, November 2025Expected: Operational before 2030
idealista/newspress, July 2025
idealista/newspress, November 2025Checked 10 Oct 2026
Edgnex Madrid data centreEdgnex (DAMAC Group)Madrid region, about 15 km from the city centre (municipality not stated)40 MWelectricity supply rights (10 MW immediate, 30 MW additional for Q1 2026)Announced
Plot of almost 23,000 m2 with ratified 40 MW power supply rights bought from ASG Iberia; investment of more than 400 million euros planned, October 2024
idealista/newspress, October 2024Checked 10 Oct 2026
Madrid Campus MAD01Prime Data CentersCalle de la Pedriza 1, Alcobendas40 MWcritical power (critical IT load)Announced
Plans announced after securing 7.6 acres; site page lists MAD01-01 as in development, May 2024
Prime Data Centersdeveloper, May 2024
Prime Data Centersdeveloper, 2026Checked 10 Oct 2026
Nostrum GuadalajaraNostrum Data Centers (Nostrum Group)Polígono El Ruiseñor, Guadalajara (Castilla La Mancha)40 MWelectrical power already granted (allows up to 29 MW IT)Marketed as a few kilometres from Madrid and the Corredor del Henares.Announced
About 2 hectares secured and 40 MW power granted; project presented to municipal authorities; design by IDOM, February 2026Expected: Works start planned for end of 2026; operation in 2028
Data Center Markettrade press, February 2026Checked 10 Oct 2026
Templus Alcalá de Henares expansionTemplusAlcalá de Henares, Comunidad de Madrid20 MWtarget site power after expansion (10 MW current)The operating 16,000 m2 site houses two symmetrical data centres and has 10 MW today; the row covers the planned increase to 20 MW.Announced
Plan announced to double the site from 10 MW to 20 MW in the medium term, September 2025Expected: Medium term (no date given)
Data Center Markettrade press, September 2025Checked 10 Oct 2026
Vaultica Madrid (Los Salobrales)Vaultica Data CentersPolígono Los Salobrales, Alcalá de Henares12 MWinstalled IT capacity, up toAnnounced
New data centre announced within an existing industrial complex, with two grid connections from two substations, April 2026
Data Center Markettrade press, April 2026Checked 10 Oct 2026
Digital Realty new Madrid data centre (Julián Camarillo)Digital Realty (Interxion)Polígono Julián Camarillo, San Blas Canillejas, MadridNot disclosedSource gives a range of 20 to 40 MW for the planned centre.Announced
Fifth plot acquired in the Julián Camarillo area for a new data centre, April 2025
idealista/newspress, April 2025
Brains Real Estatetrade press, April 2025Checked 10 Oct 2026
Nostrum PintoNostrum Data Centers (Nostrum Group)Pinto, Comunidad de MadridNot disclosedSix site programme totals 500 MW IT plus 300 MW for future expansion; no Pinto figure.Announced
Pinto named among six planned sites, all with land and power secured, January 2026Expected: Operational during 2027 (programme target)
Brains Real Estatetrade press, January 2026
idealista/newspress, January 2026Checked 10 Oct 2026
Spanish AI gigafactory bid (Madrid site)Public private consortium with SETT (Sociedad Española para la Transformación Tecnológica)San Fernando de Henares, Comunidad de MadridNot disclosedMulti site bid with Móra la Nova (Tarragona); outcome depends on the EU InvestAI call.Announced
Council of Ministers authorised the state investment for the bid, June 2026
Data Center Markettrade press, June 2026
Data Center Markettrade press, January 2026Checked 10 Oct 2026

Milan

Milan: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
CyrusOne MIL1CyrusOneSegrate, Metropolitan City of Milan27 MWIT capacity (three 9 MW data halls)Release describes MIL1 as the first of two CyrusOne data centres planned for Milan; MIL2 is listed separately.Under construction
CyrusOne announced it had broken ground on MIL1, its first data centre in Italy, March 2026
CyrusOnedeveloper, March 2026Checked 10 Oct 2026
Vantage MXP1 (completion of campus)Vantage Data Centers (project company VDC MXP11 S.r.l.)Melegnano, Metropolitan City of Milan64 MWcritical IT load at full campus build-outThe 64 MW figure is from the Vantage campus page (four data centres once fully developed); the regional decision gives no MW. The regional decision covers completion of MXP1 and its emergency power system, with a technology building, fire station and receiving substation. The regional favourable opinion is a step in the authorisation process; no final permit was found.In planning
Lombardy regional government adopted a resolution giving a favourable opinion on the project to complete the MXP1 data centre and its emergency power supply, May 2025Expected: Construction estimated at 600 to 650 days (per Regione Lombardia)
Lombardia Notizie (Regione Lombardia)authority, May 2025
Vantage Data Centersdeveloper, 2026Checked 10 Oct 2026
Eni and Khazna AI Data Center Campus, Ferrera ErbognoneEni and Khazna Data Centers (planned joint venture)Ferrera Erbognone, Province of Pavia, Lombardy500 MWtotal IT capacity of the campusFebruary 2025 Eni release described the first project as built in two phases of up to 500 MW of IT capacity, within a planned Italian programme of up to 1 GW IT capacity with MGX and G42.Announced
Khazna Data Centers and Eni signed Heads of Terms to set up a joint venture for the campus; Eni states development activities are under way, July 2025
Enideveloper, July 2025
Enideveloper, February 2025Checked 10 Oct 2026
CyrusOne MIL2CyrusOneMilan and Segrate (site spans both municipalities)54 MWIT capacitySource also states a 90 MVA grid supply at 220 kV from 2028; that figure is grid supply, not IT load.Announced
CyrusOne announced MIL2 after acquiring a 19.68 acre site, April 2025Expected: Power supply of 90 MVA at 220 kV from 2028 (per CyrusOne); no opening date stated
CyrusOnedeveloper, April 2025Checked 10 Oct 2026
Vantage MXP2Vantage Data CentersCastelletto, Settimo Milanese, Metropolitan City of Milan32 MWcritical IT capacity across two data centresVantage places the campus in Castelletto, about 15 km from central Milan; its listed address is in Settimo Milanese. First phase was slated to be operational in spring 2026; the row covers the campus build, including the second phase for which no date is given. Release does not state that construction has started, so the stage is set at announced.Announced
Vantage announced its second Milan campus, MXP2, with an investment of more than EUR 350 million, October 2025Expected: First phase slated to be operational in spring 2026 (per Vantage); no date for the second phase
Vantage Data Centersdeveloper, October 2025
Vantage Data Centersdeveloper, 2026Checked 10 Oct 2026

Portugal

Portugal: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
MERLIN Edged Lisbon AI Campus, Phase III (Lisbon VFX 03, 04 and 05)MERLIN Properties with EdgedCastanheira do Ribatejo, Vila Franca de Xira100 MWtotal for the three additional data centres as stated by MERLIN (basis not specified in the sentence)Under construction
Construction licence obtained and ground preparation begun; piling works and soil preparation progressing, ready for service brought forward to the first half of 2029 after decision to build the three buildings simultaneously, July 2026Expected: Ready for service in the first half of 2029
MERLIN Propertiesdeveloper, July 2026
MERLIN Propertiesdeveloper, May 2026Checked 10 Oct 2026
MERLIN Edged Lisbon AI Campus, Phase II (two data centres)MERLIN Properties with EdgedCastanheira do Ribatejo, Vila Franca de Xira80 MWIT capacity, two data centres of 40 MW each (MERLIN Phase II)Edged describes the full campus as 180 MW of critical capacity across five connected data centres.Under construction
Works on the two 40 MW data centres progressing with the structure visible (Q1 2026 report) and still progressing at H1 2026 results, July 2026Expected: Commissioning of the 80 MW expected by the fourth quarter of 2027 (Colliers via Essential Business)
MERLIN Propertiesdeveloper, July 2026
MERLIN Propertiesdeveloper, May 2026
Edgeddeveloper, 2026
Essential Businesstrade press, May 2026Checked 10 Oct 2026
SINES Data Campus SIN03 to SIN06Start CampusSines, Setúbal district (Alentejo coast)240 MWup to 240 MW of IT capacity per building, stated in the August 2024 release for each building from SIN02 to SIN06Not summed. Campus IT capacity secured from REN stated as 1.2 GW across six buildings.Permitted
Campus stated as fully permitted for 1.2GW in the May 2026 Nscale release; transformers for SIN02 to SIN06 ordered from Siemens Energy in August 2024, May 2026Expected: All buildings expected to be operational by 2030 (August 2024 release)
Start Campusdeveloper, August 2024
Start Campusdeveloper, May 2026
Start Campusdeveloper, August 2024Checked 10 Oct 2026
SINES Data Campus SIN02 (second building)Start CampusSines, Setúbal district (Alentejo coast)200 MWcapacity of the second building as stated in the May 2026 Nscale releaseEarlier figures differ: the August 2024 Siemens Energy release and SAPO Tek (April 2025) gave SIN02 as 180 MW of IT capacity; the August 2024 REN award release gave each of SIN02 to SIN06 up to 240 MW of IT capacity. Campus total stated as 1.2 GW.Permitted
Nscale announced a EUR 465 million investment in a second 200MW building at the campus, with Vera Rubin GPU deployment for Microsoft starting in late 2027; campus stated as fully permitted for 1.2GW, May 2026Expected: GPU deployment starting in late 2027 (earlier release: SIN02 due to be ready for service in 2026)
Start Campusdeveloper, May 2026
Start Campusdeveloper, August 2024
SAPO Tekpress, April 2025Checked 10 Oct 2026
Covilhã Data Center Campus expansionAsterion Industrial PartnersCovilhã, Castelo Branco district75 MWadditional capacity through new blocks within the existing campus (source does not say IT or facility power)Existing campus has 6.8 MW installed capacity. Source also cites a further opportunity of c.175 MW on adjacent land with power already secured.Announced
Asterion agreed to acquire the Covilhã campus from Altice Portugal for EUR 120m with plans to add new blocks; closing expected in the first quarter of 2026, November 2025
Asterion Industrial Partnersdeveloper, November 2025
Essential Businesstrade press, May 2026Checked 10 Oct 2026
AtlasEdge Lisbon campus, LIS002 and LIS003AtlasEdgeCarnaxide, Lisbon Metropolitan Area16 MWLIS002 future power available, as listed on the AtlasEdge Lisbon pageCampus stated as 30MW across three phases; LIS001 (in operation, 5.1MW) and LIS002 given a combined 21.1MW in the October 2025 release; LIS003 capacity not stated.Announced
EUR 190 million Facility B secured to fund LIS002 construction; LIS002 in master planning; adjoining 10,000 square metre plot acquired for LIS003, October 2025Expected: LIS002 Ready for Service scheduled for 2028
AtlasEdgedeveloper, October 2025
AtlasEdgedeveloper, 2026Checked 10 Oct 2026

Spain

Spain: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
SP01Alto Infrastructure (formerly Sierra DC)CITAI technology park, Escúzar, Granada, Andalusia100 MWgranted gross power (about 70 MW IT)Phase one 10 MW IT and 15 MW gross; 25 MW IT and 40 MW gross before end of 2027Under construction
Works started on site, June 2026Expected: First phase summer 2027; full development end of 2029
El Español (Invertia)press, June 2026Checked 10 Oct 2026
Bilbao-Arasur 02Merlin PropertiesArasur, Basque Country48 MWIT capacityUnder construction
Fully let twelve months before delivery; Phase II works progressing as planned, July 2026Expected: Developer says the building was pre-let one year before delivery; no delivery date given
Merlin Propertiesdeveloper, July 2026
Merlin Propertiesdeveloper, February 2026Checked 10 Oct 2026
Bilbao-Arasur third buildingMerlin Properties (Merlin-Edged)Arasur logistics platform, Rivabellosa (Ribera Baja), Álava, Basque Country48 MWcapacity of the building as stated by the developer (basis not specified)The July 2026 release lists Bilbao-Arasur 01 (48 MW) as let eighteen months before becoming operational; the developer does not state whether this is the same buildingUnder construction
Construction licence obtained in December 2025; construction works started, as reported in the February 2026 annual results, February 2026
Merlin Propertiesdeveloper, February 2026
Merlin Propertiesdeveloper, 2026Checked 10 Oct 2026
Mediterra BCN01Mediterra DataCentersBarcelona region, Catalonia8 MWIT capacity, in 1.3 MW increments; 12 MW power connectionDeveloper page gives 8 MW as installed electricity in 1.3 MW blocksUnder construction
Site acquired with permits and power connection; construction started, February 2026Expected: Operational in the second half of 2027
W.Mediatrade press, February 2026
Mediterra DataCentersdeveloper, 2026Checked 10 Oct 2026
NxN Valencia data centreNxN Data CentersVara de Quart, Valencia, Comunitat Valenciana5 MWpower as stated by the sourceUnder construction
First stone laid and works started, February 2026Expected: Opening planned for the first half of 2027
El Españolpress, February 2026Checked 10 Oct 2026
AWS Villanueva de Gállego expansionAmazon Web ServicesVillanueva de Gállego, Zaragoza, AragónNot disclosedUnder construction
Expansion works continuing under the PIGA approved in August 2025; town council filed a second appeal against a later expansion project, August 2026
elDiario.espress, August 2026Checked 10 Oct 2026
AWS second data centre at WalqaAmazon Web ServicesWalqa technology park, Huesca, AragónNot disclosedSources give annual consumption of 2,270,600 MWh and 342 MW of diesel generator power, not a capacity figureUnder construction
Reported under construction after the Aragón government approved the building projects in May 2026, October 2026
elDiario.espress, October 2026
elDiario.espress, May 2026Checked 10 Oct 2026
Microsoft Aragón data centre campuses (La Muela, Villamayor de Gállego, Zaragoza)MicrosoftLa Muela, Villamayor de Gállego and Zaragoza (including the Puerto Venecia site), AragónNot disclosedUnder construction
Earthworks reported under way at several sites, with Microsoft stating construction would start in 2026; a PIGA modification was published in the BOA on 30 July 2026 for public consultation, October 2026Expected: First operational phase within four years of final PIGA approval
El Españolpress, October 2026
El Españolpress, November 2025
elDiario.espress, September 2026Checked 10 Oct 2026
Proyecto Rhodes data centre campusQTS (Blackstone), promoted by Calanza Inmuebles SLCalatorao, Zaragoza, Aragón650 MWplanned electrical capacity, first phaseelDiario.es gives 650 MW of planned electrical capacity for the first phase and says the figure includes cooling; the Aragón government release gives no MW figurePermitted
Aragón government gave definitive partial approval of the PIGA covering urbanisation, substation, power lines and water networks; the eight data centre buildings still await environmental assessment; no construction start date set as of October 2026, September 2026Expected: First installations to start operating in 2028 and the complex ready within seven years, per the Aragón president's stated condition (El Español)
Aragón Hoy (Gobierno de Aragón)authority, September 2026
elDiario.espress, September 2026
El Españolpress, October 2026Checked 10 Oct 2026
Meta Talavera de la Reina data centre campusMeta (Zarza Networks SL)Torrehierro industrial estate phase two, Talavera de la Reina, Toledo, Castilla-La ManchaNot disclosedPermitted
Definitive approval of the land reparcelación published in the DOCM; regional government approvals in place for works to start, August 2026
El Español (El Digital Castilla-La Mancha)press, August 2026
elDiario.espress, September 2026Checked 10 Oct 2026
Tillion Aragón data centre campusAzoraVillamayor de Gállego, Zaragoza, AragónNot disclosedPermitted
PIGA approved in July 2026; agreement in principle reached in October 2026 for the town council to withdraw its court appeal against the PIGA, pending formal steps, October 2026Expected: Urbanisation works to start at the end of 2026 or during 2027 (El Español)
El Españolpress, October 2026
El Españolpress, October 2026Checked 10 Oct 2026
La Puebla de Alfindén data centre campusACS with BenbrosLa Puebla de Alfindén, Zaragoza, Aragón150 MWinitial capacity as stated by ACSIn planning
Initial approval of the PIGA published in the BOA on 2 December 2025, December 2025Expected: Urbanisation works to start at the end of 2026 or during 2027 (El Español)
El Españolpress, October 2026
El Españolpress, September 2026Checked 10 Oct 2026
Zaragoza-WIND data centre campusMerlin Properties (Merlin-Edged)Botorrita (Polígono Industrial San Antonio), Zaragoza, Aragón144 MWIT capacity, single buildingAragón government also cites guaranteed power of 227.4 MW and possible expansion to 240 MW IT subject to energy availabilityIn planning
Aragón government approved the DIGA (declaration of investment of regional interest) for the campus, July 2026Expected: Operation planned for the second half of 2029
Merlin Propertiesdeveloper, July 2026
Aragón Hoy (Gobierno de Aragón)authority, July 2026Checked 10 Oct 2026
AWS Aragón consolidation sitesAmazon Web ServicesLa Puebla de Híjar and Azaila (Teruel), Huesca and San Mateo de Gállego (Zaragoza), AragónNot disclosedIn planning
Consolidation projects at DIGA stage; AWS raised its planned Spanish investment to 33.7 billion euros in March 2026, October 2026
El Españolpress, October 2026
Amazon (aboutamazon.es)developer, April 2026Checked 10 Oct 2026
Bilbao-Arasur 04 and 05Merlin Properties (Merlin-Edged)Arasur logistics platform, Rivabellosa (Ribera Baja), Álava, Basque CountryNot disclosedPart of Merlin Phase III (406 MW IT across several sites); no site figure publishedIn planning
Construction licence requested, July 2026
Merlin Propertiesdeveloper, July 2026
Merlin Propertiesdeveloper, 2026Checked 10 Oct 2026
EpilonBox2BitÉpila, Zaragoza, AragónNot disclosedIn planning
Project at DIGA stage in the Aragón regional approval process, October 2026
El Españolpress, October 2026Checked 10 Oct 2026
Green It AragónSAMCALuceni, Zaragoza, Aragón (associated wind farm upgrades in Pedrola, Plasencia de Jalón and Rueda de Jalón)Not disclosedIn planning
In the PIGA process; committed investment updated to 2,627 million euros after the renewable supply component was added to the processing, October 2026Expected: Urbanisation works to start at the end of 2026 or during 2027 (El Español)
El Españolpress, October 2026
El Españolpress, August 2026Checked 10 Oct 2026
Vantage Villanueva de Gállego campusVantage Data CentersVillanueva de Gállego, Zaragoza, AragónNot disclosedIn planning
Campus at DIGA stage in the Aragón regional approval process, October 2026
El Españolpress, October 2026Checked 10 Oct 2026
DC VillasequillaEdgeMode and Blackberry Alternative Investment Fund (BAIF) joint ventureVillasequilla, Toledo, Castilla-La Mancha600 MWplanned capacityAnnounced
Project added to the EdgeMode and BAIF joint venture portfolio, January 2026
W.Mediatrade press, January 2026Checked 10 Oct 2026
DC TomellosoEdgeMode and Blackberry Alternative Investment Fund (BAIF) joint ventureTomelloso, Ciudad Real, Castilla-La Mancha450 MWplanned capacityAnnounced
Project added to the EdgeMode and BAIF joint venture portfolio, January 2026
W.Mediatrade press, January 2026Checked 10 Oct 2026
DC Malpica AI campusEdgeMode with BlackBerry AIFMora, Toledo, Castilla-La Mancha300 MWplanned campus capacity across two facilitiesAnnounced
Project presented to Castilla-La Mancha officials after a non-binding MoU with Mora city council; developers preparing a regional Priority Project application, July 2026
Data Center Knowledgetrade press, July 2026
W.Mediatrade press, June 2026Checked 10 Oct 2026
Nostrum EvergreenGrupo IngenostrumPlataforma Logística de Badajoz, Badajoz, Extremadura300 MWstated project capacityIREN agreed in May 2026 to acquire Nostrum Group (Ingenostrum, S.L.), citing 490 MW of secured grid connected power in Spain; completion subject to closing conditions; W.Media does not list sitesAnnounced
Data centre announced by Grupo Ingenostrum for the Plataforma Logística de Badajoz, 2025
El Español (Invertia)press, February 2026
W.Mediatrade press, May 2026Checked 10 Oct 2026
Solaria Puertollano data centreSolaria Energía y Medio Ambiente with DatasectionPuertollano, Ciudad Real, Castilla-La Mancha200 MWmaximum capacity of the planned data centre (up to)Article says the grid operator approved supply of 155 MW for data centres; Solaria seeks to raise this to 1 GWAnnounced
Memorandum of understanding signed with Datasection to adapt a Solaria plant site in Puertollano for a data centre, September 2024
Data Center Knowledgetrade press, September 2024Checked 10 Oct 2026
GUA1Nostrum Data CentersEl Ruiseñor industrial estate, Guadalajara, Castilla-La Mancha29 MWIT capacity (up to); 40 MWe electrical power already grantedAnnounced
Project presented with Guadalajara city council; 2 hectares of industrial land acquired and 40 MWe of power granted, February 2026Expected: Works to start end of 2026; operation during 2028
El Español (El Digital Castilla-La Mancha)press, February 2026Checked 10 Oct 2026
IGNIS Data Epta Segovia data centreIGNIS and Acciona joint venture (IGNIS Data Epta)Segovia, Castilla y LeónNot disclosedAnnounced
Acciona acquired 50% of the project company IGNIS Data Epta; IGNIS had already secured grid access and connection permits for the project, August 2026
W.Mediatrade press, August 2026Checked 10 Oct 2026
LusitanusFotowatio Renewable Ventures (FRV, Jameel Energy)ExpacioMérida, Mérida, Badajoz, ExtremaduraNot disclosedAnnounced
Land reservation contract formalised for a 240,000 square metre site, February 2026
El Español (Invertia)press, February 2026Checked 10 Oct 2026
Rubix Flix AI data centreRubix Data Centers (Submer Group)Former Ercros plant, Flix, Tarragona, CataloniaNot disclosedAnnounced
Project presented at a media event attended by the President of Catalonia and the Catalan business minister; Submer Group said it will invest more than 1 billion euros, July 2026
W.Mediatrade press, July 2026Checked 10 Oct 2026
Substrate AI Talavera de la Reina developmentSubstrate AI (AI European Infrastructure SOCIMI)Talavera de la Reina, Toledo, Castilla-La ManchaNot disclosedAnnounced
Substrate AI set up a real estate investment vehicle whose first development is planned in Talavera de la Reina, August 2026
W.Mediatrade press, August 2026Checked 10 Oct 2026

Croatia

Croatia: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Digital Realty Zagreb Jankomir data centre (ZAG2)Digital RealtyJankomir, Zagreb30 MWfacility capacity (up to)Source states "kapaciteta do 30 megavata". The 2023 developer statement said the land suits a centre of up to 30 MW, built in at least two phases.Under construction
Reported under construction in Jankomir with capacity of up to 30 MW, March 2024
Lidertrade press, March 2024
Lidertrade press, October 2023Checked 10 Oct 2026
Pantheon AI data and AI campus (Kampus Topusko)Pantheon AI (investors Jako Andabak and Ryan Rich; partners Končar Group and Greenvolt)Topusko, Sisak-Moslavina County1,000 MWdata centre power capacitySources state the capacity as 1 GW ("snage jednog gigavata"; "snage 1 GW"); shown here in MW. The spatial plan also covers a substation with connecting lines, solar plants and battery storage of total capacity above 20 MW; the July 2026 report cites 280 km of new power lines and a 400 kV substation in Topusko.In planning
Sisak-Moslavina County launched amendments to its spatial plan for the project and amended the decision opening the strategic environmental assessment; the environment ministry requires a main appropriate assessment for the ecological network. HOPS accepted the grid connection study in July 2026 and the connection contract signing process started, October 2026Expected: Construction start planned in 2027, operations planned for early 2029
Lidertrade press, October 2026
Lidertrade press, July 2026Checked 10 Oct 2026

Czechia

Czechia: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Prague Gateway DCČeské Radiokomunikace (CRA Prague Gateway DC)Zbraslav, Jíloviště, on the edge of Prague26 MWpower supply secured for the data centre (napájení); the source does not say whether this is IT load or total inputLupa reports the site could grow to up to 77 MW if CRA's EU AI gigafactory bid succeeds. Polarise reserved 15 MW under a letter of intent (Lupa, 9 Sept 2026).Under construction
Skanska selected to build the data centre, with works on site infrastructure, foundations and precast frame starting immediately after signing, August 2026Expected: first clients at the end of 2027
České Radiokomunikacedeveloper, July 2025
České Radiokomunikacedeveloper, August 2026
Lupa.cztrade press, September 2026
Lupa.cztrade press, July 2026Checked 10 Oct 2026
MasterDC AI data center KaniceMasterDCKanice, near Brno (former military site with a telecom nuclear shelter)25 MWtotal site capacityInitial power capacity 4 MW; the source says the site will be built in stages according to demand.Under construction
Reconstruction of the former military site was scheduled to begin in November 2025; the developer's website now states construction is underway, November 2025Expected: opening in autumn 2026 (first part)
MasterDCdeveloper, October 2025
MasterDCdeveloper, October 2026
E15press, October 2025Checked 10 Oct 2026
Iris DCBluesio Technologies (majority owned by Blue Bridge Invest)Most, Ústí nad Labem Region24 MWplanned power draw per building; two identical buildings plannedLupa states the two buildings together come to nearly 50 MW, supplied by two nearby 110 kV sources.Announced
Investors from the United Arab Emirates bought the land near Most for CZK 1 billion; they plan to offer server space to global technology companies, November 2025
E15press, November 2025
Lupa.cztrade press, November 2025Checked 10 Oct 2026
Gi21 AI data centre, northern BohemiaGi21 (investment company of Damir Špoljarič)Northern Bohemia (municipality not disclosed)20 MWcomplex capacity, split into two 10 MW buildingsAnnounced
Land arrangements being finalised next to a 110 kV substation under completion, November 2025
E15press, September 2025
Lupa.cztrade press, September 2025
Lupa.cztrade press, November 2025Checked 10 Oct 2026
Seznam.cz third data centreSeznam.czNear Prague, by the D11 motorwayNot disclosedLupa reports Seznam wants to secure several megawatts (několik megawattů) without giving a figure.Announced
Bought land near the D11 motorway from two logistics and transport companies for its third own data centre, October 2026
E15press, October 2026
Lupa.cztrade press, October 2026Checked 10 Oct 2026

Estonia

Estonia: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Nebius Tallinn AI factory at Greenergy Data CentersGreenergy Data Centers (host) with Nebius as operator of the AI factoryHüüru, Harju County22 MWfirst phaseGreenergy has stated a site potential of "up to 300 megawatts" (ERR, 31 Jul 2026); no phase or date given for that figure. Greenergy's existing facility near Tallinn (30 MW, opened 2022 per ERR, 17 Jun 2026) is not counted in this row.Under construction
Nebius announced its Tallinn AI factory at the Greenergy Data Centers site in Hüüru; the 22 MW first phase is being built, August 2026Expected: First phase of 22 MW online by the end of 2026
ERR Newspress, August 2026
ERR Newspress, August 2026
ERR Newspress, July 2026Checked 10 Oct 2026
Risti data centre campusSunly and Magnora Data Center (joint venture Risti Kampus OÜ)Risti, Lääne-Nigula Municipality, Lääne County180 MWfacility capacity; developer cites 180 MW available at the connecting substationDeveloper release names a planned expansion to up to 400 MW, which requires a substation upgrade.In planning
Magnora Data Center agreed to acquire 50% of Sunly's Risti Kampus OÜ to develop the site as a joint venture; cable route rights are in municipal proceedings, September 2026Expected: First phases could be running by 2028, per Sunly in March 2026
Sunlydeveloper, September 2026
ERR Newspress, March 2026Checked 10 Oct 2026
Evecon Lihula data centreEveconNorthwest of Lihula, Lääneranna Municipality, Pärnu County100 MWelectricity consumption (up to)Evecon's chief executive said the final capacity will be determined later.In planning
Application filed with Lääneranna Municipality to initiate a detailed spatial plan for up to six data centre buildings and a 330 kV substation on about 22.4 ha, June 2026
ERR Newspress, June 2026Checked 10 Oct 2026

Hungary

Hungary: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
AI data centre near Paks nuclear plantParTec AG and 3D Lézertechnika Zrt.Near the Paks nuclear power plant, Tolna County96 MWmaximum power consumption of the data centreThe plan includes an agro-photovoltaic park on an initial 530 hectares and battery storage.Announced
Letter of intent signed between ParTec AG and 3D Lézertechnika Zrt.; talks with a strategic financing partner reported at an advanced stage, July 2025Expected: regular operation scheduled to begin in 2027
ParTec AG (EQS News)developer, July 2025
Világgazdaság (VG.hu)press, July 2025Checked 10 Oct 2026

Latvia

Latvia: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Tet DC7 second phaseTetSalaspils5 MWtotal capacity after the second phaseFirst phase opened at 1 MW; the row covers the second phase that brings the site to 5 MW.Announced
First phase of DC7 opened at 1 MW; second phase to bring capacity to 5 MW, September 2026Expected: Second phase scheduled for completion in 2032
LSM (Latvian Public Broadcasting)press, September 2026Checked 10 Oct 2026

Lithuania

Lithuania: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Kruonis DCKruonis DC (Ignitis Group)Kruonis, Kaišiadorys District (Kruonis pumped storage plant substation)200 MWgrid connection (connection conditions)Invest Lithuania's site page gives other figures for the wider Kruonis site (200 MW and 100 MW near term); not used.Permitted
Kruonis DC and Litgrid signed a protocol of intent on connecting up to 200 MW to the Kruonis pumped storage plant substation; a €3 million guarantee secures the reserved capacity. Ignitis has launched a partner search, October 2026
Litgridauthority, October 2026
Ignitis Groupdeveloper, 2026
Invest Lithuaniaauthority, September 2026Checked 10 Oct 2026
Elektrėnai DCElektrėnai DC (Ignitis Group)Elektrėnai (Lietuvos elektrinė power plant site)Not disclosedAnnounced
Ignitis Group registered Elektrėnai DC on 2 June 2026, a company to develop, build and operate data centres linked to the Lietuvos elektrinė site; the Group has launched a partner search for Kruonis DC and possibly its other data centre companies, June 2026
LRTpress, June 2026
Ignitis Groupdeveloper, 2026Checked 10 Oct 2026

Poland

Poland: grid, power prices and rules

ProjectCapacityStage and latest milestoneSource
Gliwice municipal data centreŚląska Sieć Metropolitalna (City of Gliwice)Gliwice, between Bojkowska and Toruńska streetsNot disclosedThe city gives no power figure; it mentions two independent transformer stations and backup generators.Permitted
Administrative decision approving construction became final, March 2026Expected: By the end of 2028
City of Gliwiceauthority, April 2026
W.Mediatrade press, April 2026Checked 10 Oct 2026
Hillwood data centre campus RegułyHillwood PolskaReguły, Michałowice commune (Warsaw West)Not disclosedSite of more than 22 ha; four independent buildings planned in separate stages, starting with the smallest building closest to Aleje Jerozolimskie.Permitted
Revised campus concept published after resident feedback; the site lies in an area designated for this use in the local zoning plan, and each stage still needs separate administrative and environmental procedures, September 2026
Hillwood Polskadeveloper, September 2026
Eurobuild CEEtrade press, September 2026Checked 10 Oct 2026
DL Invest Park Bielsko-Biała data centreDL Invest Group with Boosteroid (joint venture)Bielsko-Biała, former Fiat engine plant site200 MWtarget capacity of the facilityThe site has its own 82 MW main supply point (GPZ). A May 2026 ITwiz article says the Bielsko-Biała facility was originally planned at up to 50 MW. The same article cites 300 MW of computing power for a new centre described as an expansion of the Bielsko-Biała project, without naming its site.In planning
Change to the local zoning plan under way (February 2026); in May 2026 the partners signed an agreement naming Argentum AI as operator of a planned expansion of the Bielsko-Biała project, May 2026
ITwiztrade press, February 2026
ITwiztrade press, May 2026
DL Invest Groupdeveloper, 2025Checked 10 Oct 2026
Baltic Data Center CampusWBS PowerChoczewo commune, Pomerania800 MWfirst stage capacityThe source gives 3,2 GW for the full campus. The developer is still seeking partners; the first stage cost is put at about USD 8 to 10 billion.Announced
Project announced by WBS Power; search for partners under way, March 2026
Wysokie Napięcietrade press, May 2026Checked 10 Oct 2026
Data Center KoninCentralna Grupa Energetyczna with CGE 171FFKonin, municipal investment land100 MWIT power (up to 100 MW)Wysokie Napięcie (May 2026) lists the project at 260 MW without stating a basis. ITwiz reports first stage energy use of 1 TWh. The lead investor is not named; CGE 171FF is named as second investor.Announced
Letter of intent on electricity supply signed by Energa Obrót, the City of Konin and Centralna Grupa Energetyczna, reported by ITwiz on 17 September 2026 (signing date not stated), September 2026Expected: First construction works planned for early 2027
ITwiztrade press, September 2026
Wysokie Napięcietrade press, May 2026Checked 10 Oct 2026
Data4 Warsaw campus, remaining build-outData4Jawczyce, Ożarów Mazowiecki commune (Warsaw West)60 MWtarget campus power (up to 60 MW; ITwiz describes it as IT power), including the two buildings already launchedThe first building is in service and the second (10 MW) launched in April 2026; both are excluded. This row covers the remaining capacity toward the 60 MW target. Data4 does not publish a separate MW figure for that remainder.Announced
Second data centre on the campus launched; Data4 says the campus will ultimately reach up to 60 MW and plans to raise its Polish investment to about EUR 600 million by 2030, April 2026Expected: Investment plan runs to 2030
Data4developer, April 2026
ITwiztrade press, September 2026Checked 10 Oct 2026
Atman Data Center WAW-3, buildings 2 and 3AtmanDuchnice, next to Ożarów Mazowiecki (west of Warsaw)43 MWtarget IT power of the full three building campusThe first building, with 14.4 MW of IT power, opened on 18 September 2025 and is excluded; this row covers the second and third buildings. No separate MW figure is published for those two buildings.Announced
First of three buildings opened; Atman says the second and third buildings will follow on a schedule tied to the pace of commercialisation, September 2025Expected: No date given; the schedule depends on commercialisation
Atmandeveloper, September 2025
Atmandeveloper, September 2026
Atmandeveloper, April 2024Checked 10 Oct 2026
Polcom Data Center 3 SkawinaPolcomSkawina (Kraków area)40 MWfacility capacity (up to 40 MW)Announced
Polcom announced Data Center 3 in Skawina, a facility of up to 40 MW with a budget of about PLN 150 million, September 2026Expected: Commissioning planned for 2030
Computerworld Polskatrade press, September 2026
ITwiztrade press, September 2026Checked 10 Oct 2026

How the tracker is built

Data-centre projects in the FLAP-D markets (Frankfurt, London, Amsterdam, Paris, Dublin) and the Nordic countries that are announced, in planning, permitted or under construction. One row per project or campus. Every row states the latest public milestone found and the source it comes from. Capacity is quoted as the source states it, with its basis (IT load, campus power, grid connection), so figures on different bases are never added together. Facts only: no ratings or rankings of operators or sites. Projects of 5 MW or more, or with no capacity published, with a public milestone since January 2024 that are not yet fully operational. Projects whose status is publicly disputed are held until a primary record settles it.

Announced
Plan published by the developer; no permit or construction start found.
In planning
Zoning, permit application or council process under way.
Permitted
Planning permission, a resolution to grant, or a site permitted for data-centre use.
Contractor appointed
Main works contract awarded; construction start not yet confirmed.
Under construction
Ground broken or preparatory works started.
Structure complete
Building structure complete (topped out); not yet in service.

Each row names the latest public milestone we found and links to where it was published: the developer's own release where one exists, otherwise the planning authority or the trade press that reported it. Projects under way are rechecked every month and announced projects every quarter; each row shows the date it was last checked, and a row that misses its recheck is marked as pending until it is checked again. To add a project or correct one, write to science.shot.page@gmail.com with a public source.

Cite as: ScienceShot, “European data centre project pipeline”, https://scienceshot.com/data-centre-pipeline (checked 2026-10-11). © ScienceShot. You may quote individual projects with a link to this page; each fact belongs to its cited source.