Data centres / Spain / Madrid

Data centre projects in Madrid

Pipeline projects2111 permitted or being builtChecked 10 Oct 2026
New grid connectionsRationedconcurso de acceso de demanda, in force since 17 Jul 2025. Spain-wide, transmissionChecked 12 Oct 2026
Wholesale power price67 €/MWhDay-ahead, 2025 mean, SpainLatest hour €239, 12 Oct 2026, 17:09 UTC
Grid carbon intensity84 g CO2e/kWhLatest hour, estimate; yearly average 15412 Oct 2026, 17:09 UTC
Next EU rule date14 Dec 2026The EU Commission's minimum performance standards consultation and call for evidence closesApplies EU-wide
Latency to nearest major hub11 msRound trip, Madrid to ParisMapped fibre route, minimum

As of 12 Oct 2026Cite as: ScienceShot, Madrid data-centre market scorecard, October 2026

These are the data-centre projects of 5 MW or more around Madrid that our pipeline tracker follows: 21 projects, 11 of them permitted or already being built. One national rule shapes new sites here: draft Royal Decree for sites above 1 MW, including hourly matching with additional renewable generation; consultation closed in early September 2026 (proposed).

Largest stated project240 MWApto Madrid campus Fuenlabrada, final campus power (5 data centres); basis not specified
Newest milestoneSep 2026latest check 10 Oct 2026

Projects by stage

  • Announced9
  • In planning1
  • Permitted2
  • Under construction8
  • Structure complete1

What the capacity figures measure

  • IT load4
  • Facility, campus or unstated basis9
  • First phase only3
  • No capacity published5

Each project’s capacity is quoted on its own stated basis, so the figures are never added together.

What changed

6 milestones in the last 90 days. The newest check was on 10 Oct 2026; each row below shows its own.

  1. Sep 2026ADC3 (Alcalá Data Center 3) construction of ADC3 started with a first stone ceremony; works awarded to Ferrovial; the project completes the expansion of the Alcalá de Henares campus Under construction
  2. Jul 2026Madrid Getafe (Phase I) phase I fully equipped and let; Getafe will start operating once electrical connections expected in Q4 2026 are completed Structure complete
  3. Jul 2026Apto Madrid campus Fuenlabrada site cleared and immediate construction phase started; IGNIS agreement signed in July 2026 to secure 82 MW grid access and connection with a 94 MW PV plant Under construction
  4. Jul 2026Madrid Getafe II developer reports works progressing at Madrid Getafe II after demolition and a construction licence request earlier in 2026 Under construction
  5. Jul 2026Madrid Tres Cantos developer reports works progressing at Madrid Tres Cantos after an urbanisation permit request in early 2026 Under construction

Projects

ProjectCapacityStage and latest milestoneChecked
Madrid Getafe (Phase I)Merlin Properties (operated by Edged)Getafe, Comunidad de MadridNot disclosedPhase I totals 64 MW IT across the Madrid, Barcelona and Basque Country data centres; no Getafe figure given. Nebius leased 18 MW at the Getafe campus (Sept 2026); phase not specified.Structure complete
Phase I fully equipped and let; Getafe will start operating once electrical connections expected in Q4 2026 are completed, Jul 2026Expected: Electrical connections expected Q4 2026
10 Oct 2026
Apto Madrid campus FuenlabradaApto (with Arnaiz; grid access by IGNIS)Fuenlabrada, Comunidad de Madrid240 MWfinal campus power (5 data centres); basis not specifiedSource also cites a 40 MW on site substation already enabled and a second phase of 122 MW. July 2026 IGNIS agreement covers 82 MW of grid access and connection capacity.Under construction
Site cleared and immediate construction phase started; IGNIS agreement signed in July 2026 to secure 82 MW grid access and connection with a 94 MW PV plant, Jul 2026
10 Oct 2026
ADC3 (Alcalá Data Center 3)NabiaxAlcalá de Henares, Comunidad de Madrid100 MWIT capacity, up to, deployed in phasesSource says up to 100 MW IT, deployed progressively until 2029. The same article says Nabiax will reach 135 MW of installed IT power in Spain.Under construction
Construction of ADC3 started with a first stone ceremony; works awarded to Ferrovial; the project completes the expansion of the Alcalá de Henares campus, Sep 2026Expected: Fully operational in phases through 2029
10 Oct 2026
Madrid campus MAD-2 to MAD-8 (remaining phases)Iron Mountain Data CentersSan Fernando de Henares, Comunidad de Madrid79 MWapproved IT capacity, full campusMAD-1 is operating with 3 MW per the developer page (2 MW first phase, Mar 2025). Remaining buildings per developer page: MAD-2 and MAD-3 at 10 MW each, MAD-4 and MAD-5 at 10 MW each, MAD-6 to MAD-8 at 12 MW each. Developer op ed (Jul 2025) refers to the remaining 76 MW. Delivery dates differ between sources: 2026 and 2027 in the Jul 2025 op ed, 2027 to 2030 on the developer page.Under construction
Developer reports accelerated construction of the remaining 76 MW of the Madrid campus, Jul 2025Expected: MAD-2 and MAD-3 in 2027; MAD-4 and MAD-5 in 2029; MAD-6 to MAD-8 in 2029 to 2030 (developer page)
10 Oct 2026
MAD02 campus (building DC02)Data4San Agustín del Guadalix, Comunidad de Madrid50 MWcampus power as listed by developer; basis not specifiedDeveloper page lists 50 MW for MAD02 on 6.7 hectares; DC02 building capacity not given.Under construction
Campus reported under construction; BREEAM Excellent design stage certification obtained for building DC02, Sep 2025
10 Oct 2026
Madrid Getafe IIMerlin Properties (operated by Edged)Getafe, Comunidad de Madrid48 MWas stated by developer for the second Getafe data centre; basis not specified (Phase II total of 254 MW is given as MW IT)Under construction
Developer reports works progressing at Madrid Getafe II after demolition and a construction licence request earlier in 2026, Jul 2026
10 Oct 2026
MAD01 Meco (Phase 1)Pure DCMeco, Comunidad de Madrid30 MWPhase 1 capacityTotal site capacity 70 MW; Phase 2 of 40 MW subject to permitting. Sale of the 18,000 m2 plot reported July 2024; the seller had secured a 25 MW electrical power contract in 2022.Under construction
Phase 1 fully permitted and under construction; developer lists a planning approval news item dated 26 November 2025, Nov 2025
10 Oct 2026
Madrid Tres CantosMerlin PropertiesTres Cantos, Comunidad de Madrid30 MWas stated by developer; basis not specified (Phase II total of 254 MW is given as MW IT)Under construction
Developer reports works progressing at Madrid Tres Cantos after an urbanisation permit request in early 2026, Jul 2026
10 Oct 2026
Quetta Tres CantosQuetta Data Centers (Azora and Core Tech Capital)Tres Cantos, Comunidad de Madrid20 MWplanned power, as reported from the companySource says planned power has doubled to 20 MW; earlier figure not stated.Under construction
Construction works started, Dec 2025
10 Oct 2026
Ferrovial data centre campus, MAD 01 first phaseFerrovialAvenida Monte de Valdelatas 10 16, Valdelacasa, Alcobendas60 MWfirst phase (MAD 01) powerTotal campus stated as more than 100 MW; investment 1,000 million euros.Permitted
Earthworks licence obtained and first phase declared a Proyecto de Especial Interés by the Comunidad de Madrid investment accelerator, Jul 2026
10 Oct 2026
ACS data centre site Alcalá de HenaresACSAlcalá de Henares, Comunidad de MadridNot disclosedPart of a 12,000 million euro programme across Alcalá de Henares, Madrid municipality and Zaragoza.Permitted
Land reported to have all permits and grid access for data centre development, Jan 2025Expected: Investment over the next 5 to 7 years (programme)
10 Oct 2026
Ignis Data Beta IIIgnisVillalbilla, Comunidad de Madrid181 MWdata centre capacity as stated; basis not specifiedLinked to seven solar parks and a planned 220 kV substation (SET Beta II).In planning
Project completed the public information stage before Madrid authorities, Feb 2026
10 Oct 2026
Madrid SurEchelon Data Centres and Iberdrola joint venture (Echelon Iberdrola Digital Infra)South of Madrid (municipality not stated)144 MWinitial operational capacitySecured grid connection of 230 MW on a 160,000 m² site.Announced
Iberdrola confirmed the joint venture with Echelon, with Madrid Sur as its first project; the JV starts activity once regulatory approvals are obtained, Nov 2025Expected: Operational before 2030
10 Oct 2026
Edgnex Madrid data centreEdgnex (DAMAC Group)Madrid region, about 15 km from the city centre (municipality not stated)40 MWelectricity supply rights (10 MW immediate, 30 MW additional for Q1 2026)Announced
Plot of almost 23,000 m2 with ratified 40 MW power supply rights bought from ASG Iberia; investment of more than 400 million euros planned, Oct 2024
10 Oct 2026
Madrid Campus MAD01Prime Data CentersCalle de la Pedriza 1, Alcobendas40 MWcritical power (critical IT load)Announced
Plans announced after securing 7.6 acres; site page lists MAD01-01 as in development, May 2024
10 Oct 2026
Nostrum GuadalajaraNostrum Data Centers (Nostrum Group)Polígono El Ruiseñor, Guadalajara (Castilla La Mancha)40 MWelectrical power already granted (allows up to 29 MW IT)Marketed as a few kilometres from Madrid and the Corredor del Henares.Announced
About 2 hectares secured and 40 MW power granted; project presented to municipal authorities; design by IDOM, Feb 2026Expected: Works start planned for end of 2026; operation in 2028
10 Oct 2026
Templus Alcalá de Henares expansionTemplusAlcalá de Henares, Comunidad de Madrid20 MWtarget site power after expansion (10 MW current)The operating 16,000 m2 site houses two symmetrical data centres and has 10 MW today; the row covers the planned increase to 20 MW.Announced
Plan announced to double the site from 10 MW to 20 MW in the medium term, Sep 2025Expected: Medium term (no date given)
10 Oct 2026
Vaultica Madrid (Los Salobrales)Vaultica Data CentersPolígono Los Salobrales, Alcalá de Henares12 MWinstalled IT capacity, up toAnnounced
New data centre announced within an existing industrial complex, with two grid connections from two substations, Apr 2026
10 Oct 2026
Digital Realty new Madrid data centre (Julián Camarillo)Digital Realty (Interxion)Polígono Julián Camarillo, San Blas Canillejas, MadridNot disclosedSource gives a range of 20 to 40 MW for the planned centre.Announced
Fifth plot acquired in the Julián Camarillo area for a new data centre, Apr 2025
10 Oct 2026
Nostrum PintoNostrum Data Centers (Nostrum Group)Pinto, Comunidad de MadridNot disclosedSix site programme totals 500 MW IT plus 300 MW for future expansion; no Pinto figure.Announced
Pinto named among six planned sites, all with land and power secured, Jan 2026Expected: Operational during 2027 (programme target)
10 Oct 2026
Spanish AI gigafactory bid (Madrid site)Public private consortium with SETT (Sociedad Española para la Transformación Tecnológica)San Fernando de Henares, Comunidad de MadridNot disclosedMulti site bid with Móra la Nova (Tarragona); outcome depends on the EU InvestAI call.Announced
Council of Ministers authorised the state investment for the bid, Jun 2026
10 Oct 2026

Formal refusals and bans since 2025

Verified decisions only. Absence is not evidence of low planning risk.

Decisions on single sites

  1. 11 Feb 2026Madrid Grid access refused at two local substationsOverturned by the energy regulator, Jun 2026; new capacity studies ordered
  2. 7 Apr 2025Meco, near Madrid Grid access refused at the local substationUpheld by the energy regulator, Feb 2026

Decisions from 1 Jan 2025; statuses checked 11 Oct 2026.

Power and grid in Spain

The latest hour, ES bidding zone

Grid carbon intensity (estimate)84 g CO2e/kWhsame hour yesterday 80
Day-ahead price239 €/MWhwholesale, not what a site pays
Renewable share of generation67 %
Best four hours for flexible load13:00Tue 13 Oct to 17:00, local time

Updated 12 Oct 2026, 17:09 UTC; refreshed every 10 minutes. Spain grid hour by hour, next 48 hours

Over a year, country level

Grid carbon, latest full-year average154 g CO2/kWh13th cleanest of 30 countries; 75% renewable or nuclear
Business electricity price, latest full year126 €/MWh8th cheapest of 26; wholesale is 71% of it
Wholesale power, 2025 average67 €/MWh5th cheapest of 30

Annual country averages, as used by the siting cost ranking. Production-based average carbon, not marginal.

Climate at Madrid

Hours a year above 27 °C dry-bulb1,117 hmean of 2016 to 2025
Hours a year above 32 °C dry-bulb441 hworst year 508 h
Hours a year above 20 °C wet-bulb63 hlimit for evaporative cooling

Hourly climate reanalysis at the city’s grid cell, from the market comparison; a site’s own conditions differ.

Fibre latency from Madrid

ToRound trip, minimumPath lengthPath
Lisbon5.2 ms536 kmMapped fibre route
Marseille10 ms1,052 kmMapped fibre route
Paris11 ms1,149 kmMapped fibre route
London12 ms1,263 kmStraight line (no mapped land route)
Dublin14 ms1,451 kmStraight line (no mapped land route)
Milan15 ms1,480 kmMapped fibre route
Amsterdam16 ms1,600 kmMapped fibre route
Frankfurt17 ms1,712 kmMapped fibre route

Light in single-mode fibre between city centres, over the mapped land fibre route where one exists, otherwise the straight line. Operator routes, equipment and the last kilometres add to these floors. Any pair in the latency calculator

Rules and dates

WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
SpainDraft Royal Decree for sites above 1 MW, including hourly matching with additional renewable generation; consultation closed in early September 2026Proposed

Next dates

  1. 14 Dec 2026the EU Commission's minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due every year

From the European data-centre regulation tracker and the market comparison.

Method

The pipeline covers data-centre projects of 5 MW or more, or with no capacity published, that are announced, in planning, permitted or under construction and not yet fully operating. It is not a list of operating facilities. A metro market follows the tracker’s own market field, so it includes the region around the city; a country page covers every tracked project in the country.

  • Projects: each row is the latest public milestone we found for the project, with the date it was last checked; the pipeline tracker holds every project.
  • Latest hour: carbon intensity estimated from the hourly generation mix, with the day-ahead price, refreshed every 10 minutes on the live grid page.
  • Over a year: national averages for the latest full year, the same figures the siting cost ranking uses.
  • Climate: hourly reanalysis at the city’s grid cell, 2016 to 2025.
  • Latency: light in fibre between city centres over the mapped land route, otherwise the straight line.

Cite as: ScienceShot, “Data centre projects around Madrid”, https://scienceshot.com/data-centres/madrid/ (checked 10 Oct 2026). © ScienceShot. You may quote individual facts with a link to this page.

ScienceShot dataset, checked 12 Oct 2026. How we build it: Method and standards.