Data centres / Operators / Merlin Properties

Merlin Properties data centre projects in Europe

Projects tracked9of 5 MW or more
Permitted or being built7none at announcement stage
Countries2with at least one project
Milestones, last 90 days8newest Jul 2026

As of 10 Oct 2026 (newest check)Cite as: ScienceShot, Merlin Properties data-centre pipeline summary, October 2026

Our European pipeline tracker follows 9 data-centre projects of 5 MW or more that Merlin Properties develops or co-develops, in 2 countries; 7 are permitted or already being built. The largest share is in Spain, with 7 projects.

78% are permitted or being built, against 43% across the whole tracker, so the pipeline is further along than the European average. The milestones we hold run from Feb 2026 to Jul 2026.

Projects by stage

  • In planning2
  • Under construction6
  • Structure complete1

What the capacity figures measure

  • IT load3
  • Facility, campus or unstated basis4
  • No capacity published2

Stated size, where a figure is published

  • 20 to 49 MW4
  • 50 to 99 MW1
  • 100 to 249 MW2

2 projects have no published capacity and are not in a band. Bands mix the bases above (a grid connection is larger than the IT load it serves), so read them as orders of size. Capacities are counted, never added together.

Where Merlin Properties is building

Projects by country, with the metro markets inside each country. Each name opens the market page.

Latest milestones

The newest 5 steps we recorded, with the market and the stage the project reached. Project names stay in our dataset.

  1. Jul 2026Spain Fully let twelve months before deliveryUnder construction
  2. Jul 2026Spain Construction licence requestedIn planning
  3. Jul 2026Spain Aragón government approved the DIGA (declaration of investment of regional interest) for the campusIn planning
  4. Jul 2026Madrid Structure complete
  5. Jul 2026Madrid Under construction
Method

The pipeline covers data-centre projects of 5 MW or more, or with no capacity published, that are announced, in planning, permitted or under construction and not yet fully operating. It is not a list of operating facilities, and it holds the projects we have found and checked, not every project a company has.

  • We count the projects Merlin Properties develops or co-develops; a joint venture counts once for each partner. Tenancies, land ownership, construction contracts and financing are not counted.
  • Markets follow the tracker: a metro market includes the region around the city, and a national market covers the rest of the country.
  • Stated capacities use different bases, so projects are counted by basis and in size bands and the figures are never added together.
  • ScienceShot is independent of Merlin Properties. The figures come from public filings and announcements, not from the company.
  • This page shows aggregates. The pipeline tracker and the market pages hold the wider picture.

Cite as: ScienceShot, “Merlin Properties data centre projects in Europe”, https://scienceshot.com/data-centres/operators/merlin-properties (checked 10 Oct 2026). © ScienceShot. You may quote individual facts with a link to this page.

ScienceShot calculation. How we build it: Method and standards.