Data centres / United Kingdom / London

Data centre projects in London

Pipeline projects3723 permitted or being builtChecked 11 Oct 2026
New grid connectionsPausedpaused to new connection applications, in force since 30 Jun 2025. United Kingdom-wide, transmissionChecked 12 Oct 2026
Wholesale power price94 €/MWhDay-ahead, 2025 mean, United KingdomLatest hour €164, 12 Oct 2026, 21:29 UTC
Grid carbon intensity104 g CO2e/kWhLatest hour, estimate; yearly average 21712 Oct 2026, 21:29 UTC
Latency to nearest major hub3.4 msRound trip, London to ParisStraight line, minimum

As of 12 Oct 2026Cite as: ScienceShot, London data-centre market scorecard, October 2026

These are the data-centre projects of 5 MW or more around London that our pipeline tracker follows: 37 projects, 23 of them permitted or already being built. Of these, 4 are under construction, and 4 are still at the announcement stage.

Largest stated project300 MWEbbsfleet AI Data Centre Campus, campus capacity as reported; basis not stated
Newest milestoneSep 2026latest check 11 Oct 2026

Projects by stage

  • Announced4
  • In planning10
  • Permitted18
  • Contractor appointed1
  • Under construction4

What the capacity figures measure

  • IT load10
  • Facility, campus or unstated basis17
  • No capacity published10

Each project’s capacity is quoted on its own stated basis, so the figures are never added together.

What changed

11 milestones in the last 90 days. The newest check was on 11 Oct 2026; each row below shows its own.

  1. Sep 2026Pure DC LON01, Brent Cross piling started on LON01B2, the campus's final build phase Under construction
  2. Sep 2026Microsoft Langley datacentre site with outline datacentre permission being cleared; community information sessions held July and September 2026 Permitted
  3. Sep 2026Thames Valley Park data centre outline application (ref 262274) validated by Wokingham Borough Council; consultation to 29 October 2026 In planning
  4. Aug 2026Heathrow Estate data centre approved by Hounslow Council Permitted
  5. Aug 2026Charlton Riverside data centre request filed with the Royal Borough of Greenwich asking whether a full Environmental Impact Assessment is needed; full application expected later In planning

Projects

ProjectCapacityStage and latest milestoneChecked
Ada Infrastructure Docklands campusAda Infrastructure (GLP Capital Partners)Royal Docks, London Borough of Newham210 MWcampus, three 70 MW buildingsUnder construction
Construction of the first of three 70 MW buildings began, Mar 2026
11 Oct 2026
Pure DC LON01, Brent CrossPure DCBrent Cross, north London90 MWcampus totalFinal building LON01B2 is 70 MWUnder construction
Piling started on LON01B2, the campus's final build phase, Sep 2026Expected: Q2 2029
10 Oct 2026
Telehouse West TwoTelehouse (KDDI)Telehouse London Docklands campus33 MWoverall building capacityUnder construction
Ground broken on the nine-storey building, Oct 2025Expected: set for completion in 2028
10 Oct 2026
Kao Data KLON-03Kao DataKao Data Harlow campus, Harlow18 MWcapacity of the new data centre (developer)A June 2026 customer agreement is stated as 22MW at the Harlow campus, to be hosted in KLON-03; the developer states the new data centre as 17.6MWUnder construction
Construction of KLON-03 announced (March 2025); a 10-year, 22MW customer agreement for the Harlow campus announced in June 2026, Jun 2026Expected: Ready for service in 2026 (developer, stated in March 2025 as "next year")
11 Oct 2026
Corscale Court Lane data centre campusCorscaleCourt Lane, Iver, Buckinghamshire140 MWcampus capacity across two buildings, as reported by the contractor and reportsDedicated 140MVA substation; Corscale's own website lists the Court Lane campus at 103 MW power capacityContractor appointed
McLaren Construction appointed with Phoenix ME under a pre-construction services agreement; predevelopment enabling works scheduled from 1 July 2026, Jun 2026Expected: Once complete in late 2029
10 Oct 2026
Equinix Hertfordshire campusEquinixSouth Mimms, Hertsmere (85-acre site)250 MWcompute capacity (250+ MW)Permitted
Site acquired; plot permitted for data-centre development, Oct 2025
10 Oct 2026
Google North Weald Airfield data centreGoogleNorth Weald Airfield, Epping Forest District, Essex163 MWestimated power requirement of the siteSource text reads "163MWW", read as MWPermitted
Outline planning application approved by Epping Forest District Council planning committee, Dec 2025
10 Oct 2026
Manor Farm data centreTritax Big Box REIT (Manor Farm Propco Limited)Land at Manor Farm and land north of Wraysbury Reservoir, Poyle Road, Slough107 MWfacility capacity as stated by the developer; measure not definedPermitted
Planning consent secured after the six-week judicial review concluded; pre-let agreement in solicitors' hands, Jul 2026
10 Oct 2026
Colt DCS Hayes Digital Park, London 6 to 8Colt DCSHayes, London Borough of Hillingdon97 MWIT capacity, three new buildingsCampus total 160 MW after expansionPermitted
Approved by Hillingdon Council, Nov 2025Expected: Construction from mid-2026, first building early 2029
10 Oct 2026
Abbots Langley hyperscale data centreGreystoke LandLand off Bedmond Road, Abbots Langley, Three Rivers, Hertfordshire96 MWdevelopment capacity as reported84,000 sq m hyperscale campusPermitted
Planning permission granted on appeal by the Secretary of State, overturning Three Rivers District Council's refusal, May 2025
10 Oct 2026
Virtus Saunderton campusVirtus Data CentresSaunderton, near High Wycombe, Buckinghamshire78 MWIT load across four data centresA February 2024 report gave 75 MW for the four data centres and a National Grid contract for 120 MVAPermitted
Campus plan announced on an approved planning site, with building works due to start Q4 2024, Feb 2024Expected: ready for service by the second quarter of 2026 (as stated in February 2024)
10 Oct 2026
Premier Park data centrePure Data Centres and SEGRO (joint venture)Park Royal, west London72 MWpower capacityPermitted
Planning permission issued on 3 July 2026 after the S106 agreement was completed (committee resolved to grant on 26 February 2026), Jul 2026Expected: Construction expected to start in 2026
11 Oct 2026
Nscale Loughton AI data centreNscaleLoughton, Epping Forest District, Essex50 MWAI compute capacityExpandable to 90MW; one report cites a revised proposal 50% larger than originally proposed, with no MW figure givenPermitted
Outline approval granted in 2024; after Nscale revised the plans, Loughton Town Council planning officers asked for a new planning application, with Epping Forest District Council holding the decision, Mar 2026Expected: construction start in Q2 2026 and operation in Q2 2027 (Nscale spokesperson, March 2026)
10 Oct 2026
Heathrow Estate data centreBrixton (Heathrow Estate) Ltd; operator not yet namedCranford, London Borough of Hounslow48 MWIT load (64 MW power requirement)Up to three buildings; a future operator brings the detailed scheme through reserved mattersPermitted
Approved by Hounslow Council, Aug 2026
10 Oct 2026
Global Switch London South data centreGlobal SwitchDocklands, London (Global Switch London campus)40 MWIT power capacityCampus utility supply of 126MVA is quoted separately by the developerPermitted
Full planning approval received for a new five-floor, 27,000 sq m building, Feb 2024
11 Oct 2026
Ark Longcross Park LP02Ark Data CentresLongcross Park, Runnymede, Surrey36 MWnew LP02 data centre buildingApproval also covers vertical extensions to existing buildings; row covers the LP02 expansion onlyPermitted
Planning approval for LP02 and expansion of existing buildings, with a GBP 807 million investment announced, Jun 2026
10 Oct 2026
Foxboro Business Park data centreCastleforge and Galaxy Data Centers (joint venture)Foxboro Business Park, Redhill, Reigate and Banstead, Surrey15 MWdata centre capacityPermitted
Full planning consent granted by Reigate and Banstead Borough Council planning committee, May 2026
10 Oct 2026
45 Maylands Avenue data centreNorthtree Investment Management45 Maylands Avenue, Hemel Hempstead, Dacorum, Hertfordshire5 MWper data hall (two halls planned)Up to 5,100 sqmPermitted
Outline planning permission granted for redevelopment of a self storage site into a data centre, Aug 2025
10 Oct 2026
Caineal Wickford AI data centreCainealNear the A127 and Old Nevendon Road, Wickford, Basildon, EssexNot disclosedReported investment GBP 1.3bnPermitted
Planning approval by Basildon Council Planning Committee; construction to start once final formalities are completed, Sep 2025
10 Oct 2026
CyrusOne Southall campus (former Honey Monster factory)CyrusOneBridge Road, Southall, London Borough of EalingNot disclosedMore than 52,000 sqm of floorspace across four storeysPermitted
Approved by Ealing Council planning committee on 17 July 2026, Jul 2026Expected: Works could start at the beginning of 2027; campus opening hoped for by 2030
10 Oct 2026
Equinix Wexham Road campus (former AkzoNobel paint factory)EquinixOff Wexham Road, SloughNot disclosedThree buildings; a detailed application is still requiredPermitted
Outline planning permission for a three building data centre campus approved by Slough Borough Council planning committee, Nov 2025
10 Oct 2026
Microsoft Langley datacentreMicrosoftLangley, SloughNot disclosedSite received outline planning permission for a datacentre in 2020Permitted
Site with outline datacentre permission being cleared; community information sessions held July and September 2026, Sep 2026
10 Oct 2026
SEGRO Slough Trading Estate powered shell data centreSEGROSlough Trading Estate, SloughNot disclosedSource gives 50MVA of power when fully operational (MVA, not MW)Permitted
Pre-let agreed with an existing customer for a 30,000 sq m powered shell; planning in place via the Simplified Planning Zone, Mar 2026
10 Oct 2026
Ebbsfleet AI Data Centre CampusClearstone (applicant CSE52 Limited)Land adjacent to New Barn Road, Dartford, Kent300 MWcampus capacity as reported; basis not statedPower to come through a National Grid transmission connectionIn planning
Section 35 direction issued so the campus is treated as a Nationally Significant Infrastructure Project requiring a Development Consent Order, Jul 2026Expected: targeting an operational start date of 2030
10 Oct 2026
SDC M40 CampusSlough Holdings UK LimitedBetween the A40 Oxford Road and the M40, about 2km west of Gerrards Cross, Buckinghamshire (Planning Inspectorate project EN0110030)300 MWIT load across three buildings (c.100MW each)On-site energy centre maximum generating capacity approximately 250 to 350MWIn planning
Planning Inspectorate published a Scoping Opinion; project at pre-application stage of the Development Consent Order process, Jun 2026Expected: The application is expected to be submitted January 2027
10 Oct 2026
Charlton Riverside data centreGreater London Industrial (GLi), joint venture of Patrizia and Kingston Space PropertyLand off Anchor and Hope Lane, Charlton Riverside, Royal Borough of Greenwich180 MWdevelopment total as reportedOne report gives 100,000 sqm for the centreIn planning
Request filed with the Royal Borough of Greenwich asking whether a full Environmental Impact Assessment is needed; full application expected later, Aug 2026Expected: Work could start in 2028 and be finished by 2033
10 Oct 2026
Project Blackwater data centre campusTritax Big Box REITBeaulieu Parkway, Beaulieu Park, Chelmsford, Essex125 MWcampus total as reportedSame source says each of the two buildings would offer 44MW; figures not reconciled in the sourceIn planning
Planning application for a two-building campus submitted; Tritax Management appointed to provide development management and technical services, Jun 2026
10 Oct 2026
Thames Valley Park data centreFH Trustees Limited and FH Trustees 2 Limited (Mapeley Beta HL Unit Trust)Thames Valley Park, Earley, Wokingham Borough, Berkshire72 MWIT capacityPeak demand about 110MW; application documents give 49.9MW and 42.5MW for the initial fuel cell supplyIn planning
Outline application (ref 262274) validated by Wokingham Borough Council; consultation to 29 October 2026, Sep 2026Expected: demolition April to October 2027; main construction February 2028 to August 2031 (per application documents)
10 Oct 2026
Bromley green belt data centreDare DCBetween Cudham Lane North and Charmwood Lane, London Borough of Bromley50 MWdata centre capacity as reportedTwo-building campus on a ten-hectare siteIn planning
EIA screening opinion request submitted to Bromley Council; no full planning application yet, Jul 2026Expected: grid connection hoped for 2028
10 Oct 2026
Amazon tape data centre, Hemel HempsteadAmazonHemel Hempstead, Dacorum, HertfordshireNot disclosedEstimated footprint of 1,935 sqmIn planning
Planning application lodged with Dacorum Borough Council, Feb 2026Expected: decision likely later in 2026
10 Oct 2026
Arena Essex data centre campusApplicant not named in the council noticeArena Essex and Fishing Lake, Arterial Road, Purfleet-on-Thames, ThurrockNot disclosedOutline element covers up to four data centre buildings with a total GEA of up to 130,500 sqmIn planning
Hybrid planning application 25/00573/OUT advertised by Thurrock Council, Jul 2025
10 Oct 2026
Denham data centre campusMulberry Commercial Developments IILand either side of Denham Court Drive, Denham, BuckinghamshireNot disclosed60,000 sqm (645,835 sq ft)In planning
Planning application submitted to Buckinghamshire Council on 1 June 2026; Denham Parish Council objected and asked for a call-in to committee, Jun 2026
10 Oct 2026
East Havering Data Centre CampusDigital ReefNorth Ockendon, London Borough of HaveringNot disclosedOne report cites a 600MVA connection via the Warley substationIn planning
Formal consultation on the East Havering Datacentre Local Development Order closed; revised plan reported as due in autumn 2026, Apr 2026
10 Oct 2026
Ark Elstree campus (former Mercure Hotel)Ark Data CentresFormer Mercure Hotel site, Watford (Ark's Elstree campus), Hertsmere Borough, Hertfordshire200 MWsite capacity as reportedUp to six data centre buildings reportedAnnounced
Public consultation launched ahead of a planning application to Hertsmere Borough Council, Nov 2025Expected: Construction could start in 2026, with the first building launching in 2029
10 Oct 2026
CyrusOne LON6CyrusOneIver Heath, Buckinghamshire90 MWIT capacityAnnounced
Plans announced for a new campus; groundbreaking targeted for Q3 2026, Jun 2025Expected: Groundbreaking Q3 2026; first capacity early 2028
10 Oct 2026
VIRTUS LONDON19Virtus Data CentresSlough Trading Estate, Slough33 MWIT loadAnnounced
Development of LONDON19 announced on the Slough campus, Jul 2026
10 Oct 2026
Kao Data Park Royal campusKao DataFormer Frogmore Industrial Estate, Park Royal, west LondonNot disclosed4.7-acre siteAnnounced
Site acquired; planning proposals to be submitted over the coming months, May 2026Expected: ready for service in 2029
10 Oct 2026

Formal refusals and bans since 2025

Verified decisions only. Absence is not evidence of low planning risk.

No formal refusal or ban recorded for London in this register. The register covers decisions we have verified, not every decision taken.

Decisions from 1 Jan 2025; statuses checked 11 Oct 2026.

Power and grid in the United Kingdom

The latest hour, GB bidding zone

Grid carbon intensity (estimate)104 g CO2e/kWh
Day-ahead price164 €/MWhwholesale, not what a site pays
Renewable share of generation60 %
Best four hours for flexible load11:00Tue 13 Oct to 15:00, local time

Updated 12 Oct 2026, 21:29 UTC; refreshed every 10 minutes. United Kingdom grid hour by hour, next 48 hours

Over a year, country level

Grid carbon, latest full-year average217 g CO2/kWh17th cleanest of 30 countries; 64% renewable or nuclear
Wholesale power, 2025 average94 €/MWh14th cheapest of 30

Annual country averages, as used by the siting cost ranking. Production-based average carbon, not marginal.

Climate at London

Hours a year above 27 °C dry-bulb61 hmean of 2016 to 2025
Hours a year above 32 °C dry-bulb4 hworst year 17 h
Hours a year above 20 °C wet-bulb45 hlimit for evaporative cooling

Hourly climate reanalysis at the city’s grid cell, from the market comparison; a site’s own conditions differ.

Fibre latency from London

ToRound trip, minimumPath lengthPath
Brussels3.1 ms321 kmStraight line (no mapped land route)
Paris3.4 ms344 kmStraight line (no mapped land route)
Amsterdam3.5 ms356 kmStraight line (no mapped land route)
Dublin4.5 ms463 kmStraight line (no mapped land route)
Frankfurt6.2 ms638 kmStraight line (no mapped land route)
Zurich7.6 ms776 kmStraight line (no mapped land route)
Munich9.0 ms918 kmStraight line (no mapped land route)

Light in single-mode fibre between city centres, over the mapped land fibre route where one exists, otherwise the straight line. Operator routes, equipment and the last kilometres add to these floors. Any pair in the latency calculator

Method

The pipeline covers data-centre projects of 5 MW or more, or with no capacity published, that are announced, in planning, permitted or under construction and not yet fully operating. It is not a list of operating facilities. A metro market follows the tracker’s own market field, so it includes the region around the city; a country page covers every tracked project in the country.

  • Projects: each row is the latest public milestone we found for the project, with the date it was last checked; the pipeline tracker holds every project.
  • Latest hour: carbon intensity estimated from the hourly generation mix, with the day-ahead price, refreshed every 10 minutes on the live grid page.
  • Over a year: national averages for the latest full year, the same figures the siting cost ranking uses.
  • Climate: hourly reanalysis at the city’s grid cell, 2016 to 2025.
  • Latency: light in fibre between city centres over the mapped land route, otherwise the straight line.

Cite as: ScienceShot, “Data centre projects around London”, https://scienceshot.com/data-centres/london/ (checked 11 Oct 2026). © ScienceShot. You may quote individual facts with a link to this page.

ScienceShot dataset, checked 12 Oct 2026. How we build it: Method and standards.