Grid connection

Grid connection for data centres in Norway

Checked 11 October 2026: new transmission connections for large loads in parts of Norway are closed to new applications (operator’s term: midlertidig stopp i reservasjoner til fremtidig stort industriforbruk, in force since 22 April 2026). 4.2 GW of data-centre demand is reserved on the grid (October 2026).

1 rule in forceChecked 11 Oct 2026

Rules on new connections in Norway

Every rule in force that pauses, rations or conditions new connections, whole country first.

WhereVoltageWhoStatusOperator’s termSince
Norway in partsTransmissionLarge loadsPausedmidlertidig stopp i reservasjoner til fremtidig stort industriforbruk22 Apr 2026Filed, checked 11 Oct 2026

Wait and demand

As published, with the month each figure refers to. Power in MVA is read as MW.

  • 4.2 GW of data-centre demand is reserved on the grid (October 2026). Filed, checked 11 Oct 2026

Next date

  1. 10 Nov 2026No rule here has a future date on record. Our next check of Norway is due by this date.

Questions

Can a new data centre get a grid connection in Norway now?

New transmission connections for large loads in parts of Norway are closed to new applications (operator’s term: midlertidig stopp i reservasjoner til fremtidig stort industriforbruk, in force since 22 April 2026).

More on Norway

From the European grid connection tracker: rules and figures as the system operators and regulators publish them, each checked against the publication. Last check 11 October 2026.

Sources, checked 11 October 2026: Elvia, Statnett.