Grid connection

Grid connection for data centres in Spain

Checked 11 October 2026: new transmission connections in parts of Spain are allocated in limited rounds (operator’s term: concurso de acceso de demanda, in force since 17 July 2025). 6.3 GW of data-centre demand has been granted grid access (October 2026).

2 rules in forceChecked 11 Oct 2026

Rules on new connections in Spain

Every rule in force that pauses, rations or conditions new connections, whole country first.

WhereVoltageWhoStatusOperator’s termSince
Spain in partsTransmissionAll customersRationedconcurso de acceso de demanda17 Jul 2025Filed, checked 11 Oct 2026
Madrid in partsTransmissionAll customersRationednudos susceptibles de convocatoria de concurso15 Sep 2026Filed, checked 11 Oct 2026

Wait and demand

As published, with the month each figure refers to. Power in MVA is read as MW.

  • 6.3 GW of data-centre demand has been granted grid access (October 2026). Filed, checked 11 Oct 2026

Next date

  1. 10 Nov 2026No rule here has a future date on record. Our next check of Spain is due by this date.

Questions

Can a new data centre get a grid connection in Spain now?

New transmission connections in parts of Spain are allocated in limited rounds (operator’s term: concurso de acceso de demanda, in force since 17 July 2025). 1 more rule applies at other voltages or places; each is listed on this page.

More on Spain

From the European grid connection tracker: rules and figures as the system operators and regulators publish them, each checked against the publication. Last check 11 October 2026.

Sources, checked 11 October 2026: BOE (Spanish official gazette), MITECO, Red Eléctrica.