Data centres / Operators / Vantage Data Centers

Vantage Data Centers data centre projects in Europe

Projects tracked9of 5 MW or more
Permitted or being built33 at announcement stage
Countries7with at least one project
Milestones, last 90 days2newest Oct 2026

As of 12 Oct 2026 (newest check)Cite as: ScienceShot, Vantage Data Centers data-centre pipeline summary, October 2026

Our European pipeline tracker follows 9 data-centre projects of 5 MW or more that Vantage Data Centers develops or co-develops, in 7 countries; 3 are permitted or already being built. The largest share is in Italy, with 2 projects.

33% are permitted or being built, against 43% across the whole tracker, so the pipeline is earlier-stage than the European average. The milestones we hold run from Apr 2024 to Oct 2026.

Projects by stage

  • Announced3
  • In planning3
  • Permitted2
  • Under construction1

What the capacity figures measure

  • IT load4
  • Facility, campus or unstated basis2
  • Grid connection2
  • No capacity published1

Stated size, where a figure is published

  • 20 to 49 MW2
  • 50 to 99 MW2
  • 100 to 249 MW2
  • 250 MW and above2

1 project has no published capacity and is not in a band. Bands mix the bases above (a grid connection is larger than the IT load it serves), so read them as orders of size. Capacities are counted, never added together.

Where Vantage Data Centers is building

Projects by country, with the metro markets inside each country. Each name opens the market page.

Latest milestones

The newest 5 steps we recorded, with the market and the stage the project reached. Project names stay in our dataset.

  1. Oct 2026Spain Campus at DIGA stage in the Aragón regional approval processIn planning
  2. Jul 2026Dublin Under construction
  3. Feb 2026France Announced
  4. Dec 2025Frankfurt Fifth amendment of the Im Schleid development plan scheduled for a city council vote on 16 December 2025In planning
  5. Oct 2025United Kingdom Permitted
Method

The pipeline covers data-centre projects of 5 MW or more, or with no capacity published, that are announced, in planning, permitted or under construction and not yet fully operating. It is not a list of operating facilities, and it holds the projects we have found and checked, not every project a company has.

  • We count the projects Vantage Data Centers develops or co-develops; a joint venture counts once for each partner. Tenancies, land ownership, construction contracts and financing are not counted.
  • Markets follow the tracker: a metro market includes the region around the city, and a national market covers the rest of the country.
  • Stated capacities use different bases, so projects are counted by basis and in size bands and the figures are never added together.
  • ScienceShot is independent of Vantage Data Centers. The figures come from public filings and announcements, not from the company.
  • This page shows aggregates. The pipeline tracker and the market pages hold the wider picture.

Cite as: ScienceShot, “Vantage Data Centers data centre projects in Europe”, https://scienceshot.com/data-centres/operators/vantage (checked 12 Oct 2026). © ScienceShot. You may quote individual facts with a link to this page.

ScienceShot calculation. How we build it: Method and standards.